Third Notice BLD | 5/25/2007 | 5/25/2007 | 7/10/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/9/2007 | 5/9/2007 | 5/25/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/18/2007 | 5/9/2007 | | DONE |
|
|
|
|
BLD-Other | 4/16/2007 | 4/18/2007 | 4/18/2007 | P | PASS |
Dave Hannah
|
|
|
Dustin Permit occupancy; Phone #: ###-#### Internet Inspection Request from: Stacie Backus ok for perm occ
|
Permanent Occupancy | | 4/18/2007 | 4/18/2007 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 4/18/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11531 issued 4-18-07 to Ada County for courtroom on the 4th floor.
|
BLD-Final | 3/27/2007 | 3/28/2007 | 3/28/2007 | A | PART |
Dave Hannah
|
|
|
dustin; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok for tyemp occ needs to finish locks
|
FIRE-Final Inspection | 3/27/2007 | 3/27/2007 | 3/28/2007 | P | PASS |
Forrest France
|
|
|
c/n items verified for completion, fire life safety finaled.
|
Temporary occupancy | | | 3/28/2007 | | DONE |
|
|
|
Temp. Occ. Cert. # 5561 issued 3-28-07 to the Ada County Courthouse 4th floor.
|
BLD-Final | 3/21/2007 | 3/22/2007 | 3/22/2007 | P | CANC |
Dave Hannah
|
|
|
Dustin; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
FIRE-Final Inspection | 3/21/2007 | 3/22/2007 | 3/22/2007 | P | FAIL |
Forrest France
|
|
|
Door hardware at one conference room is installed backward, missing max occupant load sign in the courtroom, exit signs and door hardware at the north courtroom exits do not correlate properly, panic hardware is not yet installed at the two south courtroom exit doors.
|
BLD-Final | 2/28/2007 | 2/28/2007 | 2/28/2007 | P | FAIL |
Dave Hannah
|
|
|
dustin ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs fire life saftey ect finals first
|
BLD-Final | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | CANC |
Dave Hannah
|
|
|
dustin ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Wall cover | 12/12/2006 | 12/13/2006 | 12/13/2006 | P | PASS |
Dave Hannah
|
|
|
dustin ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith beam fire proofing patched ok to cover entry
|
BLD-Framing/Rough-in | 12/7/2006 | 12/7/2006 | 12/7/2006 | P | PART |
Dave Hannah
|
|
|
dustin ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs to fix fire proofing on beam
|
BLD-Framing/Rough-in | 12/4/2006 | 12/5/2006 | 12/6/2006 | P | PASS |
Dave Hannah
|
|
|
JUSTIN - 4TH FLOOR; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Issue PAID IN FULL permit | | | 11/7/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 11/1/2006 | | |
|
|
|
|
Telephone call | | | 11/1/2006 | | DONE |
|
|
|
talked to greg allen at ###-#### that permit is ready & need rce # for gc
|
Print Occupancy Form | | | 10/31/2006 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/14/2006 | | 10/28/2006 | | PASS |
|
|
|
10/28/2006 08:42:41 CJW - activity updated through activity BLDA022 from case BLD06-02535.
|
Routing - PLAN CHECK | 10/12/2006 | | 10/28/2006 | | PASS |
|
|
|
The drawings were approved after the resubmittal review.
|
Plan resubmittals received | | | 10/26/2006 | | |
|
|
|
received letter (2) pages of transmittal from hummel arch, "2" copies of letter from engineering incor (2) pages each, "2" copies from rick stanley (11) pages each & "2" sets of a project manual. also AV.OO, A2.OO, A2.O1, A8.OO, A8.01, A8.02, A8.03, A8.04, MO.O, M1.O, M2.O, E2.OD, E2.OFL, E2.OPS, E3.O, AV.O1, AV.O2, AV.O3, AV.O4, AV.O5-plans taken to carl westfall
|
Routing - FIRE | 10/9/2006 | | 10/12/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 10/12/2006 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PLAN CHECK | 9/15/2006 | | 10/9/2006 | | FAIL |
|
|
|
The IBC plan review was started on October 5, 2006 and was finished on October 9. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 9/14/2006 | | 9/15/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/31/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/31/2006 | | |
|
|
|
|
Application received | | | 8/30/2006 | | |
|
|
|
|