Case Summary (BLD) | | | 11/15/2011 | | DONE |
|
|
|
|
Third Notice BLD | 2/22/2007 | 2/22/2007 | 3/13/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 2/7/2007 | 2/7/2007 | 2/22/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
Telephone call | | | 2/13/2007 | | DONE |
|
|
|
Called Bob Runyon. Left a message. Need new bld permit application for processing.
|
First Notice | | 1/25/2007 | 2/7/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/25/2007 | 1/25/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/25/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11397 issued to Meals Squared.
|
Plan resubmittals received | | | 1/24/2007 | | |
|
|
|
Received document transmittal, 9pg. details on mechanical equipment, 2 copies of page M1.0; per Carl Westfall ok to log in as resubmittals, plans taken to him
|
BLD-Final | 1/16/2007 | 1/17/2007 | 1/17/2007 | A | NR |
Jim Storey
|
|
|
Derrick; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
FIRE-Final Inspection | 12/20/2006 | 12/21/2006 | 12/21/2006 | A | PASS |
Forrest France
|
|
|
Required corrections are complete, the automatic flush bolts at the main entry/exit doors are to be installed prior to structural final. Noted the range oven and hood are not to be installed per contractor.
|
Temporary occupancy | | | 12/21/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5495 issued 5495 issued 12-21-06 to Meals Squared.
|
BLD-Final | 12/20/2006 | 12/20/2006 | 12/20/2006 | P | PART |
Jim Storey
|
|
|
derrick; Phone #: ###-#### Internet Inspection Request from: Patricia Smith temp only need reinsp. for final perm. ok pending others.
|
FIRE-Final Inspection | 12/19/2006 | 12/20/2006 | 12/20/2006 | A | FAIL |
Forrest France
|
|
|
Duct detectors are not powered to enable testing or functionality.
|
BLD-Final | 12/19/2006 | 12/20/2006 | 12/20/2006 | A | DEFR |
Jim Storey
|
|
|
derrick; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Final | 12/19/2006 | 12/19/2006 | 12/19/2006 | P | CANC |
Jim Storey
|
|
|
Derik note: call 30min before insp; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett
|
FIRE-Final Inspection | 12/18/2006 | 12/19/2006 | 12/19/2006 | A | FAIL |
Forrest France
|
|
|
Provide building address numbers, manual flush bolts are not allowed at the main entry/exit pair of doors, door hardware at the mech. room is not approved, need provide testing for the two duct detectors.
|
BLD-Other | 12/14/2006 | 12/14/2006 | 12/14/2006 | P | PASS |
Jim Storey
|
|
|
Derik Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Sherri Bennettceilling ok pending others
|
Case Summary (BLD) | | | 12/11/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 11/28/2006 | 11/28/2006 | 11/28/2006 | P | PART |
Jim Storey
|
|
|
Derek Cooper; Phone #: ###-#### Internet Inspection Request from: Letitia Gallop
|
Inspection Record Card- Bld | | | 11/15/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/15/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/15/2006 | | |
|
|
|
|
Telephone call | | | 11/15/2006 | | DONE |
|
|
|
customer came in & will pick up later
|
Issue PAID IN FULL permit | | | 11/15/2006 | | |
|
|
|
|
Plan assigned to (CJW) | 10/2/2006 | | 11/14/2006 | | PASS |
|
|
|
11/14/2006 16:56:35 CJW - activity updated through activity BLDA022 from case BLD06-02699.
|
Routing - FIRE | 11/13/2006 | | 11/14/2006 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLAN CHECK | 11/14/2006 | | 11/14/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/7/2006 | | 11/13/2006 | | |
|
|
|
Inserted revised drawings required by Fire.
|
Plan resubmittals received | | | 11/13/2006 | | |
|
|
|
Received 1 response, & 2 copys of sheets A1.1,H1.0 taken to Carl W.
|
Routing - PUBLIC WORKS | 11/13/2006 | | 11/13/2006 | | PASS |
|
|
|
Added drinking fountain
|
Routing - FIRE | 11/3/2006 | | 11/6/2006 | | FAIL |
|
|
|
Dave Hanneman has determined that the residential stove, which is used for a commercial purpose, will require a commercial type 1 hood system. Resubmittal item has been faxed to the architect. Review comments have been inserted into plans.
|
Plan resubmittals received | | | 11/6/2006 | | |
|
|
|
Received 1pg. response letter addressed to Scott Arellano from Patrick McKeegan, and 2 copies of pages A1.1 & A1.3; taken to Carl Westfall
|
Routing - PLAN CHECK | 11/1/2006 | | 11/3/2006 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
1st review completed | | | 11/1/2006 | | FAIL |
|
|
|
Failed fire and Plan check.
|
Routing - FIRE | 10/24/2006 | | 11/1/2006 | | FAIL |
|
|
|
Faxed resubmittal items to architect. Forwarded request letter to Dave Hanneman. Attached review comments to plans.
|
Plan resubmittals received | | | 10/25/2006 | | |
|
|
|
Received 1 copy of response letter from Pat McKeegan, 1 copy of memo dated 7/7/99 from Pat McKeegan, 1 copy of Boise City Plan analysis dated 4/16/99, 2 copies of sheets--T1.0, A1.1, A1.2, A1.3, A5.1 and taken to Carl Westfall
|
Routing - PLUMBING | 10/23/2006 | | 10/24/2006 | | PASS |
|
|
|
cold water tenant isolation valve must be in this tenant space.
|
Routing - PLAN CHECK | 10/3/2006 | | 10/23/2006 | | FAIL |
|
|
|
The IBC plan review was started on October 21, 2006 and was finished on October 23, 2006. Revised drawings were required. See the plan review report.
|
Routing - PLANNING | 10/3/2006 | | 10/3/2006 | | PASS |
|
|
|
Approved per CZC06-00192
|
Routing - PUBLIC WORKS | 10/2/2006 | | 10/3/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/20/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/20/2006 | | |
|
|
|
|
Application received | | | 9/19/2006 | | |
|
|
|
|