Permit Information
Permit NumberBLD06-03212
StatusFinaled
Name STEVEN-HENAGER COLLEGE
Site Address 1444 S ENTERTAINMENT AVE Unit: 200
Project NameANTHEM OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
(STEVENS HENAGER COLLEGE - ANTHEM OFFICE BLDG - 2ND FLR) To finish a 13,975 square foot, full floor tenant space for use as a vocational school per approved plans and CUP05-00093 & DRH05-00287. The full floor area is 15,280 square feet. The core areas of this floor were finished under the shell and core permit (BLD06-01621). This tenant space will include administrative offices, two small conference rooms, classrooms, two medical labs, a student lounge, a study area, library/reading area and multi-purpose assembly area. All construction per the approved plans and attached comment list.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD10/30/200710/30/200712/27/2007 DONE
Second Notice has not been responded to.
(F) Reprint permit  11/26/2007 DONE
Second Notice BLD10/17/200710/17/200710/30/2007 DONE
First Notice has not been responded to.
First Notice 9/27/200710/17/2007 DONE
FIRE-Final Inspection9/27/20079/27/20079/27/2007 CANC
DetailsTroy Cobbley
Life safety passed
BLD-Final9/27/20079/27/20079/27/2007PPASS
DetailsMike Jordan
Was looked at yesterday Phone #: ###-#### Internet Inspection Request from: Duane Seid. ok for perm occ.
Permanent Occupancy  9/27/2007 DONE
BLD-Final9/4/20079/4/20079/4/2007PNR
DetailsMike Jordan
Phone #: ###-#### Internet Inspection Request from: Duane Seid
BLD-Final7/26/20077/26/20077/26/2007PPART
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Duane Seidtemp ok
FIRE-Final Inspection7/26/20077/26/20077/26/2007PPART
DetailsTroy Cobbley
A temporay occupancy was given until the east elevator has been inspected and approved. Until then the east elevator is to remain locked out and is not to be used. The west elevator is approved for use. Also one additional emergency light is required in the exit lobby of the first floor south exit. Temporary signage in the stair towers has been provided until the permanant signs have been made. The non approved hardware on the second floor pocket door has been removed. The three fire hydrants have been tested for flow.
BLD-Other6/28/20076/28/20076/28/2007PPASS
DetailsMike Jordan
dwayne - grid ceiling; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang. grid ok.
BLD-Wall cover6/25/20076/25/20076/25/2007PPART
DetailsJim Sly
Instpect ceiling grid and above ceiling rough-ins. Phone #: ###-#### Internet Inspection Request from: Duane Seid
Select grid ceilings....2nd floor....OK. Entry...hard lid frame...OK
BLD-Wall cover5/30/20075/30/20075/30/2007APASS
DetailsMike Jordan
I am ready for cover in the remainder of the TI on the second floor. Phone #: ###-#### Internet Inspection Request from: Duane Seid. grid in ada restroom.
BLD-Energy code compliance5/21/20075/21/20075/21/2007PPASS
DetailsMike Jordan
Perimeter walls are insulated and ready for inspection Phone #: ###-#### Internet Inspection Request from: Duane Seid. Should be shell and core energy.
BLD-Framing/Rough-in5/11/20075/11/20075/11/2007PPASS
DetailsMike Jordan
I am ready for inspection for cover on the second floor tennant space. Phone #: ###-#### Internet Inspection Request from: Duane Seid Interior framing 2nd floor. pending plumbing.
BLD-Aging Inspection4/25/20074/25/20074/25/2007 PASS
DetailsMike Jordan
wip on shell and core.
Issue PAID IN FULL permit  1/24/2007  
Print Occupancy Form  1/17/2007 DONE
Telephone call  1/17/2007 DONE
tlk to bryce Jones ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  1/17/2007 DONE
Plan assigned to (JCM)11/9/2006 1/16/2007 PASS
1/16/2007 11:36:20 JCM - activity updated through activity BLDA022 from case BLD06-03212.
Routing - FIRE1/11/2007 1/16/2007 PASS
Attached updated review comments to plans.
Routing - PLAN CHECK1/16/2007 1/16/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/16/2007 DONE
Routing - PLAN CHECK11/27/2006 1/11/2007 PASS
Plan Reviewer's activity  1/11/2007 PASS
Review and approved resubmitted construction documents. JCM
Plan resubmittals received  1/9/2007  
received transmittal from mhtn arch totaling (34) pages. also "2" sets of plans including each sheet of EL102, AC102, AE001, AE102, & AE409/ plans taken to john menard
1st review completed  11/27/2006 FAIL
Failed plan check and fire.
Routing - FIRE11/22/2006 11/27/2006 FAIL
Faxed resubmittal item to architect. Attached review comments to plans.
Plan resubmittals requested  11/22/2006 DONE
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK11/16/2006 11/21/2006 FAIL
Routing - PLUMBING11/13/2006 11/16/2006 PASS
additional cross connection protection may be required at the lab sinks.
Routing - PLANNING11/9/2006 11/16/2006 PASS
Susan Riggs for Carl Miller CUP05-00093 Pending DR approval
plans for 2nd story tennant improvement

Sarah Schafer DRH05-00287 - Approved per the DR.
Routing - PUBLIC WORKS11/9/2006 11/9/2006 PASS
Plans ACCEPTED BY PLAN TECH  11/9/2006  
Application received  11/7/2006  
Recd Pcfee & Taken To Pln CK  11/7/2006 DONE
Routing - PLANNING1/16/2007 1/17/2006 PASS
Routed to Sarah S. to verify if approved. JCM

Approved per DRH05-00287.