Permit Information
Permit NumberBLD06-03220
StatusFinaled
Name EKC INC
Site Address 8001 W FRANKLIN RD
Project NameFRANKLIN TOWNE PLAZA
Customer Number 
ePlanReviewNo
Description
(EKC RCE-6142) (FRANKLIN TOWNE PLAZA - CANOPY FACELIFT - EAST END) To remodel the exterior canopy on the north, west and south sides of 8001, 8017, 8033 & 8079 W. Franklin Road per approved plans, attached engineering and DRH06-00328. The canopy remodel on the west end of the building performed under BLD06-00632. Work to include new overbuild roofs and installation of new roofing, installation of EFIS system, new accessible curb ramps, new brick veener, miscellaneous related exterior finishes. This building is fully fire sprinklered any modifications or alterations to the sprinkler system shall be maintained per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD8/8/20078/8/200710/2/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD7/27/20077/27/20078/8/2007 DONE
First Notice has not been responded to.
First Notice7/13/20077/13/20077/27/2007 DONE
DetailsMike Jordan
BLD-Final7/13/20077/13/20077/13/2007PPASS
DetailsMike Jordan
dale Phone #: ###-####. Letter of Compliance issued.
DOC - Permit Finaled7/13/20077/13/20077/13/2007PPASS
DetailsMike Jordan
BLD-Final6/19/20076/20/20076/26/2007ANR
DetailsJim Sly
dale; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
Talked to Contr...Still need letter from MTI
Code Occupancy Approval6/13/20076/13/20076/13/2007APASS
DetailsScott M.Brown
OK PER DRH06-00378
BLD-Framing/Rough-in5/22/20075/22/20075/22/2007PPASS
DetailsMike Jordan
dale ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in4/4/20074/5/20074/5/2007APASS
DetailsMike Jordan
dale; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in3/26/20073/27/20073/27/2007ACANC
DetailsMike Jordan
Dale; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
BLD-Framing/Rough-in3/16/20073/19/20073/19/2007APASS
DetailsMike Jordan
Dale late morning if possible; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
BLD-Framing/Rough-in3/13/20073/14/20073/14/2007APASS
DetailsMike Jordan
dale - partial framing; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Verified anchor bolt install and box headers prior to cover.
BLD-Framing/Rough-in3/8/20073/9/20073/9/2007APASS
DetailsMike Jordan
Dale; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Remaining two tie backs ok.
BLD-Framing/Rough-in3/8/20073/8/20073/8/2007PPART
DetailsMike Jordan
Dale, partial framing right now; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Visually inspected dragstruts on existing roof.
BLD-Foundation2/8/20072/9/20072/9/2007PPASS
DetailsMike Jordan
BILL - 2PM IF POSS; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. column pad footing extensions, west half, phase 1.
BLD-Footing2/7/20072/8/20072/8/2007PPASS
DetailsMike Jordan
dale; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Footings for new canopies, east half of phase 1.
Issue PAID IN FULL permit  1/19/2007 DONE
Telephone call  1/5/2007 DONE
tlk to kyle hamilton ###-#### that permit and fees are ready to be picked up but needs RP/RCE #
Permit Ready to Issue  1/5/2007 DONE
Inspection Record Card- Bld  1/4/2007 DONE
Routing - PLAN CHECK12/22/2006 1/2/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/2/2007 DONE
Plan assigned to (R_H)11/15/2006 1/2/2007 PASS
1/2/2007 08:20:28 RMH - activity updated through activity BLDA022 from case BLD06-03220.
1st review completed  12/22/2006 FAIL
Routing - FIRE12/18/2006 12/22/2006 PASS
Attached review comments to plans.
Plan resubmittals received  12/20/2006  
Received transmittal letter from BRS Architects, transmittal letter from Stapley Engineering, 1pg. response letter from Stapley Eng., 5pg. Project Start Up for Special Inspections form, and 3 copies of page S1.1; taken to Ron Hill
Case Summary (BLD)  12/18/2006 DONE
Routing Off Site - STRUCTURAL11/16/2006 12/18/2006 FAIL
Sent to outside engineer.///Called Action Courier for Pick up @ 8:20am on 11/16/06 BAS
Routing - PLAN CHECK11/20/2006 12/18/2006 FAIL
Failed structural plan review, Faxed and mailed copy to architect, routed plans to fire for review, Will not have to go back out to structural for rereview, In house only.
Routing - PLANNING11/20/2006 11/20/2006 PASS
Approved per DRH06-00328
Routing - Erosion and Sediment11/17/2006 11/20/2006 PASS
ESC waiver request approved with attached conditions.
Routing - PUBLIC WORKS11/15/2006 11/17/2006 PASS
Pending Assignment by MYS11/13/2006 11/15/2006 DONE
11/15/2006 15:45:42 MYS - activity updated through activity BLDA175 from case BLD06-03220.
Plans ACCEPTED BY PLAN TECH  11/13/2006  
Application received  11/9/2006  
Recd Pcfee & Taken To Pln CK  11/9/2006