First Notice | | 8/18/2009 | 9/15/2009 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/18/2009 | | DONE |
Tim L. Woodard
|
|
|
On August 18th 2009 Adam Ware contacted me to inform us of a name change only. It is the same company ownership and the exact same use just a change in use. I changed the name and had a new C of O printed to reflect the new name. TLW Old Name - HEADMASTERS SCHOOL OF HAIR.
|
Permanent Occupancy | | | 8/18/2009 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 11/3/2008 | | |
|
|
|
|
Third Notice BLD | 7/18/2007 | 7/18/2007 | 8/30/2007 | | DONE |
|
|
|
This permit finaled on the web by Anna Buschbacher
|
Second Notice BLD | 7/5/2007 | 7/5/2007 | 7/18/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/22/2007 | 7/5/2007 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 6/22/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11675 issued 6-22-07 to the Headmasters School of Hair Design.
|
FIRE-Final Inspection | 6/20/2007 | 6/20/2007 | 6/21/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 6/20/2007 | 6/20/2007 | 6/20/2007 | P | PASS |
Tom Arcoraci
|
|
|
jack; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
Permanent Occupancy | | 6/20/2007 | 6/20/2007 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/19/2007 | 6/19/2007 | 6/19/2007 | P | PART |
Forrest France
|
|
|
Need final for the project related fire sprinkler permit, noted tape at two sprinkler heads in the mezz. storage area to be removed, post one additional PFE at the front entrance as discussed, remainder of fire life safety items appear acceptable.
|
BLD-Other | 5/17/2007 | 5/18/2007 | 5/18/2007 | A | PASS |
Tom Arcoraci
|
|
|
mat - grid; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Conference | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PASS |
Tom Arcoraci
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Beall nand rails ect
|
BLD-Framing/Rough-in | 2/26/2007 | 2/27/2007 | 2/27/2007 | A | PASS |
Tom Arcoraci
|
|
|
matt ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 2/9/2007 | 2/9/2007 | 2/9/2007 | P | PASS |
Dave Hannah
|
|
|
matt hall; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt ok to cover int walls
|
Telephone call | | | 1/5/2007 | | DONE |
|
|
|
lft ms for dwaine carver ###-#### that permit and fees are ready to be picked up but needs GC/RCE
|
Permit Ready to Issue | | | 1/5/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/5/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/4/2007 | | DONE |
|
|
|
|
Routing - FIRE | 1/2/2007 | | 1/2/2007 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLAN CHECK | 1/2/2007 | | 1/2/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2007 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/27/2006 | | 1/2/2007 | | PASS |
|
|
|
1/2/2007 15:57:54 CJW - activity updated through activity BLDA022 from case BLD06-03094.
|
Routing - PLAN CHECK | 12/27/2006 | | 1/2/2007 | | |
|
|
|
Resubmitted drawings inserted and drawings sent back to Fire.
|
Plan resubmittals received | | | 12/27/2006 | | |
|
|
|
Received 1pg. response letter addressed to Scott Arellano, and 2 copies of page A2.1; taken to Carl Westfall
|
Routing - PLANNING | 12/26/2006 | | 12/27/2006 | | PASS |
|
|
|
Plans adhere to CUP approval.
|
Routing - PLUMBING | 12/22/2006 | | 12/26/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - FIRE | 12/20/2006 | | 12/22/2006 | | FAIL |
|
|
|
Faxed resubmittal item to archtiect. Attached updated review comments to plans.
|
Routing - PLAN CHECK | 12/7/2006 | | 12/20/2006 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 12/15/2006 | | |
|
|
|
Received 9pg. letter of response from Trout Architects, 3pg. letter of response from Musgrove Engineering, 2 copies of the following pages: cover page(A0.0), A2.1, A2.5, A5.1, A5.4, A5.5, A8.1, MC1.1, M1.1, M2.1, M3.1, M4.1, P1.1, P2.1, P2.2, P3.1; taken to Carl Westfall
|
1st review completed | | | 12/7/2006 | | FAIL |
|
|
|
|
Routing - FIRE | 12/2/2006 | | 12/7/2006 | | FAIL |
|
|
|
Faxed resubmittal items to the architect. Attached review comments to plans.
|
Routing - PLAN CHECK | 10/31/2006 | | 12/2/2006 | | FAIL |
|
|
|
The IBC plan review was started on November 27, 2006 and was finished on December 2, 2006. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 11/14/2006 | | DONE |
|
|
|
Received three copies of plans sheet P2.1 with letter of transmittal and plumbing plan review comments.
|
Routing - PLUMBING | 10/30/2006 | | 10/31/2006 | | FAIL |
|
|
|
shampoo sinks are 3 fixture unit fixtures on the waste side. 2" waste to the group on the east wall is undersized. waste to the 10 unit group isn't sized and the 2" vent is undersized. 2" waste to the wet dispense/break area is undersized. 2" to the 4 shampoo sinks in the classrooms and student break room is undersized.
|
Routing - PLANNING | 10/30/2006 | | 10/30/2006 | | FAIL |
|
|
|
Cody Riddle (verify if this is an allowed use in a C-2D zone)
This use requires a conditional use permit. Contacted applicant via telephone at 9:45 a.m. on 10/30/06. CER
|
Routing - PUBLIC WORKS | 10/27/2006 | | 10/30/2006 | | PASS |
|
|
|
|
Pending Assignment by MYS | 10/26/2006 | | 10/27/2006 | | DONE |
|
|
|
10/27/2006 09:44:23 MYS - activity updated through activity BLDA172 from case BLD06-03094.
|
Recd Pcfee & Taken To Pln CK | | | 10/26/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/26/2006 | | |
|
|
|
|
Application received | | | 10/26/2006 | | |
|
|
|
|