Override - People Holds | | | 10/29/2009 | | |
|
|
|
|
Permanent Occupancy | | | 10/29/2009 | | DONE |
|
|
|
|
BLD-Final | 10/27/2009 | 10/27/2009 | 10/27/2009 | P | PASS |
Jim Sly
|
|
|
###-#### - tony units A & D........ All four units inspected and passed. Four unit Building passed. OK for Perm. Occ.
|
Override - People Holds | | | 10/27/2009 | | |
|
|
|
|
Override - People Holds | | | 8/19/2009 | | |
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 8/19/2009 | | DONE |
|
|
|
|
BLD-Final | 8/18/2009 | 8/18/2009 | 8/18/2009 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/18/2009 at 10:53:40 AM. Contact: ###-####. OK for Temp Occ. Unit 14C 2858 N. Cloverdale.
|
BLD-Final | 1/17/2009 | 1/20/2009 | 1/20/2009 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/17/2009 at 9:27:50 AM. Contact: ###-####. OK for temp occ on unit 14B only. OK to Perm when all trades Perm on remaining (3) units included on this permit. Note: Fire has approved for Perm. Occ on all four units.
|
FIRE-Final Inspection | 1/17/2009 | 1/20/2009 | 1/20/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Override - People Holds | | | 1/20/2009 | | |
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 1/20/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
BLD-Final | 1/16/2009 | 1/16/2009 | 1/16/2009 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/16/2009 at 11:17:50 AM. Contact: ###-####. Need Fire Final OK
|
FIRE-Final Inspection | 1/14/2009 | 1/16/2009 | 1/16/2009 | A | PART |
Troy Cobbley
|
|
|
The addresses of 2842, 2844 and 2860 are ok to occupy. Address 2858 does not have the smoke alarms placed as per the plans. Basically two smoke alarms have not been placed immediately outside of the bedrooms but instead have been placed in the common areas near the peak. Plan review approval is required if they are to remain or they will need to be placed as per the plans.
|
BLD-Conference | 1/14/2009 | 1/14/2009 | 1/14/2009 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/14/2009 at 10:40:59 AM. Contact: ###-####. Need Fire, P/W and Electr finals.
|
Zoning Approval | 11/25/2008 | 11/25/2008 | 11/25/2008 | | PASS |
Sarah Schafer
|
|
|
|
Override - People Holds | | | 11/25/2008 | | |
|
|
|
|
BLD-Conference | 11/24/2008 | 11/24/2008 | 11/24/2008 | P | DONE |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/24/2008 at 8:04:06 AM. Contact: ###-####. Gave list of Req. for final.
|
BLD-Conference | 10/8/2008 | 10/9/2008 | 10/10/2008 | A | PEND |
Jim Sly
|
|
|
Level 3 Dev. working on finals for all permits on issued status.
|
BLD-Conference | 10/7/2008 | 10/7/2008 | 10/8/2008 | P | CANC |
Jim Sly
|
|
|
level 3 dev company Phone #: ###-####
|
Override - People Holds | | | 10/7/2008 | | |
|
|
|
|
(F) Reprint permit | | | 10/10/2007 | | |
|
|
|
|
BLD-Energy code compliance | 7/9/2007 | 7/10/2007 | 7/10/2007 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/9/2007 at 11:27:26 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/28/2007 | 6/29/2007 | 6/29/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/28/2007 at 10:29:31 AM. Contact: ###-####.
|
BLD-Conference | 6/13/2007 | 6/13/2007 | 6/13/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/13/2007 at 8:12:17 AM. Contact: ###-####. Shear wall OK
|
BLD-Conference | 6/1/2007 | 6/4/2007 | 6/4/2007 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/1/2007 at 4:55:12 PM. Contact: ###-####.
|
BLD-Other | 4/27/2007 | 4/27/2007 | 4/27/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/27/2007 at 9:41:50 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 3/28/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/13/2007 | | |
|
|
|
|
Telephone call | | | 3/13/2007 | | DONE |
|
|
|
t/c w jeff likes at ###-####, permit ready and fees given - also needs to furnish RCE# and the RP name
|
Override - Parcel Holds | | | 3/13/2007 | | |
|
|
|
|
Permit Ready to Issue | | | 3/13/2007 | | |
|
|
|
|
Plan assigned to (M_P) | 11/6/2006 | 11/6/2006 | 3/12/2007 | | PASS |
|
|
|
3/12/2007 16:19:19 M_P - activity updated through activity BLDA022 from case BLD06-03137.
|
Routing - PLAN CHECK | 3/4/2007 | | 3/12/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2007 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/12/2007 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/12/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/12/2007 | | DONE |
|
|
|
|
Routing - PLANNING | 2/28/2007 | | 3/5/2007 | | PASS |
|
|
|
Approved per CUP05-00122 and DRH05-00426
|
Routing - PLAN CHECK | 2/23/2007 | | 2/28/2007 | | |
|
|
|
Routing to Planning.
|
1st review completed | | | 2/23/2007 | | FAIL |
|
|
|
Failed planning and plan check.
|
Routing - FIRE | 2/15/2007 | | 2/23/2007 | | PASS |
|
|
|
Attached review comments to plans. Plans approved with red lined comments on plans.
|
Case Summary (BLD) | | | 2/15/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 12/7/2006 | | 2/15/2007 | | FAIL |
|
|
|
Sent correction report to the archirtect, requesting additional information to be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 1/30/2007 | | |
|
|
|
(plans were taken to Greg Johnson first by mistake and he brought them to the permit desk) received 4 copies of pages L1.0, L1.1, L1.2; taken to Mike Phillips
|
Plan resubmittals received | | | 1/30/2007 | | |
|
|
|
rec'd 1 transmittal cover sheet - memo from BRS Architects - revised cert of value - 4 sets of sheet#s SD1.1, CA-II 21, CA-II 2.2, CA-II 2.4 - taken to Mike Phillips
|
Routing - PLANNING | 11/29/2006 | | 12/7/2006 | | FAIL |
|
|
|
Cup05-00122-(12/7/06) Angela W: FAiled CUP Requires Mod to change location of approved structures / Contacted project architect.
DRH05-00426-Sarah S (12/1/06) - Failed DR. Plans do not show compliance with conditions of approval. Greg has contacted Jeff Likes. Sent on to Angela for review.
|
Routing - PLUMBING | 11/27/2006 | | 11/29/2006 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/20/2006 | | 11/27/2006 | | PASS |
|
|
|
11/27/06 Refer to ESC06-01723 as master ESC plan for project. RP must be indentified before permits are issued.adh.
|
Routing - PUBLIC WORKS | 11/15/2006 | | 11/20/2006 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 11/6/2006 | | 11/15/2006 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 11/6/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 11/6/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/6/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/6/2006 | | |
|
|
|
|
Application received | | | 10/31/2006 | | |
|
|
|
|
First Notice | | 11/8/2009 | | | |
|
|
|
|