Permit Information
Permit NumberBLD06-02655
StatusFinaled
Name FALASH & ROSS CONSTRUCTION
Site Address 1010 W JEFFERSON ST (BASEMENT)
Project Name1010 JEFFERSON LLC BLDG
Customer Number 
ePlanReviewNo
Description
(RCE-2502 FALASH & ROSS CONSTRUCTION) (BASEMENT REMODEL) The basement is fire sprinklered. To create a common reception/lobby area (718 square feet), hallway (646 square feet), conference room (560 square feet), and break room (295 square feet) within the 7,863 square foot basement of an existing 2 story with basement building. Fire sprinkler heads in the basement will be changed to quick-response sprinklers in conjunction with this project. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD4/2/20074/2/20074/2/2007 DONE
Second Notice has not been responded to.
Second Notice BLD3/21/20073/21/20074/2/2007 DONE
First Notice has not been responded to.
First Notice3/1/20073/1/20073/21/2007 DONE
DetailsDave Hannah
Letter of compliance  3/16/2007 DONE
Letter of Compliance issued 3-16-07
BLD-Final2/28/20073/1/20073/1/2007PPASS
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
DOC - Permit Finaled3/1/20073/1/20073/1/2007PPASS
DetailsDave Hannah
FIRE-Final Inspection3/1/20073/1/20073/1/2007PPASS
DetailsForrest France
Duplicate entry, inspection passed.
FIRE-Final Inspection2/23/20072/26/20073/1/2007APASS
DetailsForrest France
Fire life safety passed inspection, noted two covers at SD to be removed after const. cleaning is finished and prior to occupancy, contractor also agreed to remove locking hasp at the door to the mech. room while on site.
BLD-Final2/23/20072/26/20072/26/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/23/2007 at 7:31:19 PM. Contact: ###-####.ok for perm occ after other trades go perm
Telephone call  2/12/2007 DONE
gave customer plans per carl wesfall
Telephone call  2/8/2007 DONE
talked to sam burrows at ###-#### that revised plans are ready for pickup & no fee
BLD-Other1/18/20071/18/20071/19/2007PPASS
DetailsDave Hannah
This is for a ceiling inspection. Please contact Greg Bolton @ ###-####. Thank you Phone #: ###-####
Telephone call  12/26/2006 DONE
tlk to sam burrows ###-#### that revised permit is ready to be picked and no fee
Plan Reviewer's activity  12/23/2006 PASS
Reviewed and approved revised drawings. No additional fees required. CJW
BLD-Framing/Rough-in12/13/200612/14/200612/14/2006ADONE
DetailsDave Hannah
Please contact Greg Bolton prior to going out at ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
BLD-Framing/Rough-in12/14/200612/14/200612/14/2006PPASS
DetailsDave Hannah
Please contact Greg Bolton prior to going out at ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
Plan resubmittals received  12/11/2006  
Received transmittal sheet and 3 copies of the following pages: A0.1, A2.0, A2.1, A9.0, P1.0, P1.1, M1.0, E1.2, EC2.0; taken to Carl Westfall
BLD-Framing/Rough-in12/6/200612/7/200612/7/2006APART
DetailsJim Sly
Please contact Greg Bolton at ###-####, prior to going out. Thank You; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
Walls not per appr plan........Resubmitted plan in plan check for approval.....Contr wants to 1side walls.....OK , but on his own..... do not proceed beyond this until plans appr, and frame insp completed.
Issue PAID IN FULL permit  11/17/2006 DONE
Print Occupancy Form  11/16/2006 DONE
Telephone call  11/16/2006 DONE
lft vm with sam burrows ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  11/16/2006 DONE
Routing - FIRE11/13/2006 11/15/2006 PASS
Attached review comments to plans.
Routing - PLAN CHECK11/15/2006 11/15/2006  
PLANS/APPL TAKEN TO FRONT DESK  11/15/2006 DONE
Plan assigned to (CJW)9/25/2006 11/15/2006 PASS
11/15/2006 13:15:53 CJW - activity updated through activity BLDA022 from case BLD06-02655.
Routing - PLAN CHECK10/24/2006 11/13/2006  
Sent back to Fire.
Plan resubmittals received  11/9/2006  
Received transmittal letter and 3 copies of page A2.0; taken to Carl Westfall
Routing - FIRE10/20/2006 10/24/2006 FAIL
Faxed resubmittal item to architect. Attached review comments to plans.
1st review completed  10/24/2006 FAIL
Failed fire.
Routing - PLAN CHECK9/26/2006 10/20/2006 PASS
The IBC plan review was started on October 19, 2006 and was finished the next day. The drawings were approved per the plan review report and 'red lines' on the drawings.
Routing - PUBLIC WORKS9/25/2006 9/26/2006 PASS
Plans ACCEPTED BY PLAN TECH  9/18/2006  
Application received  9/15/2006  
Recd Pcfee & Taken To Pln CK  9/15/2006