Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD06-02211
StatusFinaled
Name KEYSER DAVID SCOTT
Site Address 11560 W PRESIDENT DR
Project NameRAYCO OFFICE BUILDING
Customer Number 
ePlanReviewNo
Description
(K2 Construction RCE-1824) Rayco Office Building - To construct a new 5,150 square foot, one story, wood framed office building and related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD3/30/20073/30/20074/4/2007 DONE
First Notice has not been responded to.
First Notice 3/19/20073/30/2007 DONE
Code Occupancy Approval3/19/20073/19/20073/19/2007PPASS
DetailsScott M.Brown
OK FOR FINAL & RELEASE OF BOND.
Permanent Occupancy 3/19/20073/19/2007 DONE
Details
Permanent occupancy UNPAID FEE  3/19/2007 DONE
Perm. Occ. Cert. # 11484 issued 3-19-07 to the Rayco Office Building.
BLD-Final12/28/200612/29/200612/29/2006PPART
DetailsMike Jordan
Julio; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Temp occ given. Noted bond has been received. Will be ok for perm occ once others have finaled.
FIRE-Final Inspection12/28/200612/29/200612/29/2006APASS
DetailsTroy Cobbley
Life safety finaled
Temporary occupancy  12/29/2006 DONE
Temp. Occ. Cert. # 5504 issued 12-29-06 to the Rayco Office Building.
FIRE-Final Inspection12/27/200612/28/200612/28/2006AFAIL
DetailsTroy Cobbley
Lower and tag fire extinguishers. Provide correct sample tubes and remote annunciators for the duct smoke detectors.
BLD-Final12/27/200612/28/200612/28/2006PNR
DetailsMike Jordan
julo; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs life/safety and public works.
Code Occupancy Approval Temp  12/26/2006 FAIL
NEEDS TO BOND FOR $28,000, LANDSCAPE. BLACK TOP, PARKING LOT MARKING, STONE WORK ALL TO BE DONE FOR THIS BOND AMOUNT. WILL RECALL TURSDAY FOR TEMP AND PLACE BOND WITH CATHY.
BLD-Conference12/19/200612/21/200612/21/2006ADONE
DetailsMike Jordan
Julio; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett
BLD-Conference12/18/200612/19/200612/19/2006ADONE
DetailsMike Jordan
Julio; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
Print Occupancy Form  12/19/2006 DONE
BLD-Other12/7/200612/8/200612/8/2006APART
DetailsMike Jordan
julio - note: ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Needs to repair some wires, exceed 1 in 8 as noted on approved plans. insp. pending other ri prior to cover.
BLD-Energy code compliance12/8/200612/8/200612/8/2006APASS
DetailsMike Jordan
julio - note: ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Attic insul.
BLD-Framing/Rough-in12/8/200612/8/200612/8/2006APASS
DetailsMike Jordan
julio - note: ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Wall cover11/6/200611/6/200611/6/2006PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/6/2006 at 10:26:52 AM. Contact: ###-####.
BLD-Framing/Rough-in10/20/200610/23/200610/23/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/20/2006 at 1:44:29 PM. Contact: ###-####. Ok to cover soffitt. All hardware installed as per plan.
BLD-Framing/Rough-in10/11/200610/12/200610/12/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/11/2006 at 2:01:40 PM. Contact: ###-####. Roof shear nailing, interior holdowns for panel system. Needs to have welds on strapping inspected by special insp.
BLD-Energy code compliance9/19/20069/19/20069/19/2006PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/19/2006 at 10:29:25 AM. Contact: ###-####.
BLD-Footing9/11/20069/12/20069/12/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/11/2006 at 10:36:45 AM. Contact: ###-####. wip. perimeter footings. Project will have special insp. on conc. and vrebar.
(F) Reprint permit  9/1/2006  
Routing - PLAN CHECK8/28/2006 8/31/2006  
Plan resubmittals received  8/31/2006  
received memo brs architects & transmittal sheet-also "3" sheets of C1.O, & "3" sheets of SD1.1-plans taken to john menard
Routing - FIRE8/31/2006 8/31/2006 PASS
Attached review comments to plans.
Routing - PLAN CHECK8/31/2006 8/31/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/31/2006 DONE
Print Occupancy Form  8/31/2006  
Telephone call  8/31/2006  
tlk to doug ###-#### that permit and fees are ready to be picked up but needs a copy of ACHD
Permit Ready to Issue  8/31/2006 DONE
Issue PAID IN FULL permit  8/31/2006 DONE
Plan assigned to (JCM)8/1/2006 8/31/2006 PASS
8/31/2006 10:56:43 JCM - activity updated through activity BLDA022 from case BLD06-02211.
Plan Reviewer's activity  8/29/2006 PASS
Reviewed and approved structural and nonstructural revisions with redlined notes and attachments. JCM
1st review completed  8/28/2006 FAIL
Failed Plumbing, Structural, Plan Check & Fire.
Routing - FIRE8/21/2006 8/28/2006 FAIL
Faxed review comments to architec. Attached review comments to plans.
Plan resubmittals received  8/23/2006  
Received 1 copy of cover transmittal, 1 copy of TSX-8500 Insulation for exposed use sheet, 3 copies of letter from Stapley Engineering for plan reveiw response, 3 copies of Calcs handwritten called sheet # SD-1, 3 copies of the following sheets--G1.1, S0.1, A1.1, A3.1, A5.1, A6.1, A6.2, A8.1 and taken to John Menard
Routing - PLUMBING8/17/2006 8/21/2006 PASS
vent all traps
Plan resubmittals requested  8/17/2006 DONE
Faxed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals received  8/17/2006 DONE
Received 1 transmittal & 3 copys of sheet P1.0 taken to John M.
Routing - PLAN CHECK8/11/2006 8/17/2006 FAIL
John Menard
Plan resubmittals requested  8/16/2006 DONE
Faxed the architec a copy of the structural review from the consulting structural engieer requesting revisions. JCM
Routing Off Site - STRUCTURAL8/1/2006 8/14/2006 FAIL
Routing - PLANNING8/10/2006 8/11/2006 PASS
Drh06-00001 Sarah; Cup05-00168 Cody-Drawings meet the requirements of both the Conditional Use and Design Review approvals.
Routing - PLUMBING8/9/2006 8/10/2006 FAIL
provide plumbing plans
Routing - Erosion and Sediment8/9/2006 8/9/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS8/7/2006 8/9/2006 PASS
Routing - PLANNING Land Div8/2/2006 8/7/2006 PASS
Recd Pcfee & Taken To Pln CK  8/2/2006 DONE
Plans ACCEPTED BY PLAN TECH  8/2/2006  
Plan routing begun/NEW & ADDTN  8/2/2006  
Telephone call  8/1/2006  
called Action Couriers to pick up plans and deliver to AHJ Engineers
Application received  8/1/2006