PubWorks Occupancy Approval | 3/28/2007 | 3/28/2007 | 3/28/2007 | | DONE |
|
|
|
Final inspection signed off 03/26/07 by R. Anderson.
|
Letter of compliance | | | 3/26/2007 | | DONE |
|
|
|
Letter of Compliance issued 3-26-07
|
Code Occupancy Approval | 3/22/2007 | 3/22/2007 | 3/22/2007 | P | PASS |
Dena Gambrel
|
|
|
3-22-07 Final Occupancy Signed.
|
FIRE-Final Inspection | 3/22/2007 | 3/22/2007 | 3/22/2007 | P | PASS |
Troy Cobbley
|
|
|
LIfe safety passed.
|
BLD-Final | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | PASS |
Tom Arcoraci
|
|
|
Vick; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
BLD-Foundation | 2/14/2007 | 2/15/2007 | 2/15/2007 | A | PART |
Jim Sly
|
|
|
vic- early morning; Phone #: ###-#### Internet Inspection Request from: Victoria Beall Kiosk......Special insp req on project......Kiosk foot/wall OK pending special insp, tests and approvals from MTI
|
BLD-Footing | 2/14/2007 | 2/15/2007 | 2/15/2007 | A | CANC |
Tom Arcoraci
|
|
|
vic - early morn if possible; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Footing | 2/5/2007 | 2/6/2007 | 2/6/2007 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/5/2007 at 12:56:43 PM. spec insp
|
BLD-Conference | 2/2/2007 | 2/5/2007 | 2/5/2007 | A | PASS |
Tom Arcoraci
|
|
|
vic; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
CHANGE STATUS TO (ISS) | | | 1/16/2007 | | DONE |
|
|
|
already pd on 1/11/06/mls
|
Telephone call | | | 1/11/2007 | | |
|
|
|
telephone call with someone from Meng-Hannan said he mailed in check for fees due, told him fees still due and need ACHD
|
Telephone call | | | 12/7/2006 | | |
|
|
|
talked to jake at ###-#### to verify plans are ready. & need achd
|
Telephone call | | | 10/4/2006 | | DONE |
|
|
|
tlk to nicole anderson ###-#### that permit and fees are ready to be picked up needs ACHD, GC, RP
|
Permit Ready to Issue | | | 10/4/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/3/2006 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 8/17/2006 | | 10/2/2006 | | PASS |
|
|
|
10/2/2006 15:40:50 MLO - activity updated through activity BLDA022 from case BLD06-02357.
|
Plan resubmittals received | | | 10/2/2006 | | DONE |
|
|
|
Received 1 letter of transmittal ,2 structural calcs,2 copys of sheets A1,A1.1,AB1 OF 1,E1 OF 4,E2 OF 4, E3 OF 4,E4 OF 4 taken to Mike O.
|
Plan resubmittals received | | | 10/2/2006 | | |
|
|
|
Received 2 design calcs taken to Mike Otto
|
Case Summary (BLD) | | | 10/2/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 10/2/2006 | | 10/2/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2006 | | DONE |
|
|
|
|
Routing - FIRE | 8/31/2006 | | 9/5/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 9/5/2006 | | FAIL |
|
|
|
Failed plan check.
|
Plan resubmittals requested | | | 8/31/2006 | | DONE |
|
|
|
Metal building plans, foundation plans not provided
|
Routing - PLAN CHECK | 8/29/2006 | | 8/31/2006 | | FAIL |
|
|
|
corrections sent to Great Basin Engineering
|
Routing - PLANNING | 8/28/2006 | | 8/29/2006 | | PASS |
|
|
|
DRH06-00267- Josh Wilson
|
Routing - PLUMBING | 8/28/2006 | | 8/28/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 8/23/2006 | | 8/28/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals received | | | 8/24/2006 | | |
|
|
|
Received transmittal letter, 2 copies of structural calculations, 2 copies of the following pages: E1, E2, E3, EL1, EL2, M1, F1; taken to Mike Otto
|
Routing - PUBLIC WORKS | 8/22/2006 | | 8/23/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 8/18/2006 | | 8/22/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/18/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/17/2006 | | DONE |
|
|
|
|
Application received | | | 8/16/2006 | | |
|
|
|
|