PubWorks Occupancy Approval | 2/3/2010 | 2/3/2010 | 2/3/2010 | | DONE |
Tiffany Lowery
|
|
|
|
Telephone call | | | 6/26/2008 | | DONE |
Tisha Gallop
|
|
|
Called Shawn and told him need final value and will be faxing another request. He said will fax back//6/26/08 4:00pm LEG
|
Code Occupancy Approval | | | 4/3/2008 | | DONE |
|
|
|
This sign-off is for the landscaping only at this site. The landscaping was completed per the bond which was posted by contractor.
|
Letter of compliance | | | 4/3/2008 | | DONE |
|
|
|
Letter of Compliance issued 4-3-08
|
BLD-Final | 1/9/2008 | 1/10/2008 | 1/10/2008 | A | PASS |
Dave Hannah
|
|
|
nick Phone #: ###-#### ok for c.c
|
Temporary Occupancy UNPAID FEE | | | 1/10/2008 | | DONE |
|
|
|
|
BLD-Final | 1/8/2008 | 1/8/2008 | 1/8/2008 | P | NR |
Jim Sly
|
|
|
nick Phone #: ###-#### Need letter of approval from Eng. Check returns on handrails.....plus all other prev corr.
|
Code Occupancy Approval Temp | | | 1/4/2008 | | DONE |
|
|
|
Bond for the remaining landscape has been posted. Re-inspection for the FINAL will occur when the owner calls for a time and date.
|
FIRE-Final Inspection | 1/2/2008 | 1/3/2008 | 1/3/2008 | A | PASS |
Forrest France
|
|
|
Correction notice items are finished, sprinkler supervisory signals cleared by contractor, fire life safety inspection passed.
|
FIRE-Final Inspection | 12/26/2007 | 12/27/2007 | 12/27/2007 | A | FAIL |
Forrest France
|
|
|
Need to repair EM lights at four locations including the exit discharges, provide signage at the door to the FACP room, one missing PFE provided while on site, need to final project related fire alarm permit and recieve copies of NFPA 72 record of completion.
|
BLD-Final | 12/12/2007 | 12/12/2007 | 12/13/2007 | P | FAIL |
Dave Hannah
|
|
|
nick Phone #: ###-#### c/n on site
|
BLD-Conference | 9/11/2007 | 9/11/2007 | 9/12/2007 | P | PASS |
Dave Hannah
|
|
|
nick Phone #: ###-####
|
BLD-Other | 9/5/2007 | 9/5/2007 | 9/5/2007 | P | PASS |
Dave Hannah
|
|
|
hand rail; Nick; Phone #: ###-#### Internet Inspection Request from: Hattie James
|
BLD-Framing/Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | PART |
Dave Hannah
|
|
|
ceiling t-bar; Nick; Phone #: ###-#### Internet Inspection Request from: Hattie James hallways and top of stairs ok to cover
|
BLD-Other | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | PART |
Dave Hannah
|
|
|
nick - ceiling; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ceiling west stair tower ok to cover
|
BLD-Other | 5/17/2007 | 5/17/2007 | 5/17/2007 | P | PASS |
Dave Hannah
|
|
|
nick - caulking behind walls ; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 5/2/2007 | 5/2/2007 | 5/2/2007 | P | PART |
Dave Hannah
|
|
|
Nick; Phone #: ###-#### Internet Inspection Request from: Andrea Whitema ok to cover entryway and rest room on 1st and 2nd floors shaft openning also ok
|
BLD-Framing/Rough-in | 4/24/2007 | 4/25/2007 | 4/25/2007 | A | PART |
Dave Hannah
|
|
|
Nick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall core areas ok to cover walked project with nick
|
BLD-Footing | 2/8/2007 | 2/9/2007 | 2/9/2007 | A | PART |
Dave Hannah
|
|
|
nick ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith rebar for stair tower ftgs
|
Issue PAID IN FULL permit | | | 1/25/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2007 | | DONE |
|
|
|
spoke with someone from Russell Corp. about what fees ($18,971.81) are due and need ACHD
|
Permit Ready to Issue | | | 1/22/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/18/2007 | | 1/19/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/19/2007 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 11/6/2006 | | 1/19/2007 | | PASS |
|
|
|
1/19/2007 07:06:56 RMH - activity updated through activity BLDA022 from case BLD06-03180.
|
Routing - FIRE | 1/17/2007 | | 1/18/2007 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLAN CHECK | 12/21/2006 | | 1/17/2007 | | PEND |
|
|
|
No corrections required by building department, routed plans to fire 12-17-07
|
Plan resubmittals received | | | 1/16/2007 | | |
|
|
|
Received 1pg. response letter, and two copies of the following pages: A2.3, A3.0, A3.1, A5.0, A5.1, A6.0, A9.0, A9.1, A9.2 ; taken to Ron Hill
|
Plan resubmittals received | | | 1/16/2007 | | |
|
|
|
Rec'd 2 copies of sheet # A6.0, A2.3 - taken to Ron Hill
|
Meeting | | | 1/3/2007 | | |
|
|
|
Met with Cory Nelson discussed stair enclosure issue, Cory stated that they were going to reconfigure stair to add landing and keep within enclosure, this will require structural and architectual resubmittals.
|
Plan resubmittals received | | | 12/28/2006 | | |
|
|
|
received transmittal letter to Ron Hill, 2pg. Plan Review Response, 2 copies of the following pages: A1.0, A2.0, A2.1, A2.2, A2.3, A2.4, A2.5, A5.0, A6.0, A7.0, A7.1, A9.0, A9.1; transmittal letter to Scott Arellano, 1pg. Plan Reveiw Response, 2 copies of the following pages: A2.1, A2.2, A2.3; taken to Ron Hill
|
1st review completed | | | 12/21/2006 | | FAIL |
|
|
|
|
Routing - FIRE | 12/18/2006 | | 12/21/2006 | | FAIL |
|
|
|
Faxed review comments to plans. Attached review comments to plans.
|
Routing - PLAN CHECK | 11/16/2006 | | 12/18/2006 | | FAIL |
|
|
|
faxed and mailed requirements to the architect, routed plans to fire for review, 12/18/06
|
Plan resubmittals received | | | 12/13/2006 | | |
|
|
|
received letter of transmittal, 1pg. letter of response, and 2 copies of the following pages: S0.2, S1.1, S2.1; taken to Ron Hill
|
Routing - PLUMBING | 11/14/2006 | | 11/16/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 11/9/2006 | | 11/14/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 11/8/2006 | | 11/8/2006 | | PASS |
|
|
|
Cody Riddle (greenbelt setback verification)-No work proposed, or allowed within the greenbelt setback. CER
Approved per DRH06-00334 11-8-06 Andrea Tuning
|
Routing - PUBLIC WORKS | 11/6/2006 | | 11/8/2006 | | PASS |
|
|
|
|
Pending Assignment by MYS | 11/3/2006 | | 11/6/2006 | | DONE |
|
|
|
11/6/2006 14:18:43 B_S - activity updated through activity BLDA175 from case BLD06-03180.
|
Routing Off Site - STRUCTURAL | 11/6/2006 | | 11/6/2006 | | PASS |
|
|
|
Called Action Courier for pick up @ 1:15pm on 11/6/06 BAS
|
Plans ACCEPTED BY PLAN TECH | | | 11/6/2006 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/6/2006 | | DONE |
|
|
|
|
Application received | | | 11/3/2006 | | |
|
|
|
|