Permit Information
Permit NumberBLD06-02615
StatusFinaled
Name CONGER-SAUCERMAN
Site Address 9288 W EMERALD ST
Project NameGE HARRIS LLC
Customer Number 
ePlanReviewNo
Description
CONGER/SAUCERMAN RCE # 2946 (T-MOBILE COMMUNICATIONS) This building is fire sprinklered for area increase. To construct a 9,307 square foot telephone exchange tenant space within an existing 20,634 square foot building. Work is to include 1-hr fire barrier walls around a battery room control area, interior nonbearing walls, interior doors, 2 new exterior doors, a single user shower room accessible to the disabled, suspended ceilings, and interior finishes. In addition, two existing restrooms will be upgraded to be accessible to the disabled. A 2,377 square foot equipment enclosure will be constructed next to this building. A generator with fuel tanks and condensers for cooling will be installed within the enclosure. The enclosure will be surrounded by a chain link fence and will be open to the sky. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  11/24/2014 DONE
Third Notice BLD7/18/20077/18/20077/26/2007 DONE
Second Notice has not been responded to.
Second Notice BLD6/21/20076/21/20077/18/2007 DONE
First Notice has not been responded to.
First Notice 5/24/20076/21/2007 DONE
Permanent occupancy  5/24/2007 DONE
Perm. Occ. Cert. # 11632 issued 5-24-07 to T-Mobile Communications.
BLD-Final5/22/20075/22/20075/22/2007PPASS
DetailsMike Jordan
rich; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Ok for perm occ. All issues resolved.
Permanent Occupancy 5/22/20075/22/2007 DONE
Details
FIRE-Final Inspection5/1/20075/1/20075/1/2007PPASS
DetailsTroy Cobbley
Life safety passed.
Temporary occupancy  3/26/2007 DONE
Temp. Occ. Cert. # 5559 issued 3-26-07 to T-Mobile Communications.
BLD-Final3/22/20073/23/20073/23/2007PPART
DetailsMike Jordan
rich ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Temp. occ. granted. Needs to post HC signs and finish installing grab bars in restrooms. Replace door hardware on janitors closet to lever type. All ceiling grid issues have been resolved and is ok to cover.
FIRE-Final Inspection3/23/20073/23/20073/23/2007PPART
DetailsTroy Cobbley
A temporary occupancy was given with dave hannimans permission until items as noted by mike timmermans inspection have been corrected for the fire alarm and suppression permits. Also the battery containment issues needs addressed.
BLD-Other3/21/20073/21/20073/21/2007PFAIL
DetailsMike Jordan
Rich Ceiling ; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Tile already in place. Noted upon further insp. that additional wires needed for diffusers, etc... Also needs rto remove wall angle used to attach runners and used approved connectors.
Code Occupancy Approval3/19/20073/19/20073/20/2007PPASS
DetailsCarol Montgomery
Meets compliance (insp. on 3-19-2007)
Code Occupancy Approval3/14/20073/16/20073/19/2007ACANC
DetailsCarol Montgomery
Rich called at approx. 4:00pm- NR
Code Occupancy Approval3/13/20073/13/20073/14/2007PCANC
DetailsCarol Montgomery
Called Rich. They have landscape in and fence posts up. Fence is not completed - so, they are not ready for inspection - schedule inspection for Friday (3-16-2007)
FIRE-Final Inspection2/22/20072/22/20072/22/2007PFAIL
DetailsTroy Cobbley
Inspection was not for a final but for a cover inspection on part of the sprinkler piping. The sprinkler piping in the areas outside of the pre-action system areas are ok to cover.
BLD-Framing/Rough-in2/9/20072/9/20072/9/2007PPASS
DetailsMike Jordan
rich; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. On site to inspect truss penetration repair at 1hr fire barrier wall around battery room. All modifications were done in accordance with plans approved by G. Slane
Plan resubmittals received  1/25/2007  
Received 4 copies of page T2; given to Carl Westfall and George Slane.
Plan resubmittals received  12/15/2006  
received form from conger saucerman general cont (2) pages & "4" sheets of T2- plans taken to carl westfall
Plan Reviewer's activity  12/15/2006 DONE
Sent resubmitted drawings to George Slane, Building Official.
BLD-Framing/Rough-in11/27/200611/28/200611/28/2006AFAIL
DetailsMike Jordan
richard; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Wood truss and wood beam penetrations not allowed at 1hr fire barrier wall. Architect to provide UL approved listed assembly for wood truss and wood beam penetrations or provide detail to plan review for approval for aequate protection.
Print Occupancy Form  11/6/2006 DONE
Telephone call  11/6/2006 DONE
tlk to david sarver ###-#### that permit and fees are ready to be picked up but needs GC/RCE and RP
Permit Ready to Issue  11/6/2006 DONE
Issue PAID IN FULL permit  11/6/2006  
Plan resubmittals received  11/3/2006  
Received 1 cover letter, 2 copies of sheets T1, E1, E3 and taken to Carl Westfall
Routing - PLAN CHECK10/17/2006 11/2/2006 PASS
Drawings approved after resubmittal review.
Routing - PLANNING11/2/2006 11/2/2006 PASS
Approved per DRH06-00365
Routing - PLAN CHECK11/2/2006 11/2/2006  
PLANS/APPL TAKEN TO FRONT DESK  11/2/2006 DONE
Plan assigned to (CJW)9/22/2006 11/2/2006 PASS
11/2/2006 16:22:15 CJW - activity updated through activity BLDA022 from case BLD06-02615.
Plan resubmittals received  10/30/2006 DONE
Received letter of transmittal,1 letter, 1 review, & 2 copys of sheets T1,A1,A3,A4,A6,E4,E5 taken to Carl W.
Routing - FIRE10/16/2006 10/17/2006 PASS
Attached review comments to plans.
1st review completed  10/17/2006 FAIL
Failed planning and plan check.
Routing - PLAN CHECK9/26/2006 10/16/2006 FAIL
The IBC plan review was started on October 13. 2006 and was finished on October 16, 2006. Revised drawings were required. See the plan review report.
Plan resubmittals received  10/4/2006  
Received 2 copies of sheets A0 from Planning & Zoning (Greg Johnson) and taken to Carl Westfall
Routing - Erosion and Sediment9/25/2006 9/26/2006 PASS
ESC plan waiver approved with attached conditions.
Routing - PLANNING9/26/2006 9/26/2006 FAIL
A revised site plan showing that conditions have been met must be submitted to Design Review. The revised site plan must also be included with building permit plans.
Routing - PUBLIC WORKS9/22/2006 9/25/2006 PASS
Application received  9/12/2006  
Recd Pcfee & Taken To Pln CK  9/12/2006 DONE
Plans ACCEPTED BY PLAN TECH  9/12/2006 DONE
Spoke with David Sarver and told him that the Lighting compliance may need corrected E-4, T-1 codes used for design Plumbing is blank, and fire code 2000///9/12/06 @ 9:00am BAS