First Notice | 9/24/2010 | 9/24/2010 | 10/8/2010 | | DONE |
Tony Young
|
|
|
|
BLD-Final | 9/22/2010 | 9/23/2010 | 9/24/2010 | A | DONE |
Tony Young
|
|
|
David; Phone #: ###-####,,
|
DOC - Permit Finaled | 9/24/2010 | 9/24/2010 | 9/24/2010 | P | PASS |
Tony Young
|
|
|
DONE
|
BLD-Aging Inspection | 9/21/2010 | 9/21/2010 | 9/23/2010 | | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/16/2010 | 7/19/2010 | 7/19/2010 | A | PASS |
Tony Young
|
|
|
david Phone #: ###-####,, soil machine room ok
|
BLD-Footing | 7/16/2010 | 7/16/2010 | 7/16/2010 | P | PART |
Tony Young
|
|
|
david Phone #: ###-####,, footings for 60 x 26 dirt warehouse ok
|
BLD-Aging Inspection | 6/22/2010 | 6/22/2010 | 6/22/2010 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/21/2010 | 4/21/2010 | 4/22/2010 | | PASS |
Tony Young
|
|
|
|
BLD-Conference | 10/2/2009 | 10/2/2009 | 10/2/2009 | P | PASS |
Tony Young
|
|
|
DAVID Phone #: ###-#### ok to keep active
|
BLD-Conference | 4/8/2009 | 4/10/2009 | 4/10/2009 | P | PASS |
Tony Young
|
|
|
David Phone #: ###-#### ok to keep active
|
BLD-Framing/Rough-in | 10/20/2008 | 10/21/2008 | 10/21/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/20/2008 at 11:17:17 AM. Contact: ###-####.
|
BLD-Other | 5/14/2008 | 5/15/2008 | 5/15/2008 | P | PASS |
Mike Jordan
|
|
|
david Note: stem wall - please call 1/2 hr prior to inspection to meet with Phone #: ###-####. PERIMETER STEMWALLS OK.
|
BLD-Conference | 11/21/2007 | 11/21/2007 | 11/21/2007 | P | PASS |
Tony Young
|
|
|
David Phone #: ###-####
ftgs for work shop wip ok
|
BLD-Footing | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/31/2007 at 2:53:59 PM.
|
BLD - Request for Extension | 6/1/2007 | 6/1/2007 | 6/1/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/31/2007 at 2:53:59 PM. ok to extend
|
BLD-Conference | 11/30/2006 | 11/30/2006 | 11/30/2006 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/30/2006 at 9:19:56 AM. 2nd set of holes ok
|
BLD-Concrete | 11/15/2006 | 11/15/2006 | 11/15/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/15/2006 at 8:38:54 AM. Contact: ###-####. holes for posts ok
|
BLD-Footing | 10/19/2006 | 10/20/2006 | 10/20/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/19/2006 at 12:40:51 PM. Contact: ###-####. WIP on post holes.. will recall when ready with rebar in place
|
Issue PAID IN FULL permit | | | 9/27/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/20/2006 | | DONE |
|
|
|
talked to art albanese at ###-#### that 3 permits are ready & need achd approval
|
Telephone call | | | 8/30/2006 | | DONE |
|
|
|
Left voice message for Art that permits are ready & fees///8/30/06 @2:25pm BAS
|
Permit Ready to Issue | | | 8/30/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/29/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/18/2006 | | 8/28/2006 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 7/25/2006 | | 8/28/2006 | | PASS |
|
|
|
8/28/2006 16:16:05 JCM - activity updated through activity BLDA022 from case BLD06-02114.
|
Routing - FIRE | 8/15/2006 | | 8/18/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Plan resubmittals received | | | 8/18/2006 | | |
|
|
|
Received 1 copy of plan review response letter from ZGA, 2 copies of A2.0, A3.0 and taken to John Menard
|
1st review completed | | | 8/18/2006 | | FAIL |
|
|
|
Failed Plan check.
|
Routing - PLAN CHECK | 8/4/2006 | | 8/15/2006 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 8/15/2006 | | DONE |
|
|
|
Faxed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLANNING | 8/3/2006 | | 8/4/2006 | | PASS |
|
|
|
Carl M.
|
Routing - PLUMBING | 8/2/2006 | | 8/3/2006 | | PASS |
|
|
|
no plumbing
|
Routing - Erosion and Sediment | 8/1/2006 | | 8/2/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions. Reference ESC06-01210 as master plan for the project.
|
Routing - PUBLIC WORKS | 7/28/2006 | | 8/1/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 7/25/2006 | | 7/28/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/25/2006 | | |
|
|
|
|
Application received | | | 7/24/2006 | | |
|
|
|
|