BLD-Energy code compliance | 9/19/2007 | 9/20/2007 | 9/20/2007 | P | PASS |
Tony Young
|
|
|
graham - insulation Phone #: ###-####
|
BLD-Framing/Rough-in | 9/14/2007 | 9/17/2007 | 9/17/2007 | P | PART |
Jim Storey
|
|
|
graham Phone #: ###-#### in fill truss 2x at bearing at 45 per plan ok to insulate
|
BLD-Other | 8/13/2007 | 8/14/2007 | 8/14/2007 | P | PASS |
Tony Young
|
|
|
graham - shear nail - please call 1/2 hr prior to inspection Phone #: ###-#### exterior shear ok
|
BLD-Foundation | 6/25/2007 | 6/26/2007 | 6/26/2007 | P | PASS |
Tom Arcoraci
|
|
|
matt Phone #: ###-####
|
BLD-Footing | 6/22/2007 | 6/25/2007 | 6/25/2007 | A | PASS |
Tony Young
|
|
|
matt Phone #: ###-####
|
PubWorks Subgrade Approval | 6/25/2007 | 6/25/2007 | 6/25/2007 | | DONE |
|
|
|
FOOTING SUBGRADE APPROVED BY THE GEOTECHNICAL ENGINEER
|
BLD-Footing | 6/22/2007 | 6/22/2007 | 6/22/2007 | P | FAIL |
Mike Jordan
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt. Has not been approved by public works. Concrete contractor was contacted and instructed to not place any concrete.
|
Issue PAID IN FULL permit | | | 3/15/2007 | | DONE |
|
|
|
|
Telephone call | | | 9/15/2006 | | DONE |
|
|
|
spoke to teresa@###-####/told permit was ready and fees
|
Permit Ready to Issue | | | 9/11/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/11/2006 | | DONE |
|
|
|
left vm @###-#### to call me concerning permit
|
Plan assigned to (PEP) | 8/28/2006 | 8/28/2006 | 9/8/2006 | | PASS |
|
|
|
9/8/2006 09:36:46 PEP - activity updated through activity BLDA022 from case BLD06-02511.
|
Routing - PLAN CHECK | 8/29/2006 | | 9/8/2006 | | PASS |
|
|
|
Perry P.
|
Case Summary (BLD) | | | 9/8/2006 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/8/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2006 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 8/28/2006 | | 8/29/2006 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Application received | | | 8/28/2006 | | |
|
|
|
|