Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/29/2008 | 8/11/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/29/2008 | | DONE |
|
|
|
|
BLD-Final | 3/25/2008 | 3/26/2008 | 3/26/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/25/2008 at 9:09:06 AM. Contact: ###-####. ok for perm occ.
|
FIRE-Conference | 2/12/2008 | 2/19/2008 | 2/21/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 2/11/2008 | 2/12/2008 | 2/12/2008 | P | FAIL |
Troy Cobbley
|
|
|
A sprinkler head is installed in the storage room in an area where no ceiling is present. Per my conversation with Zane, I will follow up next week to see if the ceiling has been completed. If it is the fire life safety can be passed.
|
FIRE-Final Inspection | 2/8/2008 | 2/11/2008 | 2/11/2008 | A | FAIL |
Troy Cobbley
|
|
|
zane was not here and nobody else knew anything about the inspection. No inspection performed. - fire life safety Phone #: ###-####
|
FIRE-Final Inspection | 1/23/2008 | 1/23/2008 | 1/23/2008 | P | FAIL |
Troy Cobbley
|
|
|
Fire sprinkler protection has to be added in the storage room or the ceiling needs to be permanantly removed as discussed. Also no approved plan/notes were on site for review.
|
BLD-Wall cover | 11/14/2007 | 11/15/2007 | 11/15/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/14/2007 at 2:34:44 PM.
|
BLD-Aging Inspection | 2/27/2007 | 2/27/2007 | 2/27/2007 | | PASS |
Mike Jordan
|
|
|
wip. Needs to pull mech permit, get finals from elec. and fire.
|
Issue PAID IN FULL permit | | | 11/28/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/21/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/21/2006 | | |
|
|
|
|
Telephone call | | | 11/21/2006 | | DONE |
|
|
|
left mess for pete rockwell at ###-#### that permit is ready
|
Plan assigned to (MLO) | 11/7/2006 | | 11/20/2006 | | PASS |
|
|
|
11/20/2006 13:36:55 MLO - activity updated through activity BLDA022 from case BLD06-03160.
|
Routing - FIRE | 11/16/2006 | | 11/20/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 11/20/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/16/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 11/8/2006 | | 11/16/2006 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/7/2006 | | 11/8/2006 | | PASS |
|
|
|
|
Pending Assignment by MYS | 11/1/2006 | | 11/7/2006 | | DONE |
|
|
|
11/7/2006 11:18:06 MYS - activity updated through activity BLDA174 from case BLD06-03160.
|
Recd Pcfee & Taken To Pln CK | | | 11/1/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/1/2006 | | |
|
|
|
|
Application received | | | 11/1/2006 | | |
|
|
|
|
Third Notice BLD | 9/22/2008 | 9/22/2008 | | | |
|
|
|
Second Notice has not been responded to.
|