Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/29/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 1/29/2007 | | |
|
|
|
tlk to craig from Sorecrafters the correct amount is 6220 11:30 am
|
Telephone call | | | 1/26/2007 | | DONE |
|
|
|
lft vm with store crafters concerning their values for mech
|
Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/3/2006 | 12/27/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 11/3/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11283 issued 11-3-06 to the Sunglass Hut at Boise Towne Square.
|
Permanent Occupancy | | 10/26/2006 | 10/26/2006 | | DONE |
|
|
|
|
BLD-Final | 10/19/2006 | 10/20/2006 | 10/20/2006 | P | PASS |
Mike Jordan
|
|
|
David Ponce, late afternoon; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Ok for perm occ.
|
FIRE-Final Inspection | 10/20/2006 | 10/20/2006 | 10/20/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Final | 10/17/2006 | 10/18/2006 | 10/18/2006 | P | CANC |
Mike Jordan
|
|
|
david ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
FIRE-Final Inspection | 10/17/2006 | 10/18/2006 | 10/18/2006 | A | FAIL |
Troy Cobbley
|
|
|
the only items that were ready to look at were the emergency lights, exit signs and the smoke evac system which all passed. The fire extinguisher was not hung or tagged and the door hardware was not installed. Ceiling tile was missing from the back room.
|
Plan resubmittals received | | | 10/18/2006 | | DONE |
|
|
|
Received 4 copys of sheets A-2.1,A-2.0 taken to Ron H. ( this permit was issued 9-18-06 )
|
FIRE-Final Inspection | 10/17/2006 | 10/19/2006 | 10/17/2006 | A | CANC |
Troy Cobbley
|
|
|
david ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Inspection cancelled from web by: Patricia Smith
|
BLD-Framing/Rough-in | 10/12/2006 | 10/13/2006 | 10/13/2006 | A | PASS |
Mike Jordan
|
|
|
david - note: grid ceiling insp.; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 10/9/2006 | 10/10/2006 | 10/10/2006 | A | PASS |
Mike Jordan
|
|
|
david; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Received, reviewed revised plans for new storefront and furout wall. framing ok to cover.
|
BLD-Framing/Rough-in | 10/6/2006 | 10/6/2006 | 10/6/2006 | P | FAIL |
Mike Jordan
|
|
|
David; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. No details for additional work provided. Permit is under review for additional details that were submitted.
|
Plan resubmittals received | | | 10/5/2006 | | |
|
|
|
Received 1 cover transmittal, 4 copies of sheets A-1.3, A-2.0, A-2.1 and taken to Ron Hill...permit is in the ISS status
|
BLD-Framing/Rough-in | 9/27/2006 | 9/28/2006 | 9/28/2006 | A | PART |
Mike Jordan
|
|
|
david; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Interior steel stud framed walls. !hr. wall already inspected under different permit. Needs to wrap columns, Firecaulk all penetrations at 1hr wall. May need to rtesubmit additional plans details for possible addition of new furout wall along new 1hr wall to eliminate bumpouts by columns and for new storefront to not be supported by ceiling.
|
Issue PAID IN FULL permit | | | 9/18/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/7/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/7/2006 | | DONE |
|
|
|
tlk to darren ###-#### that permit and fees are ready to be picked up but needs RCE #
|
Permit Ready to Issue | | | 9/7/2006 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 8/8/2006 | | 9/6/2006 | | PASS |
|
|
|
9/6/2006 15:53:26 RMH - activity updated through activity BLDA022 from case BLD06-02202.
|
Routing - FIRE | 9/1/2006 | | 9/6/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 9/6/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/6/2006 | | 9/6/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/1/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/8/2006 | | 9/1/2006 | | PEND |
|
|
|
No corrections required from building review, routed to fire 9/01, permit pending fires review.
|
Routing - PUBLIC WORKS | 8/8/2006 | | 8/8/2006 | | PASS |
|
|
|
|
Application received | | | 7/31/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/31/2006 | | |
|
|
|
Mechanical & Lighting Compliance have not been signed
|
Recd Pcfee & Taken To Pln CK | | | 7/31/2006 | | |
|
|
|
|