Third Notice BLD | 7/18/2007 | 7/18/2007 | 7/20/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 7/5/2007 | 7/5/2007 | 7/18/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/22/2007 | 7/5/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (FNL) | | | 6/22/2007 | | DONE |
|
|
|
|
BLD-Final | 6/8/2007 | 6/8/2007 | 6/8/2007 | P | PASS |
Mike Jordan
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang. Ok for perm occ.
|
Permanent Occupancy | | 6/8/2007 | 6/8/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/8/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11653 issued 6-8-07 to Verizon Wireless.
|
Temporary occupancy | | | 6/7/2007 | | DONE |
|
|
|
Temp. Occ. Cert. # 5604 issued 6-7-07 to Verizon Wireless.
|
FIRE-Final Inspection | 6/1/2007 | 6/1/2007 | 6/1/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 5/31/2007 | 6/1/2007 | 6/1/2007 | A | PART |
Mike Jordan
|
|
|
john ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. ok for temp occ. Needs to provide tempered glass in doorways. c/n issued.
|
FIRE-Final Inspection | 5/30/2007 | 5/31/2007 | 5/31/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide request to exit sensors and manual switch with stickes as discussed for the doors with the mag locks. Also provide means to open top leaf of double door as per discussion. All other items are ok.
|
BLD-Final | 5/30/2007 | 5/31/2007 | 5/31/2007 | A | NR |
Mike Jordan
|
|
|
JOHN; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Other | 5/23/2007 | 5/23/2007 | 5/23/2007 | P | PART |
Mike Jordan
|
|
|
John - grid; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Pending mech and elec.
|
BLD-Other | 5/14/2007 | 5/15/2007 | 5/15/2007 | A | PART |
Jim Sly
|
|
|
John - grid ceiling; Phone #: ###-#### Internet Inspection Request from: Victoria Beall OK'd Grid per astm 636........will call for insp later.
|
FIRE-Conference | 5/10/2007 | 5/10/2007 | 5/11/2007 | P | DONE |
Troy Cobbley
|
|
|
I went over the life safety requirements with the contractor.
|
Plan Reviewer's activity | | | 5/10/2007 | | DONE |
|
|
|
This builing is not fire sprinklered. Modified IFC review comments to reflect correction.
|
BLD-Energy code compliance | 4/23/2007 | 4/23/2007 | 4/23/2007 | P | PASS |
Mike Jordan
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 4/20/2007 | 4/20/2007 | 4/20/2007 | P | PART |
Dave Hannah
|
|
|
John asap.; Phone #: ###-#### Internet Inspection Request from: Stacie Backus int shear walls ok to cover int framing ok ok to insulate
|
BLD-Other | 4/6/2007 | 4/6/2007 | 4/6/2007 | P | PASS |
Mike Jordan
|
|
|
john - ext shear; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Exterior shear ok.
|
BLD-Footing | 4/4/2007 | 4/5/2007 | 4/5/2007 | P | PART |
Mike Jordan
|
|
|
john ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. wip. Needs to install transverse bar @ 24 oc.
|
Plan assigned to (R_H) | 12/12/2006 | | 3/30/2007 | | PASS |
|
|
|
3/30/2007 10:33:50 RMH - activity updated through activity BLDA022 from case BLD06-03431.
|
Routing - PLANNING | 3/28/2007 | | 3/30/2007 | | PASS |
|
|
|
Approved per DRH06-00546
|
Routing - PLAN CHECK | 3/30/2007 | | 3/30/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 3/30/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/30/2007 | | |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 3/30/2007 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/30/2007 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/27/2007 | | 3/28/2007 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 3/27/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/23/2007 | | 3/27/2007 | | PEND |
|
|
|
Permit pending approval of other departments
|
Plan resubmittals received | | | 3/21/2007 | | |
|
|
|
Received 1 copy of cover transmittal, 1 copy of responce letter (2pgs), 1 copy of plan review report, 3 copies of structural calcs, 3 copies of sheets CS, A1, A2, A3, A4, A5, A6, A7, A8, A9, A10, A11, A12, A13, A14, A15, A16, A17, A18, F1, S1, S2, S3, S4, P1, P2, P3, M1, M2, M3, ME1, E1, E2, E3, E4, E5, E6 and taken to Ron Hill
|
Routing - FIRE | 1/19/2007 | | 1/23/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 1/23/2007 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PLAN CHECK | 12/13/2006 | | 1/19/2007 | | FAIL |
|
|
|
Faxed and mailed corrections to the architect, routed plans to fire.
|
Telephone call | | | 1/12/2007 | | |
|
|
|
spoke with someone from Gruskin Group, explained routing process
|
Routing - PLANNING | 12/13/2006 | | 12/13/2006 | | FAIL |
|
|
|
Sarah Schafer (no DR or zoning certificate located)
There are no DR approvals for this project. I have contacted the applicant and they will be submitting the required information.
|
Routing - PUBLIC WORKS | 12/12/2006 | | 12/13/2006 | | PASS |
|
|
|
|
Routing - Addressing | 12/12/2006 | | 12/12/2006 | | PASS |
|
|
|
|
Pending Assignment by MYS | 12/5/2006 | | 12/12/2006 | | DONE |
|
|
|
12/12/2006 14:48:45 MYS - activity updated through activity BLDA175 from case BLD06-03431.
|
Recd Pcfee & Taken To Pln CK | | | 12/5/2006 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/5/2006 | | |
|
|
|
|
Application received | | | 12/5/2006 | | |
|
|
|
|