Case Summary (BLD) | | | 1/6/2011 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 1/4/2011 | 1/4/2011 | 1/4/2011 | P | PASS |
Perry Paine
|
|
|
questions on site drainage requirements i.e. protecting adjacent lots
|
Case Summary (BLD) | | | 1/4/2011 | | DONE |
|
|
|
|
BLD-Final | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | PASS |
Tony Young
|
|
|
cof o issued
|
DOC - Permit Finaled | 8/29/2007 | 8/29/2007 | 8/29/2007 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Conference | 8/27/2007 | 8/28/2007 | 8/28/2007 | P | PASS |
Tony Young
|
|
|
Craig ###-####. I left as msg. for Terry Records 8/27. Internet Inspection Request from: Tracey Greenlee all ok for final except need smoke det in lower bedroom
|
BLD-Grading Inspection | 8/28/2007 | 8/28/2007 | 8/28/2007 | | DONE |
|
|
|
final grading and drainage approved
|
BLD-Final | 8/24/2007 | 8/27/2007 | 8/27/2007 | A | NR |
Tony Young
|
|
|
craig Phone #: ###-#### need hillside and trades 1st
|
BLD-Energy code compliance | 2/21/2007 | 2/22/2007 | 2/22/2007 | A | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 2/16/2007 | 2/20/2007 | 2/20/2007 | A | PASS |
Tony Young
|
|
|
craig ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ext. shear and frame ok,, ok to insulate
|
BLD-Framing/Rough-in | 2/12/2007 | 2/13/2007 | 2/13/2007 | A | FAIL |
Tony Young
|
|
|
craig; Phone #: ###-#### Internet Inspection Request from: Victoria Beall shear not per plan,, need seal package prior to frame inspection
|
BLD-Other | 12/11/2006 | 12/11/2006 | 12/11/2006 | P | PASS |
Tom Arcoraci
|
|
|
cliff - note: re-bar - wall; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 12/7/2006 | 12/8/2006 | 12/8/2006 | A | PART |
Jim Sly
|
|
|
CLIFF; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles OK pending sub grade approval.
|
PubWorks Subgrade Approval | 12/8/2006 | 12/8/2006 | 12/8/2006 | | DONE |
|
|
|
Received letter from geotec approving footing subgrade. Okay to schedule footing inspection.
|
Issue PAID IN FULL permit | | | 11/17/2006 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 9/27/2006 | 9/27/2006 | 9/28/2006 | | PASS |
|
|
|
9/28/2006 13:38:55 SRZ - activity updated through activity BLDA022 from case BLD06-02387.
|
Case Summary (BLD) | | | 9/28/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/28/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/28/2006 | | |
|
|
|
|
Telephone call | | | 9/28/2006 | | DONE |
|
|
|
spoke to tracy@###-####/told permit was ready, permit#, lot & block, and fees
|
Routing - PLAN CHECK | 9/1/2006 | | 9/28/2006 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 8/18/2006 | 8/18/2006 | 9/27/2006 | | DONE |
|
|
|
|
Routing - FIRE | 8/28/2006 | | 8/29/2006 | | PASS |
|
|
|
No fire sprinklers required (Highlands Hackberry no. 5)
|
Routing - Erosion and Sediment | 8/28/2006 | | 8/28/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 8/25/2006 | | 8/28/2006 | | PASS |
|
|
|
See redlines on site plan. The eaves project too far into setback. Reduce the eave width or move the house further back on the lot.
|
Routing - PUBLIC WORKS GRADING | 8/21/2006 | | 8/25/2006 | | PASS |
|
|
|
Approved as Category 3
|
Routing - PUBLIC WORKS | 8/25/2006 | | 8/25/2006 | | PASS |
|
|
|
|
Routing - Addressing | 8/18/2006 | | 8/21/2006 | | PASS |
|
|
|
|
Application received | | | 8/18/2006 | | |
|
|
|
|