Case Summary (BLD) | | | 11/17/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/17/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/17/2016 | | DONE |
|
|
|
|
Third Notice BLD | 7/23/2007 | 7/23/2007 | 7/26/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 7/12/2007 | 7/12/2007 | 7/23/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/28/2007 | 7/12/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/28/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11683 issued 6-28-07 to thre Old Spaghetti Factory.
|
BLD-Final | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PASS |
Dave Hannah
|
|
|
ok for perm occ
|
Permanent Occupancy | | 6/27/2007 | 6/27/2007 | | DONE |
|
|
|
|
BLD-Final | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PART |
Dave Hannah
|
|
|
steve - late morning please ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for temp occ
|
Temporary occupancy | | | 5/23/2007 | | DONE |
|
|
|
Temp. Occ. Cert. #5589 issued 5-23-07 to the Old Spaghetti Factory.
|
FIRE-Final Inspection | 5/18/2007 | 5/21/2007 | 5/21/2007 | A | PASS |
Forrest France
|
|
|
Required corrections have been made, fire life safety inspection passed.
|
BLD-Final | 5/17/2007 | 5/18/2007 | 5/18/2007 | P | NR |
Dave Hannah
|
|
|
steve - early aft; Phone #: ###-#### Internet Inspection Request from: Victoria Beall needes fire life safty finaled
|
FIRE-Final Inspection | 5/17/2007 | 5/18/2007 | 5/18/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide plans for the shell permit and do inspection, final sprinkler permit, repair the exit discharge lighting on the front single man door exits and provide the occupant load signs as discussed.
|
BLD-Conference | 4/11/2007 | 4/11/2007 | 4/12/2007 | P | PASS |
Dave Hannah
|
|
|
talked about gettind a c.c
|
BLD-Framing/Rough-in | 3/12/2007 | 3/13/2007 | 3/14/2007 | A | CANC |
Jim Storey
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 3/1/2007 | 3/2/2007 | 3/2/2007 | P | PART |
Jim Sly
|
|
|
Steve; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
BLD-Framing/Rough-in | 2/20/2007 | 2/20/2007 | 2/20/2007 | P | FAIL |
Dave Hannah
|
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs spec inspection sign off
|
Issue PAID IN FULL permit | | | 1/26/2007 | | DONE |
|
|
|
|
MISC ACTIONS | | | 1/24/2007 | | |
|
|
|
proofed permit for correct fees
|
Case Summary (BLD) | | | 1/23/2007 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/23/2007 | | DONE |
|
|
|
modified fire review comments to reflect changed floor plan occupant loads.
|
Print Occupancy Form | | | 1/23/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/22/2007 | | DONE |
|
|
|
Letter from tenant owner was received.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/11/2007 | | 1/22/2007 | | PASS |
|
|
|
Drawings approved after 4th review.
|
Plan assigned to (CJW) | 10/9/2006 | | 1/22/2007 | | PASS |
|
|
|
1/22/2007 17:07:00 CJW - activity updated through activity BLDA022 from case BLD06-02665.
|
Plan resubmittals received | | | 1/17/2007 | | |
|
|
|
Rec'd 1 transmittal cover - 2 copies of 2 page response letter - 2 copies of sheet # A-2.3 - taken to Carl Westfall
|
Routing - PLUMBING | 1/10/2007 | | 1/11/2007 | | PASS |
|
|
|
Revised plumbing plans submitted. 120 deg, max hot water to hand sinks 48, and 139. use boise city approved grease interceptor detail attached.
|
Routing - PUBLIC WORKS | 1/9/2007 | | 1/10/2007 | | PASS |
|
|
|
Sent back for sewer fee adjustment. The large dining area was enlarged but a small dining room was converted to a storage room.
|
Meeting | | | 1/10/2007 | | DONE |
|
|
|
Met with Mike & Paul (building owners) and with Barry (contractor) about the unresolved issues holding up the tenant improvement permit (BLD06-02665). It was decided that the tenant improvement permit will be issued when the following has been done:
(1) A letter is submitted from Mike & Paul (building owners) to George Slane, Building Official, stating that an acceptable resolution to the ventilation and insulation issues will be proposed by February 10, 2007 and submitted as a revision to the shell permit (BLD06-02785).
(2) A letter is submitted from the owners of the Old Spaghetti Factory to George Slane, Building Official, stating that they are aware that occupancy to the building will NOT be allowed until the ventilation and insulation issues are resolved.
(3) Resubmitted drawings are received showing the routes to the trolley booths accessible to the disabled.
|
Routing - PLAN CHECK | 11/27/2006 | | 1/9/2007 | | FAIL |
|
|
|
(12-22-06) Finished resubmittal review. Several items still need resolution. See the revised plan review report. E-mailed a copy to the Architect's representative. (1-9-07) The 2nd resubmittal review was completed. Three (3) items are not resolved (#19, #25, #40). See the plan review report.
|
Plan resubmittals received | | | 1/5/2007 | | |
|
|
|
Received 1 cover transmittal, 2 copies of response letter, 2 copies of the following sheets--CS-01, A2.1, A5.4, EN1.2, MP0.1, M2.1, M9.1, P0.1, P0.2, P2.1, P2.2, P4.1, P4.2, P9.1, E2.1, E3.1, E4.1, E4.2, E6.1, E9.1, E9.2, K1, K2, K3, K4, K5, K6, K7, K8, K9, K10, K11, K12, K13, K14, K15, K16, K17, K18 and taken to Carl Westfall
|
Plan resubmittals received | | | 12/19/2006 | | |
|
|
|
Received 1 cover transmittal, 2 copies of the following-2 sets of addendum #2 which constists of 29 pages of plan review responses, specifications and revised specification index, 2 copies of the following sheets--CS-01, AS-1.1, A-2.1, A-2.2, A-2.3, A-2.4, A-5.1, A-5.4, A-6.1, E-2.1, M-9.1 and taken to Carl Westfall
|
1st review completed | | | 11/27/2006 | | FAIL |
|
|
|
Failed plan check.
|
Routing - FIRE | 11/21/2006 | | 11/27/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 11/8/2006 | | 11/21/2006 | | FAIL |
|
|
|
The IBC plan review was started on November 18, 2006 and was finished on November 21, 2006. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 11/8/2006 | | 11/8/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/19/2006 | | 11/8/2006 | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2006 | | 10/19/2006 | | FAIL |
|
|
|
Revisions required for street lighting. Contact Hank A. ###-####
|
Routing - PLUMBING | 10/12/2006 | | 10/17/2006 | | PASS |
|
|
|
move DCVA inside building per united water. additional cross connection protection will be required at the soda mech., coffee maker, upstream of the filter rack, etc.. use boise city approved grease interceptor detail, attached. 3-compartment sink must be indirectly wasted. provide floor sink. pipe rtu make-up water drain to s.s. with airgap. piping on the roof at the boiler must be protected from freezing.
|
Routing - PLANNING | 10/10/2006 | | 10/12/2006 | | PASS |
|
|
|
Julie Archambeault DRH06-00273
|
Routing - PUBLIC WORKS | 10/9/2006 | | 10/10/2006 | | FAIL |
|
|
|
Please send these plans back to Public Works for additional review on street lights. Contact Hank ###-####
|
Routing - Addressing | 10/9/2006 | | 10/9/2006 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/4/2006 | | DONE |
|
|
|
Mechanical and plumbing plans must be STAMPED & SIGNED prior to issuance of the building permit. Plans okay to begin routing as letter is attached from the State Board of Engineering noting that John Frank Rogers has been granted a temporary Idaho license which will expire on Aug. 31, 2008. (msouthard)
|
Recd Pcfee & Taken To Pln CK | | | 10/4/2006 | | DONE |
|
|
|
|
Application received | | | 9/15/2006 | | |
|
|
|
|