Third Notice BLD | 12/11/2007 | 12/11/2007 | 12/28/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 11/13/2007 | 11/13/2007 | 12/11/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
Routing Off Site - STRUCTURAL | 11/27/2006 | | 12/7/2007 | | PASS |
|
|
|
|
First Notice | | 11/1/2007 | 11/13/2007 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 11/1/2007 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/30/2007 | 10/31/2007 | 10/31/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Code Occupancy Approval | 6/15/2007 | 6/15/2007 | 6/15/2007 | A | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL AND RELEASE OF BOND
|
Temporary occupancy | | | 5/11/2007 | | DONE |
|
|
|
Temp. Occ. Cert. # 5583 issued 5-11-07 to the Cafe Ole (patio enclosures addition)
|
FIRE-Final Inspection | 5/3/2007 | 5/4/2007 | 5/4/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given by dave hanniman for the new areas to be occupied while the fire alarm and fire sprinkler systems are finished being installed. Life safety can be passed when these permits are finaled
|
BLD-Final | 5/3/2007 | 5/4/2007 | 5/4/2007 | P | PASS |
Mike Jordan
|
|
|
bill ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Temp occ. granted. Will be ok for perm occ once others go perm.
|
BLD-Conference | 5/3/2007 | 5/3/2007 | 5/3/2007 | P | CANC |
Mike Jordan
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Code Occupancy Approval Temp | 5/3/2007 | 5/4/2007 | 5/3/2007 | A | DONE |
Scott M.Brown
|
|
|
NEEDS TO BOND FOR COLOR AND SOME LANDSCAPE BOND AMOUNT IS $13,956
|
BLD-Energy code compliance | 5/2/2007 | 5/3/2007 | 5/3/2007 | A | DONE |
Mike Jordan
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Andrea Whiteman. Not energy insp. Did prelim. walk thru with contractor.
|
FIRE-Final Inspection | 5/1/2007 | 5/2/2007 | 5/2/2007 | P | FAIL |
Troy Cobbley
|
|
|
Remove the deadbolts from the doors as discussed, provide occupant load signs and repair all new and existing exit/emergency lights. When this is done a temporary occupancy can be given.
|
FIRE-Conference | 4/25/2007 | 4/26/2007 | 4/26/2007 | A | PASS |
Troy Cobbley
|
|
|
I went over life safety requirements with the general contractor
|
Telephone call | | | 3/29/2007 | | DONE |
|
|
|
telcon form Rany Hemmer, re. req'ts for HVAC smoke det's. He wasn't familiar with the actual design or the IMC requirements; I explained general req'ts and reco'd he discuss with the Mech Designer.
|
BLD-Wall cover | 3/23/2007 | 3/26/2007 | 3/26/2007 | A | PASS |
Mike Jordan
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. interior non bearing wall for womans restroom.
|
BLD-Wall cover | 3/22/2007 | 3/23/2007 | 3/23/2007 | P | CANC |
Mike Jordan
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Stacie Backus Inspection cancelled from web by: Victoria Beall
|
BLD-Framing/Rough-in | 3/20/2007 | 3/21/2007 | 3/21/2007 | A | PASS |
Mike Jordan
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Reviewed RFI from engineer and inspected interior shear walls. All additional straps, holdowns, and 2x6 framing was insatalled per rfi. ok to cover.
|
BLD-Framing/Rough-in | 3/13/2007 | 3/13/2007 | 3/13/2007 | P | PASS |
Mike Jordan
|
|
|
bill - pls call 30 min prior to inspection; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. All framing issues have been resolved.
|
BLD-Energy code compliance | 3/13/2007 | 3/13/2007 | 3/13/2007 | P | PASS |
Mike Jordan
|
|
|
bill - pls call 30 min prior to inspection; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 3/8/2007 | 3/9/2007 | 3/9/2007 | A | PASS |
Mike Jordan
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. shear nailing and framing ok. ok to insul. had contractor add straps to beams, add additional studs under beams. Needs to get rfi from engineer nfor change of cricket details.
|
BLD-Wall cover | 2/28/2007 | 2/28/2007 | 2/28/2007 | P | PASS |
Mike Jordan
|
|
|
Bill, wall cover in bathrooms, please call 1st so he can meet you there; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Framing/Rough-in | 2/9/2007 | 2/9/2007 | 2/9/2007 | P | PART |
Dave Hannah
|
|
|
Bill Please call first ; Phone #: ###-#### Internet Inspection Request from: Darla Downs mens rest rooms ok to cover
|
Issue PAID IN FULL permit | | | 1/18/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/17/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/17/2007 | | DONE |
|
|
|
|
Telephone call | | | 1/17/2007 | | DONE |
|
|
|
tlk to kyle f ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 1/17/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/11/2007 | | 1/16/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/16/2007 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 11/24/2006 | | 1/16/2007 | | PASS |
|
|
|
1/16/2007 13:45:11 RMH - activity updated through activity BLDA022 from case BLD06-03284.
|
Routing - FIRE | 1/10/2007 | | 1/11/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 1/11/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/5/2006 | | 1/10/2007 | | PEND |
|
|
|
No corrections required by builidng plan review, routed plans to fire 1/10/07 permit pending fire departments review.
|
Routing - PLANNING | 12/4/2006 | | 12/5/2006 | | PASS |
|
|
|
Approved per DRH06-00126
|
Routing - PLUMBING | 11/28/2006 | | 12/4/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 11/24/2006 | | 11/28/2006 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 11/28/2006 | | 11/28/2006 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Recd Pcfee & Taken To Pln CK | | | 11/22/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/22/2006 | | |
|
|
|
|
Application received | | | 11/17/2006 | | |
|
|
|
|