Third Notice BLD | 2/12/2007 | 2/12/2007 | 4/19/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 3/23/2007 | | DONE |
|
|
|
call to dixie w/ cloverdale need fv on this permit, left msg on ans mach.
|
Letter of compliance | | | 3/20/2007 | | DONE |
|
|
|
Letter of Compliance issued 3-20-07
|
Second Notice BLD | 2/2/2007 | 2/2/2007 | 2/12/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 1/16/2007 | 1/16/2007 | 2/2/2007 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 1/15/2007 | 1/16/2007 | 1/16/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/15/2007 at 12:47:11 PM. Contact: ###-####.
|
DOC - Permit Finaled | 1/16/2007 | 1/16/2007 | 1/16/2007 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 1/2/2007 | 1/3/2007 | 1/3/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
FIRE-Final Inspection | 12/13/2006 | 12/13/2006 | 12/14/2006 | P | NR |
Forrest France
|
|
|
Project not yet completed for life safety final inspection at this time.
|
BLD-Other | 12/8/2006 | 12/11/2006 | 12/11/2006 | A | PASS |
Dave Hannah
|
|
|
rock - note: ceiling ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to cover
|
BLD-Framing/Rough-in | 11/17/2006 | 11/17/2006 | 11/17/2006 | P | PASS |
Dave Hannah
|
|
|
rock ; Phone #: ###-#### Internet Inspection Request from: Cathy Chilesok to cover walls
|
BLD-Framing/Rough-in | 11/15/2006 | 11/15/2006 | 11/16/2006 | P | PART |
Dave Hannah
|
|
|
rock; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover walls
|
BLD-Conference | 10/2/2006 | 10/3/2006 | 10/3/2006 | A | DONE |
Dave Hannah
|
|
|
###-#### Rock
|
BLD-Conference | 10/2/2006 | 10/2/2006 | 10/2/2006 | P | NR |
Jim Sly
|
|
|
rock; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Called Contr.......he wanted to schedule Tues
|
Issue & PRINT to be Invoiced | | | 9/28/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/27/2006 | | DONE |
|
|
|
lft ms with receptionist for curtis permit is ready
|
Permit Ready to Issue | | | 9/27/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/22/2006 | | 9/26/2006 | | PASS |
|
|
|
Plans approved by plumbing plan review. No resubmittals required. Routing to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2006 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 9/26/2006 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 8/18/2006 | | 9/26/2006 | | PASS |
|
|
|
9/26/2006 10:49:45 DRS - activity updated through activity BLDA022 from case BLD06-02302.
|
Routing - PLUMBING | 9/20/2006 | | 9/22/2006 | | PASS |
|
|
|
approved per plan, letter and note on p2.1 resubmittal and 2003 UPC
|
Routing - PLAN CHECK | 9/12/2006 | | 9/20/2006 | | PEND |
|
|
|
Received resubmittals for plumbing plan review. Inserted into plans and routed back to plumbing plan review.
|
Plan resubmittals received | | | 9/20/2006 | | |
|
|
|
received letter of transmittal from zga architects & letter for dan stuart from zga. also "2" sheets or P2.1. plans taken to dan stuart
|
1st review completed | | | 9/12/2006 | | FAIL |
|
|
|
Failed Plumbing.
|
Telephone call | | | 9/12/2006 | | DONE |
|
|
|
Called Josh Howa, ZGA architects concerning response to plumbing plan review corrections for plan showing location of med gas shut-off valves and alarms. NFPA 4-3.1.2.2 & 4-3.1.2.3. Josh said we should have response in next couple of days.
|
Routing - FIRE | 9/9/2006 | | 9/12/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 8/21/2006 | | 9/9/2006 | | PEND |
|
|
|
NO RESUBMITTALS REQUIRED. Copy of report to architect Tom Zabala. Special Inspection information to be provided to structural field inspector. Other clarifications red-lined on plan sheets and referenced in attachments.
|
Routing - PLUMBING | 8/18/2006 | | 8/21/2006 | | FAIL |
|
|
|
show location of med gas shutoff valves and alarms.
|
Routing - PUBLIC WORKS | 8/18/2006 | | 8/18/2006 | | PASS |
|
|
|
|
Routing - Addressing | 8/18/2006 | | 8/18/2006 | | PASS |
|
|
|
|
Application received | | | 8/8/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2006 | | |
|
|
|
|