Second Notice BLD | 9/22/2008 | 9/22/2008 | 12/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/13/2008 | 9/22/2008 | | DONE |
|
|
|
|
BLD-Final | 8/13/2008 | 8/13/2008 | 8/13/2008 | P | PASS |
Jim Sly
|
|
|
David Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 8/13/2008 | | |
|
|
|
|
BLD-Final | 7/25/2008 | 7/25/2008 | 7/25/2008 | A | PART |
Jim Sly
|
|
|
OK for Temp Occ. Need Letter from special insp agency and Engineer of record.
|
Temporary Occupancy | 7/25/2008 | 10/23/2008 | 7/25/2008 | | DONE |
Tisha Gallop
|
|
|
Building inspector needs letter from the engineer and Strata prior to perm occupancy
|
BLD-Final | 7/21/2008 | 7/21/2008 | 7/14/2008 | A | DONE |
Lori Flook
|
|
|
inspected per SLandaluce 7/14/08.
|
BLD-Framing/Rough-in | 7/9/2008 | 7/10/2008 | 7/10/2008 | P | DONE |
Jim Sly
|
|
|
David Phone #: ###-####
|
Code Occupancy Approval | 7/9/2008 | 7/9/2008 | 7/9/2008 | P | PASS |
Carol Montgomery
|
|
|
Insp. @ 2:00-2:15; Phone #: ###-####
Meets compliance with CUP. Signed Occupancy card FINAL
|
FIRE-Final Inspection | 7/3/2008 | 7/7/2008 | 7/7/2008 | A | PASS |
Troy Cobbley
|
|
|
Life safety completed per notes of last inspection.KR
|
FIRE-Final Inspection | 6/26/2008 | 6/27/2008 | 6/27/2008 | A | FAIL |
Forrest France
|
|
|
All testing completed. Could not pass until kitchen hood system permit is finaled. KR
|
BLD-Final | 4/10/2008 | 4/11/2008 | 4/11/2008 | A | NR |
Jim Sly
|
|
|
Reviewed Requirements to obtain final.
|
BLD-Other | 3/27/2008 | 3/27/2008 | 3/27/2008 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/27/2008 at 9:09:08 AM. OK'd 1hr Celing in Mechanical room.....in leiu of walls continuing up to roof deck. Rm at North side of bldg
|
BLD-Conference | 3/20/2008 | 3/21/2008 | 3/21/2008 | P | NR |
Jim Sly
|
|
|
Ceiling grid.....Need Fire approval Need 1 slack wire on all appliances...ie HVAC diffusers.
|
BLD-Other | 3/20/2008 | 3/20/2008 | 3/20/2008 | P | CANC |
Jim Sly
|
|
|
nacho - ceiling grid Phone #: ###-#### Need fire sprinkler approval
|
BLD-Conference | 3/19/2008 | 3/19/2008 | 3/19/2008 | P | DONE |
Jim Sly
|
|
|
Nacho Phone #: ###-#### Walk thru with Nacho.......checked wood trusses.....OK Metal Trusses in Gym questioned ........Capable of carrying extra load from basketball standards....OK'd. Looked at insulation and scrim covering....will come back later to take a better look.
|
Telephone call | | | 2/28/2008 | | DONE |
|
|
|
I called Justin Schwartz ###-####, inquiring on the status of the eave sprinkler Modification request we discussed last week; Per Mark Senteno, the FD hasn't received a letter from him. Not available, left voice message to call me.
|
Telephone call | | | 2/20/2008 | | DONE |
|
|
|
Telcon from Justin Schwartz, Hummel Arch's regarding the eave soffits which have a clear space between the top and botton chord of 7" (just over 1" greater than the code exception for sprinkler protection o fless than 6"). I suggested he could write Dave Hanneman, requesting special design approval based on several factors of the situation, and see if those factors might be considered sufficient for equivalency of intent and protection of occupants and fire fighters. If this is not approved, an alternative would be to add a nominal 2"x2" to the top or botton chord to reduce the space to less than 6".
|
BLD-Conference | 2/14/2008 | 2/14/2008 | 2/14/2008 | P | DONE |
Troy Cobbley
|
|
|
I did a quick walk through while waiting for the sprinkler underground flush and found the t-bar is being installed as well as some ceiling tiles/lights. I notified the project superintendant that no ceiling are to be installed or sprinkler piping to be covered since the sprinkler system has not been inspected yet. Jim Sly the structural inspector has also been notified.
|
Third Notice BLD | 12/22/2008 | 12/22/2008 | 2/13/2008 | | DEFR |
Rita DeYoung
|
|
|
Second Notice has not been responded to. Brandon called to say he should have his paper work done in March.
|
BLD-Framing/Rough-in | 12/3/2007 | 12/4/2007 | 12/4/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/3/2007 at 3:23:59 PM. Contact: ###-####. interior classroom walls...... and select walls ok.
|
BLD-Framing/Rough-in | 10/22/2007 | 10/23/2007 | 10/23/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/22/2007 at 5:14:34 PM. Contact: ###-####. Nailing for roof diaphragm, low roofs only.
|
BLD-Foundation | 6/26/2007 | 6/26/2007 | 6/26/2007 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/26/2007 at 7:30:13 AM. Contact: ###-####. OK pending STRATA SPECIAL INSP, TESTS and approvals
|
BLD-Foundation | 6/22/2007 | 6/22/2007 | 6/22/2007 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/22/2007 at 7:28:45 AM. In/terior footings............STRATA
|
BLD-Foundation | 6/18/2007 | 6/20/2007 | 6/20/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/18/2007 at 11:33:50 AM. Contact: ###-####. Interior footings...........OK pending STRATA insp, tests, and approvals.
|
BLD-Foundation | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/31/2007 at 12:26:41 PM. Contact: ###-####. OK pend STRATA insp and appr.
|
BLD-Foundation | 5/29/2007 | 5/30/2007 | 5/30/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/29/2007 at 12:54:18 PM. OK pend STRATA insp and appr.
|
BLD-Foundation | 5/17/2007 | 5/21/2007 | 5/21/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/17/2007 at 1:35:44 PM. Contact: ###-####. OK pending STRATA insp, tests, and approvals
|
BLD-Foundation | 5/15/2007 | 5/18/2007 | 5/18/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/15/2007 at 1:06:41 PM. Contact: ###-####. Footings at South East area....section C OK pending STRATA special insp, tests, and approvals.
|
BLD-Foundation | 5/15/2007 | 5/17/2007 | 5/17/2007 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/15/2007 at 1:05:56 PM. Contact: ###-####. ok pending S. I. report
|
BLD-Foundation | 5/15/2007 | 5/16/2007 | 5/16/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/15/2007 at 1:05:14 PM. Contact: ###-####. Footings ... South wall OK pending STRATA special inspection, tests, and approvals.
|
(F) Reprint permit | | | 4/13/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/12/2007 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 11/20/2006 | | 3/29/2007 | | PASS |
|
|
|
3/29/2007 11:37:18 MLO - activity updated through activity BLDA022 from case BLD06-03277.
|
Routing - PLAN CHECK | 3/29/2007 | | 3/29/2007 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/20/2007 | | 3/29/2007 | | PASS |
|
|
|
Called Action Courier for pick up on 3/20/07 @ 9:50am///BAS Called Jan Welch and got verbal approval over phone. MLO
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/29/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2007 | | DONE |
|
|
|
t/c w margie kennedy at ###-#### - permit ready and fees given - also need ACHD - margie said that since it is a school they do not have to pay the fees - she will bring something in writing to that effect - faxed her a copy of the fees to show the school dist.
|
Permit Ready to Issue | | | 3/29/2007 | | |
|
|
|
|
Plan resubmittals received | | | 3/15/2007 | | |
|
|
|
Received transmittal letter, 3 copies of Structural Calculations, and 3 copies of page S1.02A; taken to Mike Otto
|
Plan resubmittals received | | | 3/14/2007 | | FAIL |
|
|
|
received copy of fax sent to our engineer which includes corrected plan sheet. Sent email to architect telling them to provide not less than two full size plan sheets stamped and signed by the engineer.
|
Routing Off Site - STRUCTURAL | 3/5/2007 | | 3/13/2007 | | FAIL |
|
|
|
Called Action Courier for pick up @ 12:10pm BAS Engineer has been in direct contact with design engineer about corrections.
|
Plan resubmittals received | | | 3/2/2007 | | DONE |
|
|
|
Received 1 transmittal letter, 3 structural calcs and 3 copys of sheets S1.02A,S1.02B,S5.02,S6.01,S6.02,S6.03,S6.04 taken to Mike Otto
|
Routing - PUBLIC WORKS | 2/21/2007 | | 2/22/2007 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/15/2007 | | DONE |
|
|
|
structural corrections
|
Routing Off Site - STRUCTURAL | 1/30/2007 | | 2/15/2007 | | FAIL |
|
|
|
called action couriers for pick up 1-30-07 corrections sent to architect
|
Routing - PUBLIC WORKS | 2/7/2007 | | 2/8/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/5/2007 | | 2/6/2007 | | PEND |
|
|
|
pending structural approval
|
Plan resubmittals received | | | 2/2/2007 | | |
|
|
|
rec'd transmittal letter, door hardware packet - 3 sets of sheet #A2.07 - taken to Mike Otto
|
Routing - PUBLIC WORKS | 1/31/2007 | | 2/1/2007 | | FAIL |
|
|
|
Bad location for trash. No way for truck to exit without backing out blindly. Contact Pam Williams ###-####
|
Routing - PLAN CHECK | 2/1/2007 | | 2/1/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 1/23/2007 | | 1/30/2007 | | FAIL |
|
|
|
need revised sheet A2.07, fire protection exterior struc members and panic hardware door 208. Called architect went over corrections.
|
Plan resubmittals requested | | | 1/30/2007 | | DONE |
|
|
|
IBC corrections
|
Plan resubmittals received | | | 1/22/2007 | | DONE |
|
|
|
rec'd 1 transmittal cover, 1 2pg response letter, 2 copies of plan review comments from Lochsa Engineering, 2 copies of sheet #s A0.10, A2.02, A2.03, A2.04, A2.21, A5.00, A5.01, A5.02, A5.03, A5.04, A5.05, A5.06, A5.07, A5.09, A5.10, A5.11; 2 copies of sheet #s S0.1, S1.01, S1.01A, S1.01B, S1.01C, S1.02, S1.02A, S1.02B, S1.02C, S1.03, S1.03A, S1.03B, S1.03C, S2.01, S2.02, S3.01, S3.02, S3.03, S4.01, S5.01, S5.02, S6.01, S6.02, S6.03, S6.04, S7.01 - taken to Mike Otto
|
Routing - FIRE | 12/15/2006 | | 12/20/2006 | | PASS |
|
|
|
Attached fire review comments to plans.
|
1st review completed | | | 12/20/2006 | | FAIL |
|
|
|
Failed structural and plan check.
|
Routing - PLAN CHECK | 12/20/2006 | | 12/20/2006 | | |
|
|
|
|
Plan resubmittals requested | | | 12/15/2006 | | DONE |
|
|
|
IBC corrections
|
Routing - PLAN CHECK | 12/11/2006 | | 12/15/2006 | | FAIL |
|
|
|
corrections sent to architect
|
Routing Off Site - STRUCTURAL | 11/20/2006 | | 12/11/2006 | | FAIL |
|
|
|
Called Action Courier for pick up @ 11:52am///11/20/06 BAS corrections sent to architect. MLO
|
Routing - PLANNING | 12/5/2006 | | 12/8/2006 | | PASS |
|
|
|
CUP06-00071--Susan Riggs
|
Routing - PLUMBING | 11/29/2006 | | 12/5/2006 | | PASS |
|
|
|
min. 2" waste piping below slab. details on page P1.4 show 2" waste to the toilets, 3" min. P-5 is a janitor sink, 3" waste detail shows 1 1/2". all fixtures used for food prep or utensil washing must be indirectly wasted, sink in snack room 207 needs to be wasted into a floor sink. use boise city approved grease interceptor detail, atrtached.
|
Routing - Erosion and Sediment | 11/28/2006 | | 11/29/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 11/22/2006 | | 11/28/2006 | | FAIL |
|
|
|
Street lighting plan required for entrances on Northview St. Contact Hank A. at ###-####
|
Routing - PLANNING Land Div | 11/20/2006 | | 11/22/2006 | | PASS |
|
|
|
Approved, parcel is over 5 acres in size.
|
Plans ACCEPTED BY PLAN TECH | | | 11/20/2006 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 11/20/2006 | | |
|
|
|
|
Pending Assignment by MYS | 11/17/2006 | | 11/20/2006 | | DONE |
|
|
|
11/20/2006 11:23:47 JCM - activity updated through activity BLDA174 from case BLD06-03277.
|
Recd Pcfee & Taken To Pln CK | | | 11/17/2006 | | |
|
|
|
|
Application received | | | 11/17/2006 | | |
|
|
|
|