Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/26/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/22/2006 | 12/27/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/21/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/20/2006 | | DONE |
|
|
|
|
BLD-Final | 11/20/2006 | 11/21/2006 | 11/21/2006 | P | PASS |
Mike Jordan
|
|
|
shad ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. ok for perm occ.
|
FIRE-Final Inspection | 11/20/2006 | 11/21/2006 | 11/21/2006 | A | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
Permanent Occupancy | | 11/21/2006 | 11/21/2006 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 11/21/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11310 issued 11-21-05 to Zumiez at Boise Towne Square.
|
FIRE-Final Inspection | 11/17/2006 | 11/20/2006 | 11/20/2006 | A | FAIL |
Troy Cobbley
|
|
|
The smoke evac systems need tested and the new duct smoke detectors are not programed in yet and therefore could not be tested.
|
Print Occupancy Form | | | 11/9/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 11/8/2006 | 11/8/2006 | 11/8/2006 | P | PASS |
Mike Jordan
|
|
|
shae; Phone #: ###-#### Internet Inspection Request from: Patricia Smith.. tenant demissing walls.
|
BLD-Conference | 11/8/2006 | 11/8/2006 | 11/8/2006 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Wall cover | 11/7/2006 | 11/8/2006 | 11/8/2006 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/7/2006 at 3:21:13 PM.
|
BLD-Other | 11/6/2006 | 11/7/2006 | 11/7/2006 | P | PART |
Mike Jordan
|
|
|
shad - sheet rock ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Tenant seperation walls. wip.
|
BLD-Framing/Rough-in | 11/1/2006 | 11/3/2006 | 11/3/2006 | A | PART |
Mike Jordan
|
|
|
shad; Phone #: ###-#### Internet Inspection Request from: Letitia Gallop ///Per Shad resceduled inspection from 11/2 am to 11/3 am. Tenant seperation walls and framinf for new dressing rooms. Contractor to remove existing furouts to complete seperation wall. All patches at seperation wall must connect back to framing member.
|
Routing - PLAN CHECK | 10/30/2006 | | 10/31/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/31/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2006 | | DONE |
|
|
|
|
Telephone call | | | 10/31/2006 | | DONE |
|
|
|
talked to chad loveland at ###-#### that permit is ready
|
Issue PAID IN FULL permit | | | 10/31/2006 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 9/22/2006 | | 10/31/2006 | | PASS |
|
|
|
10/31/2006 07:09:36 RMH - activity updated through activity BLDA022 from case BLD06-02572.
|
Routing - FIRE | 10/26/2006 | | 10/30/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 10/30/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 10/26/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/25/2006 | | 10/26/2006 | | PEND |
|
|
|
No corrections required by the building plan review, routed plans to fire for review on 10/26/06
|
Routing - PUBLIC WORKS | 9/22/2006 | | 9/25/2006 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/18/2006 | | DONE |
|
|
|
Received 1 transmittal,1 letter, & 4 copys of sheets A2.01,A7.01,M1,E1,E2,EN-1 taken to Carl W.
|
Application received | | | 9/5/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/5/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/5/2006 | | |
|
|
|
|