VOIDED CHANGE STATUS | | | 3/31/2009 | | DONE |
Tisha Gallop
|
|
|
Ok per Carl Westfall and owner Ron Sargent to void this permit and refer to Bld08-00764
|
Plan Reviewer's activity | | | 3/30/2009 | | DONE |
|
|
|
Since this project was voided, the drawings were discarded.
|
BLD - Request for Extension | 8/16/2007 | 8/17/2007 | 8/17/2007 | | DONE |
Jim Sly
|
|
|
Ron Sargent ###-#### OK for Ext.
|
BLD-Conference | 4/27/2007 | 4/30/2007 | 4/30/2007 | A | DONE |
Jim Sly
|
|
|
allan; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Aging Inspection | 3/1/2007 | 3/1/2007 | 3/5/2007 | | DONE |
Jim Sly
|
|
|
WIP
|
Telephone call | | | 11/21/2006 | | DONE |
|
|
|
lft vm with ronsargent that permit and fees are ready to be picked up but needs GC/RCE
|
Permit Ready to Issue | | | 11/21/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/21/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/20/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/8/2006 | | 11/17/2006 | | PASS |
|
|
|
11/17/2006 16:18:39 CJW - activity updated through activity BLDA022 from case BLD06-02458.
|
Routing - PLUMBING | 11/15/2006 | | 11/17/2006 | | PASS |
|
|
|
S-1 changed to service sink per carl westfall. 7.07sq. in. of venting must communicate with building drain. an approved relief valve or expantion tank, ect. required.
|
Routing - PUBLIC WORKS | 11/14/2006 | | 11/15/2006 | | PASS |
|
|
|
Additional fixture
|
Routing - PLAN CHECK | 10/30/2006 | | 11/14/2006 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 11/14/2006 | | |
|
|
|
Received 2 copies of sheets P2.1 and taken to Carl Westfall
|
Plan resubmittals received | | | 11/6/2006 | | |
|
|
|
Received 1 cover letter from TRW Architects, 2 copies of P2.1 and taken to Carl Westfall
|
1st review completed | | | 10/30/2006 | | FAIL |
|
|
|
Failed plumbing and plan check.
|
Routing - FIRE | 10/26/2006 | | 10/30/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 10/6/2006 | | 10/26/2006 | | FAIL |
|
|
|
The IBC plan review was started on October 26, 2006 and was finished the same day. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 10/23/2006 | | |
|
|
|
Received 1pg. letter of response, 2 copies of the following pages: P1.1, P2.1, A2.1, A6.1; taken to Carl Westfall
|
Routing - PLANNING | 10/4/2006 | | 10/6/2006 | | PASS |
|
|
|
Approved per CVA04-00034.
|
Routing - PLUMBING | 10/4/2006 | | 10/4/2006 | | FAIL |
|
|
|
venting cross sectional area is undersized. drinking fountain and service sink are required. provide thermol expantion protection.
|
Routing - PUBLIC WORKS | 9/27/2006 | | 9/28/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 9/8/2006 | | 9/27/2006 | | PASS |
|
|
|
|
Application received | | | 8/23/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/23/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/23/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 11/17/2006 | | | | |
|
|
|
|