Case Summary (BLD) | | | 11/17/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/17/2016 | | DONE |
|
|
|
|
BLD-Final | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PASS |
Dave Hannah
|
|
|
steve - late morning please ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
Letter of compliance | | | 5/23/2007 | | DONE |
|
|
|
Letter of Compliance issued 5-23-07.
|
BLD-Framing/Rough-in | 5/22/2007 | 5/22/2007 | 5/22/2007 | P | CANC |
Dave Hannah
|
|
|
|
BLD-Final | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | FAIL |
Dave Hannah
|
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs other signoffs
|
FIRE-Final Inspection | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | PASS |
Forrest France
|
|
|
Shell life safety passed.
|
BLD-Framing/Rough-in | 4/26/2007 | 4/27/2007 | 4/30/2007 | A | FAIL |
Dave Hannah
|
|
|
steve - ceiling grid for kitchen area ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs elec r/i wire up lights ect
|
BLD-Framing/Rough-in | 4/25/2007 | 4/26/2007 | 4/26/2007 | A | NR |
Dave Hannah
|
|
|
steve - ceiling grid for kitchen area ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs elec final
|
Plan Reviewer's activity | | | 4/5/2007 | | DONE |
|
|
|
Revised the plan review report to document that the requirement for roof insulation and ventilation was deferred.
|
BLD-Framing/Rough-in | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | PART |
Dave Hannah
|
|
|
Steve mid morning if possible; Phone #: ###-#### Internet Inspection Request from: Stacie Backus insulation ok in extb walls ok to cover
|
BLD-Framing/Rough-in | 3/19/2007 | 3/20/2007 | 3/20/2007 | A | PART |
Dave Hannah
|
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to cover int wallc and soffits
|
BLD-Framing/Rough-in | 3/12/2007 | 3/13/2007 | 3/14/2007 | A | CANC |
Jim Storey
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Plan resubmittals received | | | 3/8/2007 | | |
|
|
|
Received transmittal sheet, 1pg. letter, 1pg. ventilation detail, 1pg. info on WMP-VR Black, 1pg. report on Insulstar spray foam, and 2 copies of page A1.3; taken to Carl Westfall
|
BLD-Framing/Rough-in | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PART |
Jim Sly
|
|
|
Steve; Phone #: ###-#### Internet Inspection Request from: Stacie Backus OK to cover Kitchen area ....and area North of Kitchen.
|
Plan resubmittals received | | | 2/28/2007 | | |
|
|
|
Received 1 cover transmittal letter, 2 page letter from BRS(Jeff), 1 letter from Elkhorn, 2 copies of sheet A1.3 and taken to Carl Westfall
|
Plan resubmittals received | | | 2/21/2007 | | DONE |
|
|
|
rec'd transmittal cover - memo from BRS Architects - legacy report - spray foam insulation report - memo from system design consultants - venting report - 2 set of sheet #s A1.3 - taken to Carl Westfall
|
Plan Reviewer's activity | | | 2/21/2007 | | FAIL |
|
|
|
Considered proposal for roof insulation and ventilation. Proposal NOT approved. Letter sent to Jeff Likes (arch rep).
|
BLD-Framing/Rough-in | 2/20/2007 | 2/20/2007 | 2/20/2007 | P | FAIL |
Dave Hannah
|
|
|
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs other trades to sign off need to resubmit insulation plans no inspection done
|
BLD-Other | 1/10/2007 | 1/11/2007 | 1/12/2007 | A | PART |
Dave Hannah
|
|
|
steve - rebar ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith shear walls along front of bld ok to pour after mti spec inspection is oked
|
BLD-Framing/Rough-in | 12/27/2006 | 12/28/2006 | 12/29/2006 | A | PART |
Dave Hannah
|
|
|
TIM; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles wall on roof area back of bld needs fire blking
|
BLD-Footing | 12/7/2006 | 12/7/2006 | 12/7/2006 | P | PART |
Dave Hannah
|
|
|
Steve or Tim; Phone #: ###-#### or ###-#### Internet Inspection Request from: Cathy Weisshaupt column and shear wall ftgs ok will have mti do spec inspection
|
Issue PAID IN FULL permit | | | 12/7/2006 | | DONE |
|
|
|
|
Telephone call | | | 12/6/2006 | | DONE |
|
|
|
tlk to trent 12/5/2006 that permit and fees are ready to be picke dup but needs ACHD
|
Permit Ready to Issue | | | 12/6/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/16/2006 | | 12/5/2006 | | PASS |
|
|
|
Drawings approved after issues were resolved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2006 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/5/2006 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/27/2006 | | 12/5/2006 | | PASS |
|
|
|
12/5/2006 11:37:54 CJW - activity updated through activity BLDA022 from case BLD06-02785.
|
Routing Off Site - STRUCTURAL | 11/30/2006 | | 12/4/2006 | | PASS |
|
|
|
Called Action Courier for pick up @ 9:35am on 11/30/06 BAS
(12-4-06) The structural concerns of the Consultant Structural Engineer were resolved. CJW
|
Plan resubmittals received | | | 11/29/2006 | | |
|
|
|
received a transmittal from brs architects & (2) page memo. also from stapley engineering structural engineers calculations (9) pages each of 2 sets.also a temporary license agreement app from achd (4) pages.also "3" sets of plans 3 sheets each of SO.1, D1.1, A1.1, A3.2, A4.1, & A5.1--plans taken to carl westfall
|
Routing - FIRE | 11/14/2006 | | 11/16/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 11/16/2006 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PLAN CHECK | 10/19/2006 | | 11/14/2006 | | FAIL |
|
|
|
The IBC plan review was started on October 28, 2006 and was finished on November 14, 2006. There was a delay in sending the drawings to a consultant Structural Engineer (he completed his 1st review is less than 10 working days). The re-assignment of projects also contributed in the long review time. Revised drawings were required. See the plan review report. CJW
|
Routing Off Site - STRUCTURAL | 10/30/2006 | | 11/9/2006 | | FAIL |
|
|
|
(10-30-06) Called Action Couriers for pick up 10-30-06 8:55 am (11-14-06) The first structural review was completed on November 9, 2006.
|
Plan resubmittals received | | | 11/6/2006 | | |
|
|
|
Received revised Certificate of value to split out demolition, and Cert of value for demo project.
|
Routing - Erosion and Sediment | 10/26/2006 | | 10/26/2006 | | PASS |
|
|
|
Independant set of drawings incorporated into the lager set on October 28, 2006. CJW
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 10/18/2006 | | 10/19/2006 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/6/2006 | | 10/18/2006 | | |
|
|
|
|
Plan resubmittals received | | | 10/17/2006 | | DONE |
|
|
|
Received 1 transmittal,2 addendum, & 2 copys of sheets CS-01,A-2.1,A-2.2,A-2.3,A-3.1,A-4.1,A-5.2,A-5.3,A-5.5,A-6.2,EN1.2,M2.1,M9.1,P0.1,P0.2,P2.1,P2.2,P4.1,P4.2,P9.1,E0.1,E2.1,E3.1,E4.1,E4.2,E6.1,E9.1.E9.2 K3 taken to Carl W. (11-14-06) These drawings actually apply to the tenant improvement permit BLD06-02665. CJW
|
Routing - PLANNING | 10/4/2006 | | 10/6/2006 | | PASS |
|
|
|
Julie Archambeault DRH06-00273
|
Routing - PLUMBING | 9/28/2006 | | 10/4/2006 | | PASS |
|
|
|
use boise city approved grease interceptor detail, attached.
|
Plan resubmittals received | | | 10/2/2006 | | DONE |
|
|
|
Received 1transmittal,2 esc applications,2 narratives,2 copys of sheet ESC-1 taken to Carl W.
|
Routing - Erosion and Sediment | 9/28/2006 | | 9/29/2006 | | FAIL |
|
|
|
ESC plan failed. Project will require an ESC permit, there was no ESC application or narrative included with submittal. Notified architect at BRS (Jeff Likes).
|
Routing - PUBLIC WORKS | 9/27/2006 | | 9/28/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/27/2006 | | DONE |
|
|
|
Was Short $207.85 so I applied the difference to the APP Permit
|
Plans ACCEPTED BY PLAN TECH | | | 9/27/2006 | | |
|
|
|
|
Application received | | | 9/26/2006 | | |
|
|
|
|