Permit Information
Permit NumberBLD06-02303
StatusFinaled
Name RIVERWALK LLC
Site Address 851 W FRONT ST
Project NameTHE ASPEN - SHELL
Customer Number 
ePlanReviewNo
Description
(THE ASPEN) To construct a new 128,710 square foot, seventeen story, post tension concrete commercial and residential high-rise building with a 5,450 square foot basement for storage and related site improvements. 1st Fl. 7,185 sq. ft. future retail shell space; 2nd Fl. 5,215 sq. ft. future office shell space; 3rd & 4th Fls. 6,975 sq. ft. parking levels with 20 parking spaces on each level; 5th - 8th Fls. 6,975 sq. ft. residential condo floors with 10 finished one bedroom or studio units on each floor; 9th Fl. 8,495 sq. ft. future residential condo condo shell; 10th Fl. 8,115 sq. ft. future residential condo shell; 11th - 14th Fls. (no 13th Floor) 8,740 sq. ft. future residential condo shell; 15th Fl. 8,395 sq. ft. future residential condo shell; 16th Fl. 8,740 sq. ft., 17th Fl. 8,875 sq. ft. future residential condo shell; 18th Fl. 5,620 sq. ft. future residential condo shell (upper floor of 17th floor condos).
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/23/2011 DONE
Case Summary (BLD)  12/8/2010 DONE
DetailsTisha Gallop
Third Notice 3/9/20103/10/2010 DONE
Third Notice 2/23/20102/24/2010 DONE
mailed
Second Notice 1/8/20102/18/2010 DONE
First Notice 12/3/200912/29/2009 DONE
Letter of compliance  8/13/2009 DONE
CHANGE STATUS TO (FNL)  8/13/2009 DONE
All floors finaled per dave hannah
Temporary Occupancy7/29/200910/27/20097/29/2009 DONE
DetailsJenifer Gilliland
BLD-Final7/17/20097/20/20097/20/2009APASS
DetailsDave Hannah
brad Phone #: ###-#### ok for c.c.
FIRE-Final Inspection5/1/20095/1/20095/1/2009PPASS
DetailsForrest France
C/N items have been finished with the exception of signage at the elevator lobbys, relocation of stairway floor signage, and braile exit signage at the balcony. Items to be completed prior to structural final approval as discussed. Shell building fire life safety passed.
BLD-Final4/28/20094/28/20094/29/2009PPART
DetailsDave Hannah
Brad Phone #: ###-#### ok for temp occ
Temporary Occupancy UNPAID FEE  4/29/2009 DONE
DetailsTisha Gallop
Per Jenifer G., Bob A., and Dave H. issue temp for condo units only. The final occupancy will be broken out into seperate permit when ready. A Certificate of compliance will be issued when this permit is finaled for the shell.
FIRE-Final Inspection4/27/20094/28/20094/28/2009APART
DetailsForrest France
Remaining items include #17 (10) telephone line at the fire command center, #93 elevator signage, fire alarm descriptor at the FACP for sprinkler supervision per TOC. letter item six. Some issues corrected while on site including fire stop at penetrations on the 3rd, 4th, and 9th floors, EM light repair at the 9th floor west stairway, correct hardware installed at the basement west exit door, building plan schematic provided at the command center, missing escutcheon installed at the 17th floor stairway. EM lighting and exit signage tested okay via generator power. Project related shell alarm and sprinkler permits finaled.
BLD-Final4/23/20094/24/20094/28/2009PNR
DetailsDave Hannah
Brad- temp occ Phone #: ###-####
FIRE-Final Inspection4/27/20094/27/20094/27/2009PPART
DetailsForrest France
Work in progress at dry sprinkler risers for the 3rd and 4th floors, phone line at the command center to be installed 4/28 per contractor, discussed remainder of items needed for fire life safety and generator test for egress lighting.
FIRE-Final Inspection4/23/20094/24/20094/24/2009AFAIL
DetailsForrest France
Missing fire code review notes for on site inspection, noted item #10 per IFC sec. 509 at the fire command center has not been installed, need to coordinate EM lighting and exit signage testing via generator backup with the electrician, project related fire sprinkler permit is not yet approved for final.
FIRE-Final Inspection4/23/20094/23/20094/23/2009PNR
DetailsForrest France
Building fire life safety cannot be approved until project related fire sprinkler and alarm permit work have passed final inspections. Note: Fire sprinkler failed dry system water delivery requirements at the 3rd and 4th level parking decks. Fire alarm system lacks interconnection to the exitsing structure sprinkler monitoring per conditions of the Temporary Occupancy agreement letter.
FIRE-Final Inspection4/20/20094/21/20094/21/2009PNR
DetailsForrest France
brad Phone #: ###-####
BLD-Conference4/14/20094/15/20094/15/2009APASS
DetailsDave Hannah
Brad Phone #: ###-####
FIRE-Final Inspection4/13/20094/14/20094/14/2009PNR
DetailsForrest France
Project related fire alarm and sprinkler permits must be approved prior to final inspection for building fire life safety.
FIRE-Final Inspection4/8/20094/9/20094/9/2009PNR
DetailsForrest France
Regarding backup power source requirements.
BLD-Final4/7/20094/9/20094/9/2009PCANC
DetailsDave Hannah
Brad Phone #: ###-####
FIRE-Hydro test above ground4/1/20094/1/20094/2/2009PPART
DetailsForrest France
Hydrostatic retesting for the 14th floor completed, concluded satisfactory 24 hr. air test for the 3rd and 4th floor dry systems.
Zoning Approval3/31/20093/31/20094/1/2009 PASS
DetailsJosh Wilson
Pass for permanent occupancy per Design Review approvals
FIRE-Hydro test above ground3/31/20093/31/20093/31/2009PPART
DetailsForrest France
Overhead hydrostatic testing for the 12th, 16th, 17th,18th and basement levels passed. NOTE: hydro test for the 14th floor failed due to 5 psi. loss at the guage. Also begin 24 hr. air testing for the 3rd and 4th floor dry systems.
PubWorks Occupancy Approval3/31/20093/31/20093/31/2009 DONE
DetailsBrian Murphy
Approved and signed off per Brian Murphy///3-31-09 BAS
Case Summary (BLD)  3/31/2009 DONE
BLD-Conference3/27/20093/30/20093/30/2009APASS
DetailsDave Hannah
brad Phone #: ###-####
FIRE-Conference3/28/20093/28/20093/28/2009ADONE
DetailsScott Arellano
Witnessed stairwell pressurization testing by independant contractor (Romar). Test report to be compiled by contractor and delivered to fire department at final inspection.
BLD-Conference3/24/20093/24/20093/25/2009PPASS
DetailsDave Hannah
Brad Phone #: ###-####
BLD-Conference3/20/20093/20/20093/23/2009PPART
DetailsDave Hannah
Brad Phone #: ###-#### walked basement with contractor has several items to fix
BLD-Framing/Rough-in3/9/20093/10/20093/10/2009PPART
DetailsDave Hannah
Brad Phone #: ###-#### elev lobbies and corr on 10 thur 17 ok to cover
BLD-Final3/3/20093/5/20093/5/2009APART
DetailsDave Hannah
Brad Phone #: ###-#### corradors floors 9,10,and 11 ok to cover ceilings
BLD-Framing/Rough-in2/26/20093/2/20093/3/2009PPART
DetailsDave Hannah
brad Phone #: ###-#### ceilings 11th floor ok to cover hard lids
BLD-Framing/Rough-in2/20/20092/23/20092/23/2009APART
DetailsDave Hannah
brad Phone #: ###-#### stairs on appt on 17th fl ok to cover
BLD-Framing/Rough-in2/19/20092/20/20092/20/2009APART
DetailsDave Hannah
brad Phone #: ###-#### ok to cover ceiling on 9th floor corr
BLD-Framing/Rough-in2/17/20092/18/20092/19/2009APART
DetailsDave Hannah
brad Phone #: ###-#### ext wall 17th and 18th floor ok to cover
BLD-Framing/Rough-in2/10/20092/11/20092/12/2009APART
DetailsDave Hannah
brad Phone #: ###-#### 7th floor corr ok to cover ceiling 3rd floor eng rm ok to cover
BLD-Framing/Rough-in2/4/20092/4/20092/4/2009PPART
DetailsDave Hannah
BRAD Phone #: ###-#### ok to cover ceiling on 8th floor corrador
BLD-Framing/Rough-in2/2/20092/3/20092/3/2009APART
DetailsDave Hannah
Brad Phone #: ###-#### ok to cover corr on 16th floor
Meeting  1/29/2009 DONE
Letter from Architect, John Price, outling design proposals related to fire command center, approved by Fire Marshal, Mark Senteno, emailed to architect and others. See Doc attached.
BLD-Framing/Rough-in1/26/20091/27/20091/28/2009PPART
DetailsDave Hannah
Phone #: ###-#### brett
BLD-Framing/Rough-in1/23/20091/26/20091/27/2009PPASS
DetailsDave Hannah
brad Phone #: ###-#### hard lids on 10th floor ok gas lines on ext walls in corr ok to cover
BLD-Framing/Rough-in1/21/20091/22/20091/22/2009APART
DetailsDave Hannah
brad Phone #: ###-#### ok to insulate 17th fl ext hallway walls and soffits on ground floor ext
BLD-Framing/Rough-in1/14/20091/15/20091/16/2009APART
DetailsDave Hannah
brad Phone #: ###-#### trash shut shaft and room on ground floor ok to cover elec bus through floors ok
BLD-Framing/Rough-in1/12/20091/13/20091/16/2009PPART
DetailsDave Hannah
brad Phone #: ###-#### ext cor walls L12-14
Meeting  1/13/2009 DONE
Attached a letter from John Price signed by G Slane and M. Senteno, outling agreement of meeting held 1-6-09 regarding interim sprinkler and fire alarm measures to allow temporary occupancy of the building, prior to full completion of all tenant spaces. Doc Attached.
BLD-Framing/Rough-in1/8/20091/9/20091/12/2009PPART
DetailsDave Hannah
brad Phone #: ###-#### looked at elec bus work in floors need to see more of the inslation
BLD-Framing/Rough-in1/7/20091/8/20091/8/2009APART
DetailsDave Hannah
brad Phone #: ###-#### 10th floor walls ok to one side
BLD-Footing1/5/20091/6/20091/6/2009ANR
DetailsDave Hannah
brad Phone #: ###-####
FIRE-Conference1/5/20091/5/20091/5/2009PDONE
DetailsForrest France
Regarding project scheduling for permit finals.
BLD-Framing/Rough-in12/29/200812/30/200812/30/2008APART
DetailsDave Hannah
brad Phone #: ###-#### corr on 8,9,and 10 lev ok to cover
BLD-Framing/Rough-in12/23/200812/23/200812/23/2008PPART
DetailsDave Hannah
david - drywall Phone #: ###-#### ok to cover walls around backup genenator on L3
BLD-Framing/Rough-in12/18/200812/19/200812/19/2008PPART
DetailsDave Hannah
BRAD Phone #: ###-#### 9th floor soffits ok to cover
BLD-Framing/Rough-in12/15/200812/16/200812/16/2008APART
DetailsDave Hannah
BRAD Phone #: ###-####
BLD-Framing/Rough-in12/15/200812/15/200812/16/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### elev fronts ok to cover
BLD-Framing/Rough-in12/8/200812/8/200812/10/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### ok to cover 9th floor
BLD-Framing/Rough-in12/9/200812/9/200812/10/2008PPASS
DetailsDave Hannah
brad Phone #: ###-#### ok to cover 9th floor walls
BLD-Framing/Rough-in12/4/200812/4/200812/5/2008PFAIL
DetailsDave Hannah
brad Phone #: ###-#### 9th floor need to fix fire protection items
BLD-Framing/Rough-in12/1/200812/2/200812/2/2008APART
DetailsDave Hannah
brad Phone #: ###-#### ok to cover 8th floor hard lids
BLD-Framing/Rough-in11/26/200812/1/200812/1/2008PCANC
DetailsDave Hannah
Brad- if possible Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
BLD-Framing/Rough-in11/21/200811/21/200811/22/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### elev shaft inner wall oklevel 5
BLD-Conference11/20/200811/20/200811/20/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/20/2008 at 9:53:42 AM. Contact: ###-####. talked about what needs to be completed to get a temp occ
BLD-Framing/Rough-in11/18/200811/19/200811/20/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### ok to cover walls 8th floor
BLD-Framing/Rough-in11/17/200811/18/200811/19/2008AFAIL
DetailsDave Hannah
Brad Phone #: ###-#### 8th floor ok to cover one side only
BLD-Framing/Rough-in10/28/200810/29/200811/4/2008ACANC
DetailsDave Hannah
brett Phone #: ###-####
BLD-Concrete10/23/200810/24/200810/28/2008APART
DetailsDave Hannah
Brad Phone #: ###-####
BLD-Framing/Rough-in10/16/200810/16/200810/20/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### stair towers and elev control room on top flor ok to cover
BLD-Conference10/13/200810/13/200810/14/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### need two hr wall in stair tower
BLD-Framing/Rough-in10/6/200810/7/200810/7/2008APART
DetailsDave Hannah
brad Phone #: ###-#### ok to cover ceiling
BLD-Framing/Rough-in9/30/200810/1/200810/1/2008ACANC
DetailsDave Hannah
brad Phone #: ###-####
BLD-Framing/Rough-in9/23/20089/23/20089/24/2008PPART
DetailsDave Hannah
Brad Phone #: ###-####
BLD-Framing/Rough-in9/18/20089/18/20089/20/2008PFAIL
DetailsDave Hannah
Brad Phone #: ###-#### ceiling grid 4th floor note to code
CHANGE STATUS TO (ISS)  9/18/2008 DONE
DetailsTisha Gallop
picked up plan modification
Plan assigned to (JCM)9/12/20089/12/20089/17/2008 PASS
DetailsJohn Menard
9/17/2008 13:32:00 JCM - activity updated through activity BLDA022 from case BLD06-02303.
Plan Reviewer's activity  9/17/2008 PASS
DetailsJohn Menard
Approved plans modification to delete finish of 10 condominiums on the 9th floor and convert back to an empty shell floor. Seven separate tenant improvement permits will be submitted to finish the 9th floor for occupancy. See revised floor plan A2.9BR2 and revised certificate of value. JCM
Routing - PLAN CHECK9/12/2008 9/17/2008 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  9/17/2008 DONE
DetailsJohn Menard
(F) Reprint permit  9/17/2008 DONE
DetailsTisha Gallop
Telephone call  9/17/2008 DONE
DetailsTisha Gallop
Called arch. John Price and told him plan mod is ready and no fees
Override - Parcel Holds  9/17/2008  
Override - Parcel Holds  9/17/2008  
Permit Ready to Issue  9/17/2008 DONE
DetailsTisha Gallop
Plan Modification Accepted  9/12/2008  
DetailsTisha Gallop
Plan Modification accepted for Bld06-02303 (The Aspen-shell) for the 9th floor to be changed to a shell and core. Seperate tenant improvement permit applications will be submitted for the (7) residential condos on this floor; the project value for the shell went down from $8,838,000 to $8,599,240 (see revised cert of value); submitted on sheet A2.9BR2; routed to John Menard.
Received Certificate of Value  9/12/2008 DONE
DetailsTisha Gallop
Revised cert of value submitted with plan modification with reduced value on 9-12-08// New Project value is $8,599,240; ele $487,093; plm $285,093; mech $386,093; fire sprinkler $190,062, fire alarm $146,031//9/12/08 LEG
BLD-Framing/Rough-in9/9/20089/9/20089/9/2008PPART
DetailsDave Hannah
###-#### - brad soffits on 7th floor ok to cover
Override - Parcel Holds  9/9/2008  
BLD-Framing/Rough-in9/4/20089/5/20089/8/2008APART
DetailsDave Hannah
Brad Phone #: ###-#### ok to cover soffits on 6th floor
BLD-Framing/Rough-in9/2/20089/3/20089/3/2008APART
DetailsDave Hannah
brad - ###-#### - 5th floor ok to cover soffits
Override - Parcel Holds  9/2/2008  
BLD-Framing/Rough-in8/28/20088/28/20088/29/2008PPART
DetailsDave Hannah
Brad Phone #: ###-#### stair towers 8th and 9th floors ok to cover
Override - Parcel Holds8/28/20081/1/19008/28/2008  
framing only
Plan Modification Accepted  8/28/2008  
DetailsJohn Menard
Plan modification accepted for Bld06-02303 (The Aspen - shell) to revise the interior at the 9th floor to be (3) 2-bed units and (4) 1-bed units. Original plan had (10) units. Submitted on sheets A2.9BR1, A3.9.1B, A3.9.2B, A7.9B, A6.1R1, A6.2R1; routed to John Menard
BLD-Framing/Rough-in8/25/20088/26/20088/26/2008APART
DetailsDave Hannah
brett Phone #: ###-####
BLD-Concrete8/25/20088/25/20088/25/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### roof deck mti on site
Override - Parcel Holds8/25/20081/1/19008/25/2008  
framing
Override - Parcel Holds8/25/20081/1/19008/25/2008  
concrete insp
BLD-Framing/Rough-in8/20/20088/20/20088/21/2008PPART
DetailsDave Hannah
Brad Phone #: ###-#### 7th floor ok to cover walls
BLD-Framing/Rough-in8/18/20088/19/20088/19/2008AFAIL
DetailsDave Hannah
brad Phone #: ###-####
Override - Parcel Holds8/18/20081/1/19008/18/2008  
for framing only
BLD-Framing/Rough-in8/14/20088/15/20088/15/2008ANR
DetailsDave Hannah
Brad Phone #: ###-####
BLD-Framing/Rough-in8/12/20088/14/20088/15/2008APART
DetailsDave Hannah
BRAD Phone #: ###-#### ok to cover insulation on ceiling of level 4 above ac units need to fire stop wall pent on 5
Override - Parcel Holds8/12/20081/1/19008/12/2008  
ASPEN FRAMING
BLD-Concrete8/11/20088/11/20088/11/2008PPART
DetailsDave Hannah
Brad Phone #: ###-#### mti on site to cover that concrete placement of the 18 th floor
BLD-Framing/Rough-in8/11/20088/11/20088/11/2008PPART
DetailsDave Hannah
Brad Phone #: ###-#### 6th floor ok to cover walls in condos
BLD-Framing/Rough-in8/8/20088/8/20088/11/2008PPART
DetailsDave Hannah
Brad Phone #: ###-#### pent in floor on 6th floor ok
Override - Parcel Holds8/8/20081/1/19008/8/2008  
framing only
BLD-Framing/Rough-in8/5/20088/6/20088/6/2008APART
DetailsDave Hannah
Brad Phone #: ###-#### ok to cover walls on 5th floor
BLD-Concrete7/23/20087/24/20087/24/2008PPART
DetailsTom Arcoraci
brad Phone #: ###-####
BLD-Framing/Rough-in7/21/20087/22/20087/23/2008PPART
DetailsDave Hannah
brad Phone #: ###-#### need puddy pads on both side of walls
Override - Parcel Holds7/23/20081/1/19007/23/2008  
concrete
BLD-Framing/Rough-in7/16/20087/21/20087/21/2008APART
DetailsDave Hannah
Brad Phone #: ###-#### ok to one side walls floor pent ok need to puddy pad elec boxs in party walls with less than 24inchs of sep
Override - Parcel Holds7/21/20081/1/19007/21/2008  
framing
BLD-Framing/Rough-in7/15/20087/15/20087/16/2008PNR
DetailsDave Hannah
brad Phone #: ###-#### needs to fire stop floor
Override - Parcel Holds7/16/20081/1/19007/16/2008  
framing
Override - Parcel Holds7/15/20081/1/19007/15/2008  
framing inspection
BLD-Concrete7/9/20087/10/20087/14/2008APART
DetailsDave Hannah
Brad Phone #: ###-####
(F) Reprint permit  7/10/2008 DONE
CHANGE STATUS TO (ISS)  7/10/2008 DONE
DetailsBarbara Stitt
Plan modification 7-10-08 bas
BLD-Framing/Rough-in7/9/20087/9/20087/9/2008APART
DetailsDave Hannah
second floor restrooms ok to cover
Plan assigned to (JCM)5/19/20085/19/20087/8/2008 PASS
DetailsJohn Menard
7/8/2008 11:22:41 JCM - activity updated through activity BLDA022 from case BLD06-02303.
Routing - PLAN CHECK7/1/2008 7/8/2008 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  7/8/2008 DONE
Inspection Record Card- Bld  7/8/2008 DONE
Details
CHANGE STATUS TO (RDY)  7/8/2008 DONE
Telephone call  7/8/2008 DONE
Called John Price permit ready and fee given
Override - Parcel Holds  7/8/2008  
Plan resubmittals received  7/2/2008  
DetailsJohn Menard
Received resubmittals for plan modification: Received letter and two copies of sheets A2.17R10, A2.18R10; taken to John Menard
Plan resubmittals received  7/2/2008  
DetailsJohn Menard
Resubmittal for Plan Modification: Received letter and three copies of sheet S3.1; taken to John Menard
BLD-Framing/Rough-in6/27/20086/30/20087/1/2008ANR
DetailsDave Hannah
Dave- Floors 5 and 6 Phone #: ###-####
Plan resubmittals requested  7/1/2008 DONE
E-mailed the architect a copy of the structural and nonstructural review comments requesting revisions. JCM
Routing - PLANNING7/1/2008 7/1/2008 PASS
DetailsJosh Wilson
Routing - PLAN CHECK5/22/2008 7/1/2008 FAIL
DetailsJohn Menard
BLD-Framing/Rough-in6/25/20086/25/20086/26/2008PPART
DetailsDave Hannah
Brad Phone #: ###-#### fire proofing between buildings ok to keep going
Plan resubmittals received  6/24/2008  
DetailsTisha Gallop
Received resubmittal for plan modification: Received letter and three copies of structural calculations and sheets S1.0, S3.0, S3.1; taken to John Menard
Telephone call  6/24/2008 DONE
DetailsTisha Gallop
called Action Couriers for pick up of resubmittals of plan mod.
BLD-Concrete6/16/20086/17/20086/17/2008APART
DetailsDave Hannah
brad - ###-#### - 15th floor
BLD-Framing/Rough-in6/17/20086/17/20086/17/2008APART
DetailsDave Hannah
brad - ###-#### - close up inspection ext walls by stair towers floors 4-8
BLD-Other6/13/20086/16/20086/17/2008PNR
DetailsDave Hannah
brad - ###-#### - close up inspection
BLD-Other6/13/20086/13/20086/16/2008PPART
DetailsDave Hannah
brad - ###-#### - close up inspection stair tower sheetrock floors 0-5 ok for second layer
Override - Parcel Holds  6/16/2008  
Override - Parcel Holds  6/13/2008  
Override - Parcel Holds  6/13/2008  
BLD-Concrete6/5/20086/5/20086/11/2008PPART
DetailsDave Hannah
brad - ###-#### - 14th floor
BLD-Final6/10/20086/10/20086/10/2008PPASS
DetailsDave Hannah
brad - ###-#### - 14th floor
Plan resubmittals requested  6/10/2008 DONE
E-mailed the architect a copy of the structural comment list requesting revissions. JCM
BLD-Concrete6/4/20086/5/20086/6/2008APASS
DetailsDave Hannah
brad - ###-#### - 14th floor
Override - Parcel Holds  6/4/2008  
BLD-Energy code compliance5/30/20086/2/20086/2/2008APART
DetailsDave Hannah
###-#### - brad walls between ext garage and new bld levels 5 6 and 7 insulation ok ok to cover walls still need to check areas that will furred out around piping
Override - Parcel Holds  5/30/2008  
Routing Off Site - STRUCTURAL5/21/2008 5/29/2008 FAIL
DetailsJohn Menard
called Action Couriers for pick up - Received comment list from consulting structural engineer requesting revisions. JCM
BLD-Framing/Rough-in5/27/20085/28/20085/28/2008APART
DetailsDave Hannah
###-#### - dave ok to start covering stair towers floors 1 thru 6 and wall between garage and res 6th thru 1
BLD-Framing/Rough-in5/23/20085/27/20085/27/2008PCANC
DetailsTom Arcoraci
###-#### david
BLD-Concrete5/23/20085/27/20085/27/2008PPASS
DetailsTom Arcoraci
david ###-####
Override - Parcel Holds  5/27/2008  
Override - Parcel Holds  5/23/2008  
Override - Parcel Holds  5/23/2008  
Routing - PLANNING5/21/2008 5/22/2008 FAIL
DetailsJosh Wilson
Design Review application for changes not yet approved 5-22-08 JGW
Received Certificate of Value  5/16/2008 DONE
DetailsBethany Sullins
Plan Modification Accepted  5/16/2008  
DetailsJohn Menard
Plan Modification accepted to change the East end of the 17, 18th and roof levels to enclose the area between grid lines 9 & 10 on 3 sets of sheets A2.17DPR6, A2.17R9, A2.18DPR8, A2.18R9, A2.19DPR4, A2.19R5, A5.0R12, A5.1R6, A5.2R10, S1.17, S1.18, S1.19, S2.1, S4.1, S4.2, 2 Slab Analysis & Design Concept books and taken to John Menard 5-19-08 BAS
BLD-Concrete5/9/20085/12/20085/12/2008APART
DetailsDave Hannah
dave Phone #: ###-#### 11th floor mti on site ok deck to place concrete
BLD-Conference5/2/20085/2/20085/5/2008PPASS
DetailsDave Hannah
david Phone #: ###-####
BLD-Other5/2/20085/2/20085/5/2008PPASS
DetailsDave Hannah
david Note: also wall Phone #: ###-####
BLD-Concrete4/14/20084/15/20084/15/2008APART
DetailsDave Hannah
brad Phone #: ###-#### placing 10th floor
BLD-Concrete4/4/20084/7/20084/7/2008APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/4/2008 at 12:58:57 PM. Contact: ###-####. 9th floor
BLD-Concrete3/27/20083/28/20083/28/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/27/2008 at 6:58:18 AM. Contact: ###-####.placed with si observation.
BLD-Concrete3/6/20083/6/20083/6/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 3/6/2008 at 8:00:01 AM. Contact: ###-####.
BLD-Framing/Rough-in3/3/20083/3/20083/3/2008PPART
DetailsDave Hannah
dave - for basement Phone #: ###-#### ok to cover walls in basement
BLD-Concrete2/25/20082/25/20082/25/2008PPART
DetailsDave Hannah
brad Phone #: ###-####
BLD-Concrete2/11/20082/12/20082/12/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/11/2008 at 5:08:19 PM. Contact: ###-####.
BLD-Conference1/28/20081/29/20081/30/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 1/28/2008 at 12:14:45 PM. Contact: ###-####. pt deck third floor
BLD-Concrete1/10/20081/11/20081/11/2008PPART
DetailsJim Storey
brad Phone #: ###-####wip/first floor pt si pending reports.
BLD-Conference1/2/20081/2/20081/4/2008PDONE
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/31/2007 at 4:14:32 PM.
BLD-Concrete12/31/20071/2/20081/2/2008APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/31/2007 at 4:14:32 PM.
BLD-Concrete12/19/200712/20/200712/21/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/19/2007 at 3:14:52 PM. Contact: ###-####.
BLD-Foundation12/11/200712/11/200712/12/2007PPART
DetailsDave Hannah
david Phone #: ###-####
Override - Parcel Holds12/11/20071/1/190012/11/2007  
foundation only
BLD-Foundation12/4/200712/4/200712/4/2007PPART
DetailsDave Hannah
brad Phone #: ###-####
BLD-Foundation12/3/200712/4/200712/4/2007ADEFR
DetailsDave Hannah
brad Phone #: ###-####
Override - Parcel Holds12/3/20071/1/190012/3/2007  
foundation
BLD-Foundation11/29/200711/30/200711/30/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/29/2007 at 3:13:41 PM. Contact: ###-####.
BLD-Foundation11/26/200711/26/200711/27/2007PPART
DetailsDave Hannah
David Grant Phone #: ###-#### on site crew still installing column steel MTI on site they will be back tomorrow to do a final inspection befor placement also the project engineer will be on site to approve before concrete placement
BLD-Foundation11/13/200711/13/200711/14/2007PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/13/2007 at 9:41:15 AM. Contact: ###-####. mti on site for spec inpection
BLD-Concrete11/1/200711/1/200711/2/2007PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/1/2007 at 7:50:04 AM. Contact: ###-####. footing sw corner ok to pour
BLD-Foundation10/12/200710/15/200710/16/2007PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/12/2007 at 1:22:14 PM. Contact: ###-####.
BLD-Foundation9/20/20079/21/20079/24/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/20/2007 at 10:18:03 AM. Contact: ###-####. shot crete
BLD-Conference8/31/20079/4/20079/5/2007APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/31/2007 at 10:23:46 AM. Contact: ###-####.
BLD-Foundation8/31/20079/4/20079/5/2007ADONE
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/31/2007 at 10:22:08 AM. Contact: ###-####. pre con meeting on concrete
BLD-Foundation8/24/20078/27/20078/27/2007PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 8/24/2007 at 11:44:17 AM. Contact: ###-####. spec insp required
Telephone call  7/24/2007 DONE
(7/24/07) - Had a conference call with CH2MHILL (Wayne Kohler and Chris R.) and MTI (David Cram) concerning modified micro-pile design using a four inch grout layer I.L.O. a sleeve. It was determined that it would be difficult to maintain the 4 inch grout layer and that there would be some loads transferred to the existing garage foundation. It was unclear if this would be acceptable to CCDC. David Cram indicated he would contact John Price (project architect) and notify him that this may not be a viable option and that CCDC would have to agree to the loading on the existing foundation. A meeting may need to be held with CCDC and KPPF Engineers. If they decide to proceed with this design, full calculations and other data will be required to approve the grouted micro-pile design. JCM
Routing Off Site - STRUCTURAL7/24/2007 7/24/2007  
Had a conference call with CH2mhill (Wayne Kohler and Chris) and MTI (David Cram) concerning modified micro-pile design using a four inch grout layer I.L.O. a sleeve. It was determined that it would be difficult to maintain the 4 inch grout layer and that there would be some friction loads transferred to the existing garage foundation. It was unclear if this would be acceptable to CCDC. David Cram indicated he would contact John Price and notify him that this may not be a viable option and that CCDC would have to agree to the loading on the existing foundation. A meeting may need to be held with CCDC and KPPF Engineers. If they decide to proceed with this design, full calculations and other data will be required to approve the grouted micro-pile design.
(F) Reprint permit  7/24/2007 DONE
CHANGE STATUS TO (ISS)  7/24/2007 DONE
picked up and paid for plan mod
Plan resubmittals received  7/23/2007  
received 1 project letter,and 2 copys of sheet S1.03 taken to John M.
BLD-Conference7/17/20077/18/20077/18/2007APASS
DetailsDave Hannah
###-#### david
Plan assigned to (JCM)4/3/20074/3/20077/12/2007 PASS
7/12/2007 10:02:31 JCM - activity updated through activity BLDA022 from case BLD06-02303.
Routing - PLAN CHECK4/3/2007 7/12/2007 PASS
Routing Off Site - STRUCTURAL6/26/2007 7/12/2007 PASS
Called Action Courier for pick up of Resubmital of Geotechnical Engineer///6/26/07 @ 8:46am BAS - Received letter from consulting structural engineer approving resubmittals.
Plan Reviewer's activity  7/12/2007 PASS
Reviewed and approved plan modification to change footin and foundation design adjacent to the existing garage foundation, to add a trash chute between the first and fourth floors, change the north exterior elevation at floors three and four. Also, discussed with Scott A. changes requested by fire and redlined requirement to relocate fire water line from under building. JCM
PLANS/APPL TAKEN TO FRONT DESK  7/12/2007 DONE
Inspection Record Card- Bld  7/12/2007 DONE
Telephone call  7/12/2007 DONE
left vm for john price at ###-#### - permit ready and fees given
Permit Ready to Issue  7/12/2007 DONE
Plan resubmittals received  6/22/2007  
received materials testing & insp letter from David Cram (2 pages)& envelope with letter (3 copies) of materials testing & insp from David Cram & stamped with engineer seal. also "3" books of materials testing & inspection geotech engineering /plans taken to John Menard
Plan resubmittals received  6/5/2007 DONE
Received 1 project letter, and 3 copys of sheets A1.2,A2.0,A2.1 taken to John M.
Telephone call  6/1/2007 DONE
Telcon from Keith at DeBest indicating they now have a signed sprinker contract for this project. He would like to have a meeting to discuss design concepts. I agreed, and reviewed past discussions we have had with John Price and Jerry O'Neil on proposed design concepts and options. He will contact us within about a week to set up a specific date/time, after they have come up with more specific design proposals.
Telephone call  5/31/2007 DONE
Spoke with John Price regarding the location of the new fire pump room for the new building. John Price will be submitting a modified plan sheet showing the new pump room to be located at grade level with direct access to the exterior from the Front Street sidewalk. The fire marshal, Dave Hanneman, has reconfirmed that the stand pipe system in the new high rise building shall be an automatic wet type.
Routing - PLANNING5/22/2007 5/23/2007 PASS
Approved per DRH06-00390 and DRH07-00130
Plan resubmittals requested  5/22/2007 DONE
E-mailed the architect with a copy of the structural and nonstructural plan review comments requesting revisions.
Plan resubmittals received  5/22/2007 DONE
received 1 project letter, and 3 copys of sheet A10.4 taken to John M.
Routing Off Site - STRUCTURAL5/9/2007 5/22/2007 FAIL
Called Action Couriers for pick up - Received comment list from consulting structural engineer requesting additional revisions.
Plan resubmittals received  5/9/2007  
received transmittal letter from the arch office & (18) pages 3 sets each from Fine Engineering & "3" sets of plans including "3" sheets each of SO.1, SO.2, S1.O, S1.O1, S1.O2, S1.O3, & S4.1 plans taken to John Menard.
Plan resubmittals received  5/7/2007  
received "2" sheets of A5.O, & transmittal letter from the architects office--plans taken to John Menard
Plan resubmittals received  5/4/2007  
Plan resubmittals received  5/4/2007 DONE
Received 1 project letter, and 2 copys of sheets A2.1,A2.2,A2.3,A2.4,A8.0,A9.0,A10.4 taken to John M
Plan resubmittals requested  4/25/2007 DONE
E-mailed the architect a copy of the structural comment list requesting revisions. JCM
Routing Off Site - STRUCTURAL4/16/2007 4/25/2007 FAIL
Called Action Couriers for pick up 1:25 - Received comment list from consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  4/16/2007 DONE
E-mailed the architect requesting additional plan revisions for the plan modification request.
Plan Modification Accepted  4/3/2007  
plan mod excepted for bld06-02303 for the redesign of sheets A2.0,S1.0,S1.01,S1.02, shows revised mat foundation, A2.1,A2.2,A2.3,A2.4- shows new trash chute, A2.3 & A2.4 - shows revised north edge of parking levels
Plans ACCEPTED BY PLAN TECH  4/3/2007  
(F) Reprint permit  2/2/2007  
Issue PAID IN FULL permit  2/1/2007 DONE
MISC ACTIONS  1/31/2007 DONE
double checked permit fees before ready to issue
Telephone call  1/31/2007 DONE
talked to john price at ###-#### to verify plans are ready & need achd before picking up & gc & rce #
Routing - FIRE1/29/2007 1/30/2007 PASS
Attached updated review comments to plans.
Routing - PLAN CHECK1/30/2007 1/30/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/30/2007 DONE
Inspection Record Card- Bld  1/30/2007  
Plan assigned to (JCM)8/10/2006 1/30/2007 PASS
1/30/2007 10:17:07 JCM - activity updated through activity BLDA022 from case BLD06-02303.
Routing - PLAN CHECK1/25/2007 1/29/2007  
Routing - PUBLIC WORKS1/24/2007 1/25/2007 PASS
Plan resubmittals received  1/25/2007  
rec'd 1 transmittal cover - 1 response letter - 3 copies of sheet #s A1.1 - taken to John Menard
Routing - PLAN CHECK12/27/2006 1/24/2007  
Plan resubmittals received  1/23/2007 DONE
Received one transmittal letter with three revised sheets of A1.2 and one fire review response letter all taken to John M.
Routing - PUBLIC WORKS12/26/2006 12/27/2006 FAIL
Trash proposal unworkable. Contact Pam Williams at ###-####
Routing - PLUMBING12/27/2006 12/27/2006 PASS
per plans and 2003 upc
Routing - PLUMBING12/21/2006 12/26/2006 FAIL
routed to public works for pretrearment and sewer connection approval prior to plumbing review.
Plan Reviewer's activity  12/21/2006 PASS
Reviewed and approved resubmitted plans revisions. JCM
Plan resubmittals received  11/29/2006  
received project letter from the architects office & "3" sets of plans including "3" sheets each of A2.1, A2.3, A2.4, A9.O, A10.1, M1.3, M1.4, & M5.0---plans taken to john menard
Telephone call  11/28/2006 DONE
called action courier for pickup
Routing Off Site - STRUCTURAL11/28/2006 11/28/2006 ----
Sent a copy of the report by kpff on the concerns raised by CCDC.
Routing - FIRE11/15/2006 11/20/2006 FAIL
Faxed updated resubmittal requirements to the architect. The fire department will require current fire sprinkler riser/pump room configuration requirements for the new high rise addtiion. Attached updated review comments to plans.
Routing - PLAN CHECK11/6/2006 11/15/2006  
Plan resubmittals received  11/15/2006  
received (4) pages from the architects office & (3) sets each of A2.O, A2.1, & E10.O plans taken to john menard
Routing - FIRE11/3/2006 11/6/2006 FAIL
Faxed resubmittal items to architect. Attached review comments into plans.
Plan resubmittals requested  11/3/2006 DONE
E-mailed the architect a copy of the second plan review requesting revisions. JCM
Routing - PLAN CHECK9/22/2006 11/3/2006 FAIL
Routing Off Site - STRUCTURAL10/26/2006 11/1/2006 PASS
Called Action Couriers for pick up - Received an e-mailed letter from the consulting structural engineer approving the resubmittals. JCM
Plan resubmittals received  10/30/2006  
Received 1 project letter, 3 open garage calcs, & 3 copys of sheets A0.0,A0.1,A1.0,A1.2,A2.1,A2.3,A2.5,A2.7,A2.9,A2.19,A3.5.2,A6.3,A9.0,A9.2,A10.0,A10.1,E1.0,E2.0,E3.0,E4.0,E5.0E6.0,E7.0,E8.0,E9.0,E10.0,E11.0,E12.0,E13.0,S0.1 taken to John M.
Plan resubmittals received  10/24/2006 DONE
Received 1transmittal,1 response, 3 calcs, & 3 copys of sheets S0.1,S0.2,S4.1,S4.2,S4.3,S4.4 taken to John M.
1st review completed  9/22/2006 FAIL
Routing - FIRE9/19/2006 9/22/2006 FAIL
Faxed resubmittal items to John Price. Attached review comments to plans.
Plan resubmittals requested  9/19/2006 DONE
E-maield the architect a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK8/28/2006 9/19/2006 FAIL
John M.
Routing Off Site - STRUCTURAL8/10/2006 9/13/2006 FAIL
Called Action Couriers for pick up - Received an e-mailed comment list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  9/13/2006 DONE
E-mailed the architect a copy of the commnet list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals received  9/11/2006  
Received 7pg. plumbing response; taken to John Menard
Routing - PLANNING8/22/2006 8/28/2006 PASS
Routing - PLUMBING8/16/2006 8/22/2006 FAIL
provide secondary roof drainage. provide approval to use the parking lot roof drainage system for this building, provide existing system loading and sizing. need public works pretreatment approval prior to plumbing review approval.
Routing - Erosion and Sediment8/16/2006 8/16/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS8/9/2006 8/16/2006 FAIL
Need to show location of sewer connection to sewer main. Contact Jim Pardy ###-####: Trash proposal unworkable. Contact Pamela Williams ###-####
Routing - PLANNING Land Div8/9/2006 8/9/2006 PASS
Plans ACCEPTED BY PLAN TECH  8/9/2006  
Plan routing begun/NEW & ADDTN  8/9/2006  
Application received  8/8/2006