Inspection Record Card- Bld | | | 9/20/2007 | | DONE |
|
|
|
|
DOC-Permit Expired | 4/9/2007 | 4/9/2007 | 4/9/2007 | | DONE |
Tom Arcoraci
|
|
|
Permit expired by limitations.
|
BLD-Aging Inspection | 1/30/2007 | 1/30/2007 | 1/30/2007 | | NR |
Tom Arcoraci
|
|
|
|
(F) Reprint permit | | | 11/1/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/26/2006 | | 10/31/2006 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 10/31/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/31/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/31/2006 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 10/27/2006 | | 10/31/2006 | | PASS |
|
|
|
Pass for grading and drainage only. Still need to vacate utility easements under SOS06-00017. To be heard by the Boise City Council on November 14, 2006. Also parcels need to be combined prior to issuance of building permit for any structure.
|
Routing - PLANNING | 10/24/2006 | | 10/26/2006 | | PASS |
|
|
|
Site plans submitted 10/24/06 are approved per the current CUP and are approved for grading and drainage only. Applicant has been notified that they are required to submit for a Design Review modification.
|
Plan resubmittals received | | | 10/24/2006 | | DONE |
|
|
|
Received 4 copys of ST1.1 sheets put with plans and routed back to Sara S.
|
Routing - PLANNING | 10/12/2006 | | 10/13/2006 | | FAIL |
|
|
|
Location of the fire accesses are need a variance for their location within the setback. Applicant has been contacted and we are trying to resolve the issues.
|
Plan resubmittals received | | | 10/12/2006 | | |
|
|
|
Received 4 copys of sheet LA2.1 put with plans
|
Routing - FIRE | 10/6/2006 | | 10/10/2006 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLAN CHECK | 10/10/2006 | | 10/10/2006 | | |
|
|
|
in hold box waiting for resubmittals
|
Routing - PUBLIC WORKS | 10/5/2006 | | 10/6/2006 | | PASS |
|
|
|
|
Routing - PLANNING | 10/6/2006 | | 10/6/2006 | | FAIL |
|
|
|
Sara S. Plans are appropriate for the additional units, however a design review modification will have to be filed for review of the access roads. Applicant was contacted by Cody Riddle with this information.
|
1st review completed | | | 9/19/2006 | | FAIL |
|
|
|
Failed Fire.
|
Routing - PLAN CHECK | 9/19/2006 | | 9/19/2006 | | HOLD |
|
|
|
On hold waiting for resubmittal information
Note this tag put on parcel: BLD06-02454 Drainage & Grading Permit for Candlewood Suites. The drainage and grading permit cannot be issued until Dave Abo has approved the vacation of an existing easement on this property.
|
Routing - FIRE | 9/6/2006 | | 9/19/2006 | | FAIL |
|
|
|
Faxed resubmittal requirements to arhitect. Attached review comments to plans.
|
Routing - PLANNING | 9/5/2006 | | 9/6/2006 | | PASS |
|
|
|
Approved per DRH06-00082 and CU.
|
Routing - PUBLIC WORKS | 8/31/2006 | | 9/5/2006 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/30/2006 | | |
|
|
|
|
Routing - PLUMBING | 8/30/2006 | | 8/30/2006 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/30/2006 | | 8/30/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/30/2006 | | |
|
|
|
|
Application received | | | 8/23/2006 | | |
|
|
|
|
CHANGE STATUS TO (PND) | | | 8/23/2006 | | |
|
|
|
Waiting for initial fee to be paid ///DLD
|
Plan assigned to (DLD) Darla | 8/30/2006 | 8/30/2006 | | | |
|
|
|
|
Routing - PUBLIC WORKS | | | | | |
|
|
|
Need to re-review landscaping, because of new access road behind the buildings for fire department access.
|
Routing - PLAN CHECK | 10/13/2006 | | | | |
|
|
|
Plans back in hold box waiting for resubmittals for planning ///dld
|