Permit Information
Permit NumberBLD06-02320
StatusFinaled
Name CRB LLC
Site Address 3005 -3059 W CRESCENT RIM DR
Project NameCRESCENT RIM #2 #3-PARKING
Customer Number 
ePlanReviewNo
Description
RCE 19740 CRB LLC (CRESCENT RIM PARKING GARAGE BLDGS 2 & 3) To construct a new 32,257, square feet, enclosed, basement parking garage, below a three hour horizontal assembly per IBC Section 508.2, the installation of a NFPA 13 fire sprinkler system is required through out this structure. NOTE: This permit is for a shell only and includes under floor plumbing, electrical, refer to BLD06-02901 for the grading permit. All additional work which includes: interior finishes, electrical, plumbing and mechanical shall be completed under BLD 06-02323. MJP CUP 05-00015 * DRH 05-00397
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection7/8/20127/9/20127/12/2012APART
DetailsForrest France
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil
DOC - Permit Finaled  7/11/2012 DONE
DetailsChristina Prado
Per Bob & Jason -- ok to final permit for garage only at crescent rim condos
BLD-Final7/9/20127/10/20127/10/2012ACANC
DetailsTom Arcoraci
Call prior to going Phone #: 6318646 >> Inspection requested via mobile web by Gil
FIRE-Conference4/25/20124/25/20124/26/2012ACANC
DetailsTroy Cobbley
Bob phone #: ###-####
BLD-Aging Inspection2/7/20122/7/20122/7/2012 PEND
DetailsTom Arcoraci
Inspection Record Card- Bld  1/11/2012 DONE
BLD-Wall cover11/8/201111/8/201111/8/2011PPASS
DetailsTom Arcoraci
BLD-Aging Inspection11/8/201111/8/201111/8/2011 PART
DetailsTom Arcoraci
BLD-Aging Inspection8/9/20118/9/20118/9/2011 PASS
DetailsTom Arcoraci
BLD-Conference5/10/20115/11/20115/10/2011PCANC
DetailsTom Arcoraci
We would like to meet with you and the fire inspector about egress from the pool area. Is it possible to get you both here at the same time? Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
BLD-Conference5/5/20115/6/20115/6/2011PPASS
DetailsTom Arcoraci
BLD-Energy code compliance5/5/20115/6/20115/6/2011ACANC
DetailsTom Arcoraci
BLD-Energy code compliance5/4/20115/5/20115/5/2011APASS
DetailsTom Arcoraci
2nd floor bldg 3 insulation. Phone #: ###-#### >> Inspection requested via web by Bob Thornton
BLD-Wall cover4/27/20114/28/20114/28/2011APASS
DetailsTom Arcoraci
Framing inspection for bldg 3 level 2. Phone #: ###-#### >> Inspection requested via web by Bob Thornton
BLD-Energy code compliance4/25/20114/26/20114/26/2011APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by Bob Thornton
BLD-Framing/Rough-in4/22/20114/25/20114/25/2011APASS
DetailsTom Arcoraci
We are ready to cover the changes in the models. Phone #: ###-#### >> Inspection requested via web by Bob Thornton
BLD-Conference4/13/20114/14/20114/14/2011PPASS
DetailsTom Arcoraci
BLD-Conference4/12/20114/14/20114/13/2011ACANC
DetailsTom Arcoraci
BLD-Conference4/1/20114/11/20114/12/2011APASS
DetailsTom Arcoraci
talked on final issues
BLD-Conference4/1/20114/1/20114/1/2011PPASS
DetailsTom Arcoraci
Tom, Call me when you head this way. Phone #: ###-#### >> Inspection requested via web by Bob Thornton
BLD-Aging Inspection2/28/20112/28/20112/28/2011 NR
DetailsTom Arcoraci
BLD-Aging Inspection12/27/201012/27/201012/27/2010 PART
DetailsTom Arcoraci
BLD-Aging Inspection10/25/201010/25/201010/25/2010 PART
DetailsTom Arcoraci
BLD-Aging Inspection8/23/20108/23/20108/23/2010 PART
DetailsTom Arcoraci
BLD-Energy code compliance6/22/20106/23/20106/23/2010PCANC
DetailsTom Arcoraci
Building 2 fourth floor insulation inspection. Please call to coordinate Inspection requested from web by: Bob Thornton Phone #: ###-#### should 06-02323
BLD-Aging Inspection5/31/20105/31/20106/2/2010 PASS
DetailsTom Arcoraci
BLD-Aging Inspection3/29/20103/29/20103/29/2010 PASS
DetailsTom Arcoraci
Case Summary (BLD)  3/15/2010 DONE
BLD-Aging Inspection1/26/20101/26/20101/26/2010 PASS
DetailsTom Arcoraci
BLD-Other11/23/200911/23/200911/23/2009PPASS
DetailsTom Arcoraci
BLD-Aging Inspection11/23/200911/23/200911/23/2009 PASS
DetailsTom Arcoraci
BLD-Aging Inspection9/22/20099/22/20099/22/2009 PASS
DetailsTom Arcoraci
BLD-Other6/24/20096/25/20096/25/2009APASS
DetailsTom Arcoraci
BLD-Aging Inspection6/1/20096/1/20096/1/2009 PASS
DetailsTom Arcoraci
BLD-Aging Inspection3/30/20093/30/20093/30/2009 PASS
DetailsTom Arcoraci
BLD-Aging Inspection1/26/20091/26/20091/26/2009 PASS
DetailsTom Arcoraci
BLD-Aging Inspection11/24/200811/24/200811/24/2008 PASS
DetailsTom Arcoraci
BLD-Energy code compliance9/24/20089/24/20089/24/2008PPASS
DetailsJim Sly
Bob ###-####
BLD-Energy code compliance9/23/20089/24/20089/23/2008PPART
DetailsJim Sly
If you have issues call Zac @ ###-####. Dennis from Johnson Drywall is ###-####. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
4 units ...1st floor OK
BLD-Conference9/22/20089/24/20089/23/2008PCANC
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference9/22/20089/24/20089/23/2008ACANC
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference9/22/20089/23/20089/23/2008PPART
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
OK to insulate 4 units ....main floor Bldg 3....OK to rock 4th floor ceilings.
BLD-Conference9/22/20089/23/20089/23/2008ACANC
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference9/22/20089/22/20089/22/2008PDONE
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference9/19/20089/19/20089/19/2008PDONE
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
C/N Talked about maintaining integrety of 1hr walls where ducts or vents run through.
BLD-Wall cover9/17/20089/18/20089/18/2008AFAIL
DetailsJim Sly
I would like to inspect 1st floor bldg 3 units to insulate and sheetrock. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
Looked at 4 unit in Bldg #3.....Need all UL listings for all trade.... ceiling and wall penitrations...... Need listing for protection pads on plumbing washer boxes.....Dryer box and ducting in 1hr wall....Architect to address......OK to insulate and add channel to ceiling only......Check for fireblocking at double walls (at ceiling line).
BLD-Framing/Rough-in9/10/20089/10/20089/10/2008PPART
DetailsMike Jordan
ok to prerock 2nd floor corridor lids.
BLD-Framing/Rough-in9/9/20089/10/20089/10/2008ACANC
DetailsMike Jordan
Re-inspect the 2nd floor corridor ceiling for pre-rock on bldg 3. Phone #: ###-#### Internet Inspection Request from: Bob Thornton. reshduled for this afternoon.
BLD-Conference9/4/20089/5/20089/5/2008APASS
DetailsJim Storey
Inspect bldg 3 corridors for pre-rock on 2nd and 3rd floor. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference9/1/20089/2/20089/2/2008APART
DetailsJim Sly
Inspect roof trusses. Call me when you are on your way. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
Preliminary truss inspection prior to pre-rock and frame inspection....Trusses appear OK in Bldg #2 & #3.
BLD-Conference8/28/20088/29/20088/29/2008ADONE
DetailsMike Jordan
Look at the 4th floor ceiling in bldg 3 for pre-rock. Phone #: ###-#### Internet Inspection Request from: Bob Thornton. Contractor wants to change termination piont of refuse chute. Wants to terminate at 4th floor ceiling instead of continueing thru roof deck. Noted to contractor to have architect submit new detail to plan review for approval.
BLD-Framing/Rough-in8/29/20088/29/20088/29/2008APART
DetailsMike Jordan
Look at the 4th floor ceiling in bldg 3 for pre-rock. Phone #: ###-#### Internet Inspection Request from: Bob Thornton. ok to pre rock 4th floor corridor flat ceiling areas only.
BLD-Conference8/22/20088/22/20088/22/2008PPART
DetailsMike Jordan
Phone #: ###-#### Internet Inspection Request from: Bob Thornton.. On site to review opening protection for can lights in floor ceiling assemblies, a second layer of 5/8 type X needs added for box outs, firecaulk seems. Also inspected lid on 4thfloor corridor for pre rock, some areas still need to be firecaulked, and some additional straps need to be added at roof drain penetrations through top plates.
BLD-Framing/Rough-in8/4/20088/5/20088/5/2008APART
DetailsMike Jordan
Let look at 4th floor areas to pre rock and review the can lights Phone #: ###-#### Internet Inspection Request from: Bob Thornton. Talk to contractor about can lights in floor ceiling assembly and required protection.
BLD-Conference7/17/20087/17/20087/17/2008PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in7/9/20087/9/20087/9/2008APART
DetailsTom Arcoraci
Covering the 1st floor corridor ceiling Phone #: ###-#### Internet Inspection Request from: Bob Thornton wip ok
BLD-Conference6/26/20086/30/20086/30/2008APASS
DetailsTom Arcoraci
BLD-Conference6/26/20086/27/20086/27/2008APASS
DetailsTom Arcoraci
BLD-Other6/25/20086/26/20086/26/2008APASS
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Bob Thornton
Meeting  5/15/2008 DONE
Meeting with Dave Hanneman, Mark Senteno, Treasure Valley Fire Protection, Bryan Johnson and Sam Rogers regarding FDC and standpipe issues.
The Fire Marshal, Dave Hanneman, has agreed to allow the dry standpipe throughout the parking garage and respective stairwells within buildings #2 & #3. The location of the FDC for the fire sprinkler system serving building 2 & 3 will be located at the southeast portion of building #3 at grade level, within 100 feet of the approved fire department vehicle access roadway, accessed from the northeast property entrance, along Crescent Rim Drive. Approved signage shall be installed along Crescent Rim Drive at this northeast driveway entrance directing FD personnel to the FDC location to the South of building #3. An additional FD approved sign shall be located at the southeast corner of building #3, directing FD personnel to the FDC location south of building #3.

BLD-Framing/Rough-in5/8/20085/8/20085/8/2008PPART
DetailsTom Arcoraci
wip ok
BLD-Framing/Rough-in5/7/20085/8/20085/8/2008APART
DetailsTom Arcoraci
Look at shear walls and framing progress. Phone #: ###-#### Internet Inspection Request from: Bob Thornton wip ok
BLD-Framing/Rough-in4/25/20084/25/20084/25/2008PPART
DetailsTom Arcoraci
wip ok shesr
BLD-Framing/Rough-in4/24/20084/25/20084/25/2008APART
DetailsTom Arcoraci
Look at shear walls and progress. Phone #: ###-#### Internet Inspection Request from: Bob Thornton wip ok 408
BLD-Conference4/9/20084/11/20084/11/2008PPASS
DetailsTom Arcoraci
The Architect would like to meet with us Friday, preferably after 1:30, to discuss the 2 hour assembly at the south stairs. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference4/9/20084/9/20084/9/2008PPASS
DetailsTom Arcoraci
I need to talk to you about installation of the HM jam in the 2 hour shaft. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference3/27/20083/27/20083/27/2008PPASS
DetailsTom Arcoraci
Lets talk about stair landings. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Conference3/25/20083/25/20083/25/2008PPASS
DetailsTom Arcoraci
BLD-Conference3/24/20083/25/20083/25/2008APASS
DetailsTom Arcoraci
BLD-Conference3/14/20083/14/20083/14/2008PPASS
DetailsTom Arcoraci
BLD-Conference3/12/20083/14/20083/14/2008APASS
DetailsTom Arcoraci
BLD-Conference3/13/20083/13/20083/13/2008PPASS
DetailsTom Arcoraci
BLD-Conference3/10/20083/14/20083/13/2008APASS
DetailsTom Arcoraci
BLD-Conference3/10/20083/12/20083/12/2008APASS
DetailsTom Arcoraci
BLD-Conference3/7/20083/10/20083/10/2008APASS
DetailsTom Arcoraci
BLD-Conference3/6/20083/7/20083/7/2008APASS
DetailsTom Arcoraci
Will you meet with me and the framer to discuss shear wall etc. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Aging Inspection1/9/20081/9/20081/9/2008 PASS
DetailsTom Arcoraci
BLD-Conference9/28/20079/28/20079/28/2007PPASS
DetailsTom Arcoraci
Lets talk about penetrations etc. Phone #: ###-#### Internet Inspection Request from: Bob Thornton
BLD-Aging Inspection8/30/20078/30/20078/30/2007 NR
DetailsTom Arcoraci
BLD-Aging Inspection5/21/20075/21/20075/21/2007 PASS
DetailsTom Arcoraci
wip
Plan resubmittals received  3/15/2007  
received transmittal letter from erstad arch & "3" sets of plans including S3.01, S3.03, S3.04, S2.05, S2.06-F, S2.06-R, S2.11, S2.12-F, S2.12-R---plans taken to mike phillips
BLD-Foundation3/13/20073/14/20073/14/2007APASS
DetailsTom Arcoraci
Special inspection by Strata. Pour at noon Phone #: ###-#### wip ok
BLD-Foundation3/7/20073/9/20073/9/2007APASS
DetailsTom Arcoraci
Pouring walls at noon. Special inspection by Strata Phone #: ###-####
BLD-Footing2/5/20072/6/20072/6/2007APART
DetailsTom Arcoraci
Pouring at noon. Special inspection by Strata as always. Phone #: ###-#### spec insp
BLD-Footing1/30/20071/31/20071/31/2007PPASS
DetailsTom Arcoraci
###-#### spec insp
BLD-Footing1/30/20071/31/20071/31/2007APASS
DetailsTom Arcoraci
###-#### Bob spec insp
BLD-Footing1/26/20071/29/20071/29/2007APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 1/26/2007 at 3:29:54 PM. spec insp
Telephone call  1/26/2007  
spoke with Bob from CRC LLC (a general contractor) told him only Holm construction can schedule inspection on this permit
(F) Reprint permit  12/21/2006  
Plan assigned to (M_P)8/14/20068/14/200612/20/2006 PASS
12/20/2006 09:56:24 M_P - activity updated through activity BLDA022 from case BLD06-02320.
Routing - PLANNING12/18/2006 12/20/2006 PASS
Approved per the DR and the CUP.
Routing - PLAN CHECK12/20/2006 12/20/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/20/2006 DONE
Inspection Record Card- Bld  12/20/2006  
Telephone call  12/20/2006 DONE
called ###-#### and left message for Dave Holm that permit is ready
Permit Ready to Issue  12/20/2006 DONE
Issue PAID IN FULL permit  12/20/2006 DONE
Routing - PLAN CHECK12/15/2006 12/18/2006  
Routing to Planning.
Routing Off Site - STRUCTURAL12/8/2006 12/18/2006 PASS
Called Action Courier for pick up @8:52 on 12/8/06 BAS
Routing - PLAN CHECK12/12/2006 12/15/2006 PEND
Waiting for others to approve prior toissuing permit.
Routing Off Site - STRUCTURAL12/14/2006 12/15/2006 PASS
Called action Courier for pick up of 1 structural calcs book volume 2///12/14/06 @ 3:55
Routing - FIRE12/15/2006 12/15/2006 PASS
Attached updated review comments to plans.
Routing - PLUMBING12/11/2006 12/12/2006 PASS
Resubmittals from Bob Tikker. garage only. see bld06-02316 for review comments
Plan resubmittals received  12/11/2006  
Received three copies of the following pages: A300, A310, A320, A321. Received 4 copies of the following pages: C3.1, C5.0; taken to Mike Phillips
Routing - PLANNING12/4/2006 12/8/2006 FAIL
Sarah SchaferSarah Schafer
Failed DR and CUP review. Letter being sent to applicant with explination. Still needs drainage easement shown on plans, elevations that match DR approved, pork chop in Peasly Dr.
Routing - PLANNING Land Div12/8/2006 12/8/2006 PASS
Approved. Parcels are combined.
Plan resubmittals received  12/8/2006  
Received 4 copies of pages M100, M200, M201, M202, M203; taken to Mike Phillips
Plan resubmittals received  12/8/2006  
Received 2 copies of structural calcs for wood permit submittal- volumes 1 & 2, 3 copies of the following sheets--S2.07, S2.08, S2.09, S2.10, S2.12W, S2.13, S2.14, S2.15, S2.16, S2.18W, S2.19, S2.20, S2.21, S5.00, S5.01, S5.02, S5.03, S5.04, S6.00, S1.00, S1.01, S2.01W, S2.02, S2.03, S2.04, S2.06W and 1 set of everything sent to outside Structural engineer and the rest taken to Mike Phillips
Plan resubmittals received  12/7/2006  
Received 4 copies of sheets A001, A200, A201, A205, A206, A211, A212, A217, A218 and taken to Mike Phillips
Plan resubmittals received  12/6/2006  
Received 3 sets of DR meeting of floor plan & elevations and taken tot Mike Phillips
Routing - PLUMBING12/4/2006 12/4/2006 FAIL
no plans
Plan resubmittals received  12/4/2006 DONE
Received Structural Engineer resubmittals in the form of 1 cover letter; 1 copy of responses to building review comments w/additional structural calculations; 1 copy of geotechnical addendum dated 7/7/06. Copy given to Mike Phillips and sent to outside engineer for review.
Routing - PLAN CHECK10/16/2006 12/4/2006  
Routing resubmittals to plumbing, planning, land division and fire.
Plan resubmittals received  11/24/2006  
Inserted new sheet into the plans on 11/28/06/ Received transmittal sheet, three copies of 12pg. letter of response, three copies of application for Project Start Up for Special Inspections, 2pg. repsonse letter from Tikker Eng., 11pg. electrical response, 17pgs. on Fire Suppression, two copies of the following pages: FP100, FP101, FP102, FP103, FP104, FP105, FP106, FP107, FP108, FP109, FP110; four copies of the following pages: L101, M500, M504, M509, M514, E1.9, E2.1.1L, E2.2.0L, E2.2.1L, E2.3.0L, E2.3.1L, E2.4.1L; five copies of the following pages: A001, A002, A003, A010, A011, A012, A013, A014, A100, A101, A102, A110, A111, A112, A113, A114, A115, A200, A201, A202, A203, A204, A205, A206, AA207, A208, A209, A210, A211, A212, A213, A214, A215, A216, A217, A218, A219, A220, A221, A230, A231, A232, A233, A234, A235, A236, A237, A238, A239, A240, A241, A242, A243, A244, A245, A246, A247, A248, A249, A260, A261, A262, A270, A271, A272, A300, A301, A302, A303, A304, A305, A330, A360, A361, A362, A363, A364, A365, A500, A700, A701, A702, A703, A704, A705, A706, A707, A710, A800, A801, A802, A803, A804, A810, A821, A900, A902; taken to Mike Phillips
Routing - FIRE10/12/2006 10/16/2006 FAIL
Faxed review / resubmittal items comments to architect.
1st review completed  10/16/2006 FAIL
DetailsMike Phillips
Routing - PLAN CHECK9/25/2006 10/12/2006 FAIL
Plan review completed, sent correction report to the architect requesting additional information be submitted for further review prior to issuing permit.
Routing - FIRE9/21/2006 9/25/2006 FAIL
Faxed resubmittal items to architect. Reviewed for water supply and access only.
Routing - PLAN CHECK9/6/2006 9/21/2006 PEND
PLANS ROUTED TO FIRE FOR ACCESS & WATER REQUIREMENTS ONLY. Review for all building code requirements not completed at this time.
Routing - PLANNING9/5/2006 9/6/2006 FAIL
Failed both DR and CU. Letter to be issued. DRH05-00397 and CUP05-00015.
Routing - PLUMBING8/30/2006 9/5/2006 FAIL
plans are incomplete, please address the above listed items.
Routing - Erosion and Sediment8/29/2006 8/30/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS8/22/2006 8/29/2006 PASS
Routing Off Site - STRUCTURAL8/15/2006 8/28/2006 FAIL
8/15/06 - Called Action Courrier for pick up 8/15/06 @ 12:30pm BAS. Original submittal includes structural for concrete package only.
8/28 - Concrete package review received. Review failed.
Routing - Addressing8/24/2006 8/24/2006 PASS
Routing - PLANNING Land Div8/14/2006 8/22/2006 FAIL
Failed because parcels not combined.
Plan routing begun/NEW & ADDTN  8/14/2006  
Plans ACCEPTED BY PLAN TECH  8/14/2006  
Application received  8/11/2006