Case Summary (BLD) | | | 1/29/2009 | | DONE |
|
|
|
|
BLD-Final | 6/29/2007 | 7/2/2007 | 7/2/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/29/2007 at 3:34:55 PM. Contact: ###-####.
|
DOC - Permit Finaled | 7/2/2007 | 7/2/2007 | 7/2/2007 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Grading Inspection | 4/27/2007 | 4/27/2007 | 4/27/2007 | | DONE |
|
|
|
final grading and drainage approved
|
BLD-Wall cover | 1/18/2007 | 1/18/2007 | 1/19/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/18/2007 at 6:57:54 AM. Contact: ###-####.c n items completed insulation ok ok to cover
|
BLD-Framing/Rough-in | 1/15/2007 | 1/16/2007 | 1/16/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/15/2007 at 4:24:32 PM. Contact: ###-####. ok to insulate still needs to finish fire blocking fur downs in basement and installing hold downs
|
BLD-Framing/Rough-in | 1/12/2007 | 1/16/2007 | 1/15/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/12/2007 at 9:48:33 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jan 15 2007 4:29PM.
|
BLD-Framing/Rough-in | 1/8/2007 | 1/9/2007 | 1/9/2007 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/8/2007 at 4:35:51 PM. Contact: ###-####. still working on c/n items
|
BLD-Framing/Rough-in | 1/8/2007 | 1/8/2007 | 1/8/2007 | P | FAIL |
Dave Hannah
|
|
|
bob; Phone #: ###-#### c/n on site do not insulate
|
BLD-Framing/Rough-in | 1/5/2007 | 1/8/2007 | 1/8/2007 | A | CANC |
Dave Hannah
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles RESCHEDULED PM
|
BLD-Foundation | 11/1/2006 | 11/1/2006 | 11/1/2006 | P | PASS |
Dave Hannah
|
|
|
robert ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 10/19/2006 | 10/19/2006 | 10/19/2006 | P | PASS |
Dave Hannah
|
|
|
robert; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
PubWorks Subgrade Approval | 10/17/2006 | 10/17/2006 | 10/17/2006 | | DONE |
|
|
|
footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 8/29/2006 | | |
|
|
|
|
Plan assigned to (SRZ) | 8/22/2006 | 8/22/2006 | 8/28/2006 | | PASS |
|
|
|
8/28/2006 09:15:04 SRZ - activity updated through activity BLDA022 from case BLD06-02289.
|
Case Summary (BLD) | | | 8/28/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/28/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/28/2006 | | DONE |
|
|
|
|
Telephone call | | | 8/28/2006 | | DONE |
|
|
|
spoke to justin@###-####/told permit was ready, permit#, lot & block, and fees
|
Routing - PLAN CHECK | 8/16/2006 | | 8/28/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/23/2006 | | PASS |
|
|
|
Plan review Pending Engineers Structural calculations. (SRZ) Received Structual Clacs. (SRZ)
|
Telephone call | | | 8/23/2006 | | DONE |
|
|
|
I left message with Tim Johnson about needing Structural Calculations to complete plan review. (SRZ)
|
Plan assigned to (SAM) | 8/8/2006 | 8/8/2006 | 8/22/2006 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 8/16/2006 | | 8/16/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 8/16/2006 | | 8/16/2006 | | PASS |
|
|
|
Approved as Category 3
|
Routing - FIRE | 8/11/2006 | | 8/15/2006 | | PASS |
|
|
|
No fire sprinklers required. (Triplett Ranch)
|
Routing - Erosion and Sediment | 8/10/2006 | | 8/11/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 8/8/2006 | | 8/10/2006 | | PASS |
|
|
|
|
Application received | | | 8/8/2006 | | |
|
|
|
|
Routing - Addressing | 8/8/2006 | | 8/8/2006 | | PASS |
|
|
|
|