Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-02528
StatusFinaled
Name THOMPSON CHARLES C
Site Address 2580 W WILLIAMSPORT LN
Project NameVISTA FOURPLEX
Customer Number 
ePlanReviewNo
Description
(NO CONTRACTOR REGISTRATION PROVIDED. APPLICANT CERTIFIES EXEMPTION PER IDAHO STATUTE 54-5205) Vista Fourplex - (modified to current description 5/30/07) To construct a new, 5,566 square feet, two story with a basement, four unit apartment building, with attached garages. The basement floor area is 2,374 square feet with 1,144 square feet of this area for the garages, the first floor area is 2,170 square feet and the second floor area is square feet. Each unit is over 800 square feet, is two stories in height, and is two bedroom and one and one/half bath. NOTE: This building is fire sprinklered per NFPA 13-R. All construction shall be per the approved plans and attached comment list. MJP DRH 06-00419 CUP 06-00075
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD8/11/20088/11/20088/12/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 6/4/20088/11/2008 DONE
Plan Reviewer's activity  6/4/2008 DONE
DetailsSam Zahorka
See documents (Adjacent Lot 2 cannot be built on per agreement recorded on 3/26/08)
Permanent Occupancy  6/4/2008 DONE
DetailsCathy Weisshaupt
Code Occupancy Approval Temp  3/31/2008 DONE
Cathy received the bond today from Heathstone; it does cover the costs for the remaining landscaping which needs to be done.
Temporary Occupancy3/28/20086/26/20083/28/2008 DONE
DetailsCathy Weisshaupt
BLD-Final3/20/20083/20/20083/20/2008PPART
DetailsJim Storey
craig Phone #: ###-#### final ok pending p&z bond and plan review letter for unbuildabe lot to be on file.
FIRE-Final Inspection3/19/20083/20/20083/20/2008PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection3/18/20083/19/20083/19/2008PFAIL
DetailsTroy Cobbley
Life safety completed except for missing knox box's. Will call in permit for final when knox box is installed.KR
FIRE-Final Inspection3/17/20083/18/20083/18/2008PFAIL
DetailsForrest France
Provide knox box, need to final fire sprinkler and alarm permits, need closures at doors, not all items reviewed at this time.
BLD-Final3/14/20083/17/20083/18/2008ANR
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/14/2008 at 2:32:42 PM. Contact: ###-####.
Code Occupancy Approval Temp  3/18/2008 DONE
Contractor has submitted a bid for the remaining bark work. Temp granted as all other conditions have been met. He anticipates work to be done within the next two weeks, so the bond can be released.
BLD-Aging Inspection2/18/20082/18/20082/20/2008 PASS
DetailsJim Storey
wip
BLD-Energy code compliance12/18/200712/19/200712/20/2007PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/18/2007 at 10:10:53 AM. Contact: ###-####.
BLD-Framing/Rough-in12/12/200712/14/200712/14/2007APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/12/2007 at 3:38:08 PM. Contact: ###-####.
BLD-Conference10/19/200710/22/200710/22/2007APASS
DetailsJim Storey
vern
BLD-Conference10/19/200710/19/200710/19/2007PCANC
DetailsJim Storey
vern Phone #: ###-#### rolled am mon
BLD-Framing/Rough-in10/11/200710/12/200710/12/2007APASS
DetailsJim Storey
late am if possible please--fern Phone #: ###-#### 2nd floor wall gyp ok
BLD-Framing/Rough-in10/3/200710/4/200710/4/2007APASS
DetailsJim Storey
vern - around 11:00 if possible Phone #: ###-####gyp nailling ok
BLD-Framing/Rough-in10/3/200710/3/200710/3/2007PPASS
DetailsJim Storey
vern - around 3:00 if possible Phone #: ###-#### gyp nailling ok
BLD-Conference10/2/200710/2/200710/2/2007PPASS
DetailsJim Storey
vern Phone #: ###-####
BLD-Foundation9/11/20079/11/20079/11/2007PPASS
DetailsTom Arcoraci
ben; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
BLD-Footing9/5/20079/6/20079/6/2007AFAIL
DetailsMike Jordan
Ben; Phone #: ###-#### Internet Inspection Request from: Hattie James. See detail 10 on sheet S2.02, verts need to be @ 10" oc. Needs to double check spacing on verts, many areas at front is 22"oc, needs toi be 18"oc. Check special insp. start up sheet, is required. c/n posted. Also left meesage with Ben.
Telephone call  8/31/2007  
per dave abo ok to take parcel hold off regarding sub being recorded
Issue PAID IN FULL permit  8/31/2007  
Ready Permit EXTENDED  8/9/2007 DONE
Telephone call  8/7/2007 DONE
talked to bruce poe (the arch)at ###-#### said this has been an on going process with multiple modifications-- will write rita d. an extension letter
Telephone call  7/20/2007 DONE
talked to stan cole at ###-#### that permit is ready & needs gc & rce #, achd approval & responsible person--
Print Occupancy Form  7/16/2007 DONE
Print Occupancy Form  7/16/2007 DONE
Telephone call  7/16/2007 DONE
left vm for stan cole at ###-#### - permit ready and fees given - also need gc name, rce#, rp name, and ACHD receipt
Override - Parcel Holds  7/16/2007  
Permit Ready to Issue  7/16/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/13/2007 DONE
Override - Parcel Holds  7/13/2007  
Print Pending Permit.LaserJet4  7/13/2007 DONE
Case Summary (BLD)  7/13/2007 DONE
Plan assigned to (M_P)8/30/2006 7/13/2007 PASS
7/13/2007 14:32:22 M_P - activity updated through activity BLDA022 from case BLD06-02528.
Routing - PLAN CHECK5/30/2007 7/13/2007 PASS
Plan resubmittals received  7/11/2007  
Received transmittal, 2 page response letter and three copies of pages A0.1, A1.0, A2.0, A3.0, A3.1, A4.0, A7.0, S0.1, S1.01, S1.02, S1.03, S1.04, S3.04, M0.0, M1.0, M2.0, M3.0, M4.0, P1.0, P2.0, P3.0, P4.0; taken to Mike Phillips
Routing - PLAN CHECK3/13/2007 5/30/2007 FAIL
Third review completed, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
Case Summary (BLD)  5/30/2007  
Plan resubmittals received  5/25/2007  
received letter of transmittal from modus arch & "2" pages of comments. also "3" sets of plans with each sheet of AO.1, A2.O, A3.O, A3.1, A4.O, A6.O, A7.O, SO.1, S1.O1, S1.O2, S1.O3, S3.O3, S3.O4, M1.O, P1.O, & P3.O--plans taken to Mike Phillips
Routing - PLAN CHECK12/4/2006 3/13/2007 FAIL
Third review failed, had meeting with the architect to request additional informaiton to be submitted for further review prior to issuing permit.
Office Staff conference/action  3/8/2007 DONE
Agreed to release permit without non-build agreement for lot, with agreement by Chuck Thompson that the appropriate legal document creating a non-build situation on lot #2 would be submitted prior to the granting of a certificate of occupancy. No Occupancy will be granted without submission, approval and recordation of the document. jlg.
Plan resubmittals received  12/12/2006  
received lochsa engineering of idaho transmittal & "2" sets of plans & one sheet each of SO.1, S1.O1, S1.O2, S3.O2, S3.O4 -plans taken to mike phillips
Routing - PLAN CHECK11/29/2006 12/4/2006 FAIL
Second review failed, called architects office. They do not know if Poe architect will be working on this project and I can not get ahold of Stan at the number he has left me.
Routing - FRONT DESK11/28/2006 11/29/2006 PASS
Barbara
Routing - PLANNING11/27/2006 11/28/2006 PASS
DRH06-00419
Routing - PLAN CHECK10/19/2006 11/27/2006  
Routing to P{lanning.
Plan resubmittals received  11/20/2006  
received leeter of transmittal, letter to mike phillips (3) pages per your plan comments dated october 17th, lochsa engineering of idaho building department comments (3 pages) 1 page from cole & poe for listed items, project start up for specail inspect(5 pages)
also received "2" sets of plans consisting of A1.O, A2.O, A3.O, A3.1, A4.O, SO.1, S1.O1, S1.O2, S3.O2, S3.O4, EN1.O, MO.O, M1.O, M2.O, M3.O, M4.O, P1.O, P2.O, P3.O, P4.O, -plans taken to mike phillips
1st review completed  10/19/2006 FAIL
Failed planning & plan check.
Routing - FIRE10/17/2006 10/19/2006 PASS
Attached review comments to plans.
Routing - PLAN CHECK9/13/2006 10/17/2006 FAIL
Plan review completed, sent correction report to the architect requesting additional informaiton to be submitted for further review prior to issuing permit.
Case Summary (BLD)  10/17/2006  
Routing - PLANNING9/8/2006 9/13/2006 FAIL
Carl Miller CUP06-00075. Needs DR approval.
Routing - PLUMBING9/8/2006 9/8/2006 PASS
st-5 seems too small for system, verify sizing. per plans and 2003 upc.
Routing - Erosion and Sediment9/7/2006 9/8/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS9/5/2006 9/7/2006 PASS
Routing - PLANNING Land Div8/31/2006 9/5/2006 PASS
Plans ACCEPTED BY PLAN TECH  8/31/2006  
Plan routing begun/NEW & ADDTN  8/31/2006  
Application received  8/30/2006  
Recd Pcfee & Taken To Pln CK  8/30/2006