Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-02598
StatusFinaled
Name CM COMPANY
Site Address 2501 N BOGUS BASIN RD
Project NameHEALTHWISE
Customer Number 
ePlanReviewNo
Description
HEALTHWISE - To construct a 7,196 two story Type VB fully fire sprinklered office addition to the north side of the existing one story office building. Other work includes all demolition, site improvements paving and landscaping per approved plans and attachments, DRH06-00251. Area of new addition first floor 3,602 second floor 3,594. Fire sprinklers used for area increase. mlo (6/1/07: Plan modification submitted to add sound room & adjacent office on 1st floor and final modular furniture layout. mys)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/11/200712/11/20071/30/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD11/19/200711/19/200712/11/2007 DONE
First Notice has not been responded to.
First Notice 11/5/200711/19/2007 DONE
PubWorks Occupancy Approval11/5/200711/5/200711/5/2007 DONE
Signed off permit per Brian Murphy 11/05/07.
Permanent Occupancy UNPAID FEE  11/5/2007 DONE
BLD-Final11/2/200711/2/200711/2/2007PPASS
DetailsTony Young
ross Phone #: ###-####
ok for perm occ. pending others
BLD-Final11/1/200711/2/200711/2/2007ANR
DetailsTony Young
ross Phone #: ###-####
BLD-Final10/30/200710/31/200710/31/2007PPART
DetailsTony Young
ross Phone #: ###-#### Note: if possible 3:00 or later
temp ok,, need elec final on built ins
FIRE-Final Inspection10/29/200710/29/200710/29/2007PPASS
DetailsForrest France
C/N is complete, fire life safety inspection passed.
Code Occupancy Approval10/26/200710/26/200710/26/2007PPASS
DetailsMichael Garner
SITE INSPECTION COMPLETE - PARKING LOT AND LANDSCAPING COMPLETED ACCORDING TO APPROVED PLANS/PERMITS - PASS
BLD-Conference10/26/200710/26/200710/26/2007PPART
DetailsTony Young
ross Phone #: ###-####
extensive conf on final
FIRE-Final Inspection10/24/200710/25/200710/25/2007PFAIL
DetailsForrest France
Provide building address numbers, remove the manual thumbturn at the door from the SW office, provide signage at the door the to fire riser room.
Plan resubmittals received  10/2/2007  
Received letter from Erstad Arch. addressed to Tony Young and staircase details; put in Tony's box
BLD-Conference10/1/200710/1/200710/1/2007PPART
DetailsTony Young
erstad - conference set up at 2:00 Phone #: ###-####
conf on stairs,, they will send in paper to me for research etc.
BLD-Framing/Rough-in9/14/20079/14/20079/14/2007PPART
DetailsTony Young
ROSS
ceiling grids ok pending trades
BLD-Framing/Rough-in9/13/20079/14/20079/14/2007ACANC
DetailsTony Young
ross Note: above the ceiling grid Phone #: ###-####
BLD-Framing/Rough-in8/30/20078/30/20078/30/2007PPART
DetailsTony Young
Ross; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
beam RFI ok,, verified welding S. I. report,, need trades before ceiling tile drop in
(F) Reprint permit  6/29/2007 DONE
CHANGE STATUS TO (ISS)  6/29/2007 DONE
picked up and paid for plan mod
Routing - PLAN CHECK6/21/2007 6/21/2007 PASS
PLAN MODIFICATION (Marlene). No additional or new plan review comments. Revised permit wording.
Routing - FIRE6/19/2007 6/21/2007 PASS
PLAN MODIFICATION
PLANS/APPL TAKEN TO FRONT DESK  6/21/2007 DONE
PLAN MODIFICATION
Print Occupancy Form  6/21/2007 DONE
Telephone call  6/21/2007 DONE
t/c w cheryl pearse at ###-#### - permit ready and fees given
Permit Ready to Issue  6/21/2007  
Plan assigned to (MYS)6/4/2007 6/21/2007 PASS
6/21/2007 12:17:24 MYS - activity updated through activity BLDA022 from case BLD06-02598.
BLD-Framing/Rough-in6/15/20076/15/20076/15/2007PPASS
DetailsTony Young
Ross, ###-####
Override - Parcel Holds  6/15/2007  
Override - Parcel Holds  6/15/2007  
BLD-Framing/Rough-in6/11/20076/11/20076/11/2007PPART
DetailsTony Young
ross - ###-####
ok to one side int walls,, need elec. r/in 1st
Override - Parcel Holds  6/11/2007  
Override - Parcel Holds  6/4/2007  
BLD-Framing/Rough-in5/31/20076/1/20076/1/2007PPART
DetailsTony Young
ross; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
remainder of exterior ok to cover
Plan Modification Accepted  6/1/2007 DONE
PLAN MODIFICATION accepted for Bld06-02598 to add sound room and adjacent office on first floor and final modular furniture layout. Submitted on pages a0.01, a2.11, a6.11, f2.11, f2.12, m1.10, m1.11, m3.12, m4.11, e2.11, e2.12, e2.21; taken to Marlene Southard
BLD-Framing/Rough-in5/15/20075/16/20075/16/2007APART
DetailsDave Hannah
Ross; Phone #: ###-#### Internet Inspection Request from: Victoria Beall second floor east wall ok to cover ext need ok on weld tabs also ext sheeting and sheer on north wall ok
BLD-Framing/Rough-in5/4/20075/7/20075/7/2007APART
DetailsTony Young
ross Note: no wall from evelator pit to east; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
north and east exterior walls ok to cover
BLD-Framing/Rough-in5/1/20075/1/20075/1/2007PPART
DetailsTony Young
Ross; Phone #: ###-####
pan deck ok pending special inspection and engineer approval
BLD-Framing/Rough-in4/30/20075/1/20075/1/2007ACANC
DetailsTony Young
ross; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD-Framing/Rough-in4/3/20074/4/20074/4/2007APART
DetailsTony Young
ross; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
new int. walls in existing building ok pending trades
BLD-Footing2/13/20072/14/20072/14/2007APART
DetailsTony Young
ross; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
pending S. I.report,, interior north/south ftg,, north /west exterior ftg,, w i p
BLD-Footing2/5/20072/6/20072/6/2007APART
DetailsJim Sly
ROSS; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
Wall at gridline B and E .....N. wall and elevator pit footing OK pending special insp, tests, and approvals (MTI)
BLD-Footing1/26/20071/26/20071/26/2007PPART
DetailsJim Sly
ross; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
Called Eng......Bryce Stapley.......Design 2500 PSI Footings OK at gridline E A & B.......and N. (wall) footing OK Note: Need sub grade approval for elevator pit area
Override - Parcel Holds  1/16/2007  
Telephone call  1/11/2007 DONE
tlk to secretary for andy erstad ###-#### that the mod plan is ready to be picked up and the fee
Override - Parcel Holds  1/11/2007  
Permit Ready to Issue  1/11/2007 DONE
Plan assigned to (MLO)1/5/20071/5/20071/10/2007 PASS
1/10/2007 14:08:03 MLO - activity updated through activity BLDA022 from case BLD06-02598.
PLANS/APPL TAKEN TO FRONT DESK  1/10/2007 DONE
modification approved
Print Occupancy Form  1/10/2007 DONE
Routing - PLAN CHECK1/6/2007 1/9/2007 PASS
Routing - PLANNING1/9/2007 1/9/2007 PASS
Plan Modification Accepted  1/4/2007  
Accepted plan modification on Bld06-02598 to add (4) offices on the second floor and add (2) offices and (3) skylights on the first floor. Plans submitted on pages a0.01, a2.11, a2.12, a2.31, a2.32, a2.41, a2.43, a4.11, a6.11, s2.3, s7.4, m1.10, m1.11, m4.11, p1.11, p1.12, e0.0, e2.11, e2.12, e2.21, e2.22, e4.1. Routed to Mike Otto
CHANGE ISSUED DATE  12/27/2006 DONE
Issue PAID IN FULL permit  12/27/2006  
Telephone call  12/21/2006 DONE
tlk to secretary ###-#### for andy e that permit and fees are ready to be picked up but needs RP and ACHD
Permit Ready to Issue  12/21/2006 DONE
Print Occupancy Form  12/20/2006 DONE
Routing - Erosion and Sediment12/18/2006 12/19/2006 PASS
ESC plan approved with attached conditions.
Routing - PLANNING Land Div12/19/2006 12/19/2006 PASS
Approved.
PLANS/APPL TAKEN TO FRONT DESK  12/19/2006 DONE
Plan assigned to (MLO)9/11/2006 12/19/2006 PASS
12/19/2006 14:41:04 MLO - activity updated through activity BLDA022 from case BLD06-02598.
Plan resubmittals received  12/18/2006  
Recieved 1 cover transmittal, 2 copies of ESC waiver letter from Andrew Erstad (2 pgs) and taken to Mike Otto
Routing - PUBLIC WORKS12/18/2006 12/18/2006 PASS
Plan resubmittals received  12/15/2006  
received tealeys land surveying transmittal to mike otto & letter to brain murphy from tealey's land surveying including (4) pages. also received "5" sets of plans 1 sheet each of c1.O, c2.O1, & c2.O2--plans taken to mike otto
Routing - PLAN CHECK12/13/2006 12/13/2006  
Routing - Erosion and Sediment12/11/2006 12/12/2006 FAIL
ESC plan failed, does not meet BCC 8-17 requirements. Faxed checklist to PD, copy of checklist is in ESC binder
Routing - PLANNING Land Div12/6/2006 12/7/2006 FAIL
A Record of Survey is still in process. Do not issue building permit until it has received approval and all documents have been recorded.
Plan resubmittals received  12/6/2006  
Recieved 2 copies of sheets C1.0, C2.01, C2.02 and given to Mike Otto
Routing - PUBLIC WORKS12/6/2006 12/6/2006 FAIL
Requires drainage plan revisions. Contact Brian Murphy at ###-#### or Jim Wylie at ###-####.
Plan resubmittals received  12/6/2006  
Received transmittal letter and 3 copies of 1pg.(double sided) erosion and sediment control narrative; taken to Mike Otto
Routing - PLAN CHECK10/20/2006 10/26/2006 PASS
Routing Off Site - STRUCTURAL10/20/2006 10/26/2006 PASS
Called Action Couriers for pick up
1st review completed  10/20/2006 FAIL
Routing - FIRE10/17/2006 10/20/2006 PASS
Attached review comments to plans.
Plan resubmittals received  10/19/2006  
received transmittal letter from erstad architects, a (2) page) letter from stapley eng, and "3" sheets of s2.2-plans taken to mike otto
Routing - PLAN CHECK10/6/2006 10/17/2006 PEND
pending structural approval
Routing Off Site - STRUCTURAL9/11/2006 10/17/2006 FAIL
corrections sent to architect
Plan resubmittals requested  10/17/2006 DONE
structural corrections
Routing - PLANNING10/4/2006 10/6/2006 PASS
PASS per DRH06-00251 Josh W.
Routing - PLUMBING9/29/2006 10/4/2006 PASS
ceiling space is a return air plenum, no plastic piping. per plans and 2003 upc.
Routing - Erosion and Sediment9/29/2006 9/29/2006 FAIL
ESC plan failed, no narrative included with submittal, notified applicant (Andrew Erstad ###-####).
Routing - PUBLIC WORKS9/26/2006 9/29/2006 FAIL
Revisions required. Contact Brian Murphy ###-####
Routing - PLANNING Land Div9/11/2006 9/26/2006 FAIL
A Record of Survey has been submitted for this property. However, that Record of Survey has not been approved or recorded yet. As such, do not issued a Building Permit until the ROS has been finalized.
Telephone call  9/11/2006 DONE
called Action Couriers for pick up and deliver to outside engineer
Plans ACCEPTED BY PLAN TECH  9/11/2006  
Plan routing begun/NEW & ADDTN  9/11/2006  
Application received  9/8/2006