BLD-Final | 4/30/2010 | 4/30/2010 | 4/30/2010 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 4/30/2010 | 4/30/2010 | 4/30/2010 | | PASS |
Dave Hannah
|
|
|
|
Permanent Occupancy | | | 4/30/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 3/1/2007 | 3/2/2007 | 3/2/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/1/2007 at 1:15:17 PM. Contact: ###-####. OK for Perm Occ.
|
FIRE-Final Inspection | 2/28/2007 | 3/1/2007 | 3/1/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, one missing additional PFE provided for the second level while on site.
|
BLD-Final | 2/27/2007 | 2/28/2007 | 2/28/2007 | P | FAIL |
Dave Hannah
|
|
|
jeff ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs fire sign offs hand rail on stairs ada rest
|
BLD-Framing/Rough-in | 11/16/2006 | 11/16/2006 | 11/17/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/16/2006 at 11:23:50 AM. Contact: ###-####. framing for pan deck ok asper plans but plans are vage
|
BLD-Other | 11/17/2006 | 11/17/2006 | 11/17/2006 | P | PART |
Dave Hannah
|
|
|
Approved front retail area for temp.occ..CN issued
|
Print Occupancy Form | | | 11/13/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/13/2006 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/13/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/2/2006 | | 11/9/2006 | | PASS |
|
|
|
Drawings approved after 3rd resubmittal review and after direct contact with the Structural Engineer.
|
Plan assigned to (CJW) | 9/22/2006 | | 11/9/2006 | | PASS |
|
|
|
11/9/2006 16:31:28 CJW - activity updated through activity BLDA022 from case BLD06-02472.
|
Plan resubmittals received | | | 11/7/2006 | | |
|
|
|
Received 1 copy of plan review response letter from Sundell Architects, 2 pages of structural calcs, 2 copies of sheets Two & Three and taken to Carl Westfall
|
Routing - PLAN CHECK | 10/19/2006 | | 11/2/2006 | | FAIL |
|
|
|
Reviewed the resubmitted drawings. Issues remain unresolved. Sent revised report to the Architect.
|
Routing - FIRE | 11/2/2006 | | 11/2/2006 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Plan resubmittals received | | | 10/27/2006 | | |
|
|
|
Received 2pg. response letter 1 copy of 10 pg. structural calculations and 3 copies of pages Two & Three. Taken to Carl Westfall
|
Routing - FIRE | 10/17/2006 | | 10/19/2006 | | FAIL |
|
|
|
Faxed resubmittal items to architect. Attached review comments to plans.
|
1st review completed | | | 10/19/2006 | | FAIL |
|
|
|
Failed plan check and fire.
|
Routing - PLAN CHECK | 9/25/2006 | | 10/17/2006 | | FAIL |
|
|
|
(10-10-06) The IBC plan review was started and suspended. Revised drawings will be submitted showing how the space will actually be configured. (10-17-06) Reviewed drawings that were submitted on October 12. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 10/13/2006 | | |
|
|
|
Received 2 copies of sheets one & two from Sundell architecture and taken to Carl Westfall
|
Telephone call | | | 10/10/2006 | | DONE |
|
|
|
Called the Architect, Larry Sundell, and told him that the steep ships ladder that he had designed cannot be approved. He intendes to submitted drawings showing a compliant stairway.
|
Routing - PUBLIC WORKS | 9/22/2006 | | 9/25/2006 | | PASS |
|
|
|
|
Application received | | | 8/25/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/2006 | | |
|
|
|
|