Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD06-03407
StatusFinaled
Name B & B STEEL ERECTORS
Site Address 2190 S CENTURION PL
Project NameB AND B STEEL ERECTORS
Customer Number 
ePlanReviewNo
Description
(B & B Steel Erectors RCE-1589) - B & B Steel Erectors Office/Warehouse (Shell Only) - To construct a new 9,500 square foot, one story, concrete tilt-up and metal frame office and warehouse shell building and related site improvement. This is a shell permit only, separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. The B & B office and warehouse tenant improvement permit is BLD07-00003 and future tenant vanilla finish permit is BLD07-00004. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval12/23/200912/23/200912/23/2009 DONE
DetailsTiffany Lowery
FINAL INSPECTION COMPLETED FOR PERMANENT OCCUPANCY 02/11/09 ROCKY ROKOVITZ
Second Notice BLD3/4/20093/4/20097/31/2009 DONE
DetailsTisha Gallop
First Notice has not been responded to.
Zoning Approval3/12/20093/12/20093/12/2009 DONE
DetailsAndrea Tuning
The applicant obtained DR Committee approval to maintain the existing landscaping. Final occupancy is now granted and the bond will be released.
ANT
First Notice2/13/20092/13/20093/4/2009 DONE
DetailsTom Arcoraci
BLD-Final2/12/20092/13/20092/13/2009PPASS
DetailsTom Arcoraci
todd Phone #: ###-####
DOC - Permit Finaled2/13/20092/13/20092/13/2009PPASS
DetailsTom Arcoraci
FIRE-Final Inspection2/13/20092/13/20092/13/2009PPASS
DetailsTroy Cobbley
Life safety passed. The new fire hydrant has been installed to the west of the building rather than on the south east corner. This location has been approved by Mark Senteno with an on site visit. The fire hydrant was not installed as approved due to underground utilities.
FIRE-Final Inspection2/12/20092/13/20092/13/2009APASS
DetailsTroy Cobbley
Life safety passed. The new fire hydrant has been installed to the west of the building rather than on the south east corner. This location has been approved by Mark Senteno with an on site visit. The fire hydrant was not installed as approved due to underground utilities.
BLD-Final2/6/20092/9/20092/10/2009ANR
DetailsTom Arcoraci
Todd Phone #: ###-####
FIRE-Final Inspection2/6/20092/9/20092/9/2009AFAIL
DetailsTroy Cobbley
Provide missing fire hydrant per review note #1. Provide non-hardened locks per review note #4. Provide fire dept. signage per revierw note #5. Provide address on both sides of the building as discussed with a minumum of 4" contrasting color numbers. Provide suite numbers. Mount the fire extinguishers. Provide additional fire extinguisher for the vanilla finish tenant space. Repair and retest the exit discharge lights out of the warehouse area. Provide door to remain unlocked sticker at both of the keyed exits.
Zoning Approval Temp2/5/20092/5/20092/5/2009 DONE
DetailsAndrea Tuning
The applicant has posted a bond for the landscaping and has submitted a Committee Level DR application requesting that the existing landscaping be able to remain. The applicant is being granted a 90 day temporary occupancy.
BLD-Aging Inspection12/15/200812/15/200812/16/2008 NR
DetailsTom Arcoraci
BLD-Other10/13/200810/14/200810/16/2008ADONE
DetailsJim Sly
Please check this project out. I think it needs to be expired.
Talked to Todd ###-####.....Said that he will work on finals....approx 1mo out......
BLD-Conference7/22/20087/22/20087/22/2008PPASS
DetailsTom Arcoraci
BLD-Aging Inspection6/11/20086/11/20086/11/2008 DEFR
DetailsTom Arcoraci
Extend Permit 180 days 2/8/20082/8/2008 DONE
CHANGE STATUS TO (ISS)  2/8/2008 DONE
Per Tom A. chng. status to Issue becuase electrical permit was pulled so wip; and will give 6 more months to call for inspection
Expired/Cancelled1/28/20081/28/20081/28/2008APASS
DetailsTom Arcoraci
This is the one we spoke about the Louise with Public works was questioning........she can be reached at ###-#### Thanks Tom
Expired/Cancelled1/28/20081/28/20081/28/2008PPASS
DetailsTom Arcoraci
This is the one we spoke about the Louise with Public works was questioning........she can be reached at ###-#### Thanks Tom
BLD-Aging Inspection1/15/20081/15/20081/15/2008 CANC
DetailsTom Arcoraci
exp
BLD-Aging Inspection11/12/200711/12/200711/13/2007 CANC
DetailsTom Arcoraci
BLD-Aging Inspection9/10/20079/10/20079/10/2007 CANC
DetailsTom Arcoraci
MISC ACTIONS  7/12/2007 DONE
Received letter addressed to John Menard and 8 1/2" x 11" of pages MSK-1, MSK-2. Per John give to mechanical inspector. Put in Alan Hauser's box.
BLD-Aging Inspection6/7/20076/7/20076/7/2007 PASS
DetailsTom Arcoraci
(F) Reprint permit  3/9/2007  
Issue PAID IN FULL permit  3/8/2007 DONE
Telephone call  1/11/2007 DONE
lft vm for cornell Larson ###-#### that permit and fees are ready to be picked up but needs ACHD
Permit Ready to Issue  1/11/2007 DONE
Routing - FIRE1/8/2007 1/10/2007 PASS
Attached updated review comments to plans.
Routing - PLAN CHECK1/10/2007 1/10/2007  
Routing - PUBLIC WORKS1/10/2007 1/10/2007 PASS
Routing - PLAN CHECK1/10/2007 1/10/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/10/2007 DONE
Inspection Record Card- Bld  1/10/2007  
Plan assigned to (JCM)11/30/2006 1/10/2007 PASS
1/10/2007 13:08:11 JCM - activity updated through activity BLDA022 from case BLD06-03407.
Routing - PLAN CHECK1/4/2007 1/8/2007 PASS
Plan resubmittals received  1/5/2007  
received letter from larson architects p a & "2" sheets each of SP-1--plans taken to john menard
1st review completed  1/4/2007 FAIL
Failed fire.
Routing - FIRE1/2/2007 1/4/2007 FAIL
Faxed IFC review to architect. Attached review comments to plans.
Routing - PLAN CHECK12/26/2006 1/2/2007 PASS
John Menard
Plan Reviewer's activity  1/2/2007 PASS
Reviewed and approved resubmittals. JCM
Plan resubmittals received  12/27/2006  
received letter from larson architects pa, app, (3) cert of values of $381,418, $138,602, & $26,900. also "2" sets of plans including each sheet of -O, A-1, A-3, P-1, P-2, P-3, EO.O, E1.O, E2.1L, & E2.1P--plans taken to john menard
Routing - PLANNING12/22/2006 12/26/2006 PASS
Approved per DRH06-00142.
Routing - PLUMBING12/14/2006 12/22/2006 PASS
per plans and 2003 upc
Plan resubmittals requested  12/20/2006 DONE
E-mailed the architect a copy of the cover letter and plan review requesting revisions. JCM
Routing - Erosion and Sediment12/13/2006 12/14/2006 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS12/7/2006 12/13/2006 PASS
Routing Off Site - STRUCTURAL11/30/2006 12/13/2006 PASS
Received an e-mailed letter from the consulting structural engineer approving the plans and calculations as submitted. JCM
Routing - PLANNING Land Div11/30/2006 12/7/2006 PASS
Additional plans submitted  12/5/2006 DONE
Received fax copy of completed Start Up for special Inspection form from Dawna Jenkins, Larson Architects for this project. Form was not provided at plan intake meeting. Gave copy received to John Menard, the assigned plan reviewer.
Application received  11/30/2006  
Pending Assignment by MYS11/30/2006 11/30/2006 DONE
11/30/2006 13:29:03 JCM - activity updated through activity BLDA166 from case BLD06-03407.
Recd Pcfee & Taken To Pln CK  11/30/2006  
Telephone call  11/30/2006  
called Action Couriers for pick up and deliver to AHJ Engineers
Plan routing begun/NEW & ADDTN  11/30/2006  
BLD-Conference8/25/20088/25/2008 P 
DetailsJim Storey