Third Notice BLD | 4/2/2007 | 4/2/2007 | 4/2/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/21/2007 | 3/21/2007 | 4/2/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 3/1/2007 | 3/1/2007 | 3/21/2007 | | DONE |
Dave Hannah
|
|
|
|
Letter of compliance | | | 3/16/2007 | | DONE |
|
|
|
Letter of Compliance issued 3-16-07
|
BLD-Final | 2/28/2007 | 3/1/2007 | 3/1/2007 | P | PASS |
Dave Hannah
|
|
|
greg; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
DOC - Permit Finaled | 3/1/2007 | 3/1/2007 | 3/1/2007 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 3/1/2007 | 3/1/2007 | 3/1/2007 | P | PASS |
Forrest France
|
|
|
Duplicate entry, inspection passed.
|
FIRE-Final Inspection | 2/23/2007 | 2/26/2007 | 3/1/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety passed inspection, noted two covers at SD to be removed after const. cleaning is finished and prior to occupancy, contractor also agreed to remove locking hasp at the door to the mech. room while on site.
|
BLD-Final | 2/23/2007 | 2/26/2007 | 2/26/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/23/2007 at 7:31:19 PM. Contact: ###-####.ok for perm occ after other trades go perm
|
Telephone call | | | 2/12/2007 | | DONE |
|
|
|
gave customer plans per carl wesfall
|
Telephone call | | | 2/8/2007 | | DONE |
|
|
|
talked to sam burrows at ###-#### that revised plans are ready for pickup & no fee
|
BLD-Other | 1/18/2007 | 1/18/2007 | 1/19/2007 | P | PASS |
Dave Hannah
|
|
|
This is for a ceiling inspection. Please contact Greg Bolton @ ###-####. Thank you Phone #: ###-####
|
Telephone call | | | 12/26/2006 | | DONE |
|
|
|
tlk to sam burrows ###-#### that revised permit is ready to be picked and no fee
|
Plan Reviewer's activity | | | 12/23/2006 | | PASS |
|
|
|
Reviewed and approved revised drawings. No additional fees required. CJW
|
BLD-Framing/Rough-in | 12/13/2006 | 12/14/2006 | 12/14/2006 | A | DONE |
Dave Hannah
|
|
|
Please contact Greg Bolton prior to going out at ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
|
BLD-Framing/Rough-in | 12/14/2006 | 12/14/2006 | 12/14/2006 | P | PASS |
Dave Hannah
|
|
|
Please contact Greg Bolton prior to going out at ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
|
Plan resubmittals received | | | 12/11/2006 | | |
|
|
|
Received transmittal sheet and 3 copies of the following pages: A0.1, A2.0, A2.1, A9.0, P1.0, P1.1, M1.0, E1.2, EC2.0; taken to Carl Westfall
|
BLD-Framing/Rough-in | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | PART |
Jim Sly
|
|
|
Please contact Greg Bolton at ###-####, prior to going out. Thank You; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson Walls not per appr plan........Resubmitted plan in plan check for approval.....Contr wants to 1side walls.....OK , but on his own..... do not proceed beyond this until plans appr, and frame insp completed.
|
Issue PAID IN FULL permit | | | 11/17/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/16/2006 | | DONE |
|
|
|
|
Telephone call | | | 11/16/2006 | | DONE |
|
|
|
lft vm with sam burrows ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 11/16/2006 | | DONE |
|
|
|
|
Routing - FIRE | 11/13/2006 | | 11/15/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 11/15/2006 | | 11/15/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/25/2006 | | 11/15/2006 | | PASS |
|
|
|
11/15/2006 13:15:53 CJW - activity updated through activity BLDA022 from case BLD06-02655.
|
Routing - PLAN CHECK | 10/24/2006 | | 11/13/2006 | | |
|
|
|
Sent back to Fire.
|
Plan resubmittals received | | | 11/9/2006 | | |
|
|
|
Received transmittal letter and 3 copies of page A2.0; taken to Carl Westfall
|
Routing - FIRE | 10/20/2006 | | 10/24/2006 | | FAIL |
|
|
|
Faxed resubmittal item to architect. Attached review comments to plans.
|
1st review completed | | | 10/24/2006 | | FAIL |
|
|
|
Failed fire.
|
Routing - PLAN CHECK | 9/26/2006 | | 10/20/2006 | | PASS |
|
|
|
The IBC plan review was started on October 19, 2006 and was finished the next day. The drawings were approved per the plan review report and 'red lines' on the drawings.
|
Routing - PUBLIC WORKS | 9/25/2006 | | 9/26/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2006 | | |
|
|
|
|
Application received | | | 9/15/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/15/2006 | | |
|
|
|
|