Third Notice BLD | 3/5/2008 | 3/5/2008 | 11/19/2018 | | DONE |
Cathy Brown
|
|
|
This permit finaled on the web by Jeff Miller
|
Second Notice BLD | 2/6/2008 | 2/6/2008 | 3/5/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/15/2008 | 2/6/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/15/2008 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/30/2007 | 12/3/2007 | 12/3/2007 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Mark Senteno with the Boise Fire Dept is ok with the gate width being at 19'-7"
|
BLD-Conference | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/16/2007 at 1:06:22 PM. Contact: ###-####. change in corr constru ok
|
BLD-Final | 10/31/2007 | 11/1/2007 | 11/1/2007 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/31/2007 at 4:06:24 PM. Contact: ###-####. ok for temp///1/15/08 per phone call with Tom A ok to give perm occ///bas
|
BLD-Final | 10/31/2007 | 10/31/2007 | 11/1/2007 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/31/2007 at 10:34:02 AM. Contact: ###-####.
|
BLD-Final | 10/29/2007 | 10/30/2007 | 10/31/2007 | P | CANC |
Tom Arcoraci
|
|
|
tony Phone #: ###-####
|
FIRE-Final Inspection | 10/31/2007 | 10/31/2007 | 10/31/2007 | P | DONE |
|
|
|
Request from Mike Laky for Temporary Occupancy due to outstanding FA issues was approved by D. Hanneman for Fire. I signed onsite card for Fire approval 5:30 pm. Building inspection scheduled for tomorrow. See request letter attached under fire alarm permit FIR07-00380.
|
BLD-Final | 10/26/2007 | 10/29/2007 | 10/29/2007 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/26/2007 at 11:32:48 AM. Contact: ###-####. needs fire to sign
|
FIRE-Final Inspection | 10/24/2007 | 10/26/2007 | 10/26/2007 | A | FAIL |
Troy Cobbley
|
|
|
The smoke control system still has issues being worked out by the third party engineer Jerry Oneal. All other life safety items in the new medical wing are ok.
|
FIRE-Final Inspection | 10/23/2007 | 10/25/2007 | 10/26/2007 | P | FAIL |
Troy Cobbley
|
|
|
The smoke control system is not working correctly as per Mike Timmerman.
|
Code Occupancy Approval | 10/26/2007 | 10/26/2007 | 10/26/2007 | P | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
FIRE-Final Inspection | 10/22/2007 | 10/23/2007 | 10/23/2007 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler permits need finaling first.
|
FIRE-Alarm Testing | 10/18/2007 | 10/23/2007 | 10/23/2007 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit number was called in. The FIR permit number should have been used.
|
BLD-Framing/Rough-in | 9/24/2007 | 9/24/2007 | 9/24/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/24/2007 at 6:59:14 AM. Contact: ###-####. wip ok grid ok
|
BLD-Wall cover | 9/6/2007 | 9/7/2007 | 9/7/2007 | P | PASS |
Tom Arcoraci
|
|
|
see tony
|
BLD-Conference | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/5/2007 at 12:50:06 PM. Contact: ###-####.
|
BLD-Conference | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | PASS |
Tom Arcoraci
|
|
|
need arch to submit fire barrier change
|
BLD-Framing/Rough-in | 8/22/2007 | 8/23/2007 | 8/23/2007 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/22/2007 at 3:48:20 PM. Contact: ###-####. wip ok
|
BLD-Framing/Rough-in | 8/14/2007 | 8/14/2007 | 8/14/2007 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/14/2007 at 8:06:16 AM. Contact: ###-####. fat grid for hardlid in beding units, staff bathroom, janitor closet. pending elec.
|
BLD-Framing/Rough-in | 8/6/2007 | 8/6/2007 | 8/6/2007 | P | PASS |
Tom Arcoraci
|
|
|
Tony; Phone #: ###-#### Internet wip ok Inspection Request from: Cathy Weisshaupt
|
CHANGE STATUS TO (ISS) | | | 8/2/2007 | | DONE |
|
|
|
8-2-07 for unknown reason this permit was put back to rev status , could not find a reason why ... talked with Rita Deyoung and it was decided to put permit back to issue mode. /// DLD
|
Plan resubmittals received | | | 7/31/2007 | | DONE |
|
|
|
received 1 cocument transmittal,and 2 copys of sheets M1.1A,M5.1 taken to John M
|
BLD-Framing/Rough-in | 7/12/2007 | 7/13/2007 | 7/13/2007 | A | PART |
Tom Arcoraci
|
|
|
###-#### tony - corridor wip ok
|
Routing - FIRE | 6/7/2007 | | 6/11/2007 | | FAIL |
|
|
|
IFC review comments have been updated to reflect the IFC requirments for the recently submitted engineered smoke control system. Updated IFC comments and resubmittal itmes have been faxed to the mechanical engineer and architect.
|
Plan resubmittals requested | | | 6/7/2007 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 6/7/2007 | | DONE |
|
|
|
E-mailed the architect a copy of the review comments for the smoke control system design.
|
Plan resubmittals received | | | 6/1/2007 | | |
|
|
|
Received deferred resubmittals on two copies of pages M0.1, M1.0, M1.1A, M2.0; taken to John Menard
|
BLD-Aging Inspection | 5/28/2007 | 5/28/2007 | 5/30/2007 | | PASS |
Tom Arcoraci
|
|
|
|
Meeting | | | 5/9/2007 | | DONE |
|
|
|
Met with Ed Deffner, Layton Const. Mgr. and George Slane regarding the classification of part of the medical unit as a B occupancy but with locked (I-3) exiting. Explained code requirements for B vs. I-3 exiting. He will work with the architect to either provide appropriate separation and exiting for this area to be a B occupancy or re-classify it as an I-3 and provide the required guard monitoring, remote controlled exiting and other requirements for !-3 occupancies. The FA permit cannot be approved until the occupancy and exiting have been approved by the Bldg plan reviewer and are properly reflected on the FA plans. We also discussed whether manual pull stations would be required in the mechanical/plumbing service areas behind the bathrooms; if these areas are separated by an occupancy separation wall from the I-3 area, no alarm devices would be required in them. If they are not separated, (i.e. it is an unseparated use), then the I-3 required alarm devices are required within the space. He will verify that with the architect and advise the FA vendor accordingly.
|
Plan resubmittals received | | | 4/19/2007 | | |
|
|
|
Received 1 letter of transmittal,and 3 copys of sheet M1.1A taken to John M.
|
Meeting | | | 3/14/2007 | | DONE |
|
|
|
Mtg with Ed defner, Layton Const, Steve Bastian, Elkhorn Engr's, J. Menard, D. Hanneman, S.Rogers, and rep's from Ada Co Sheriff and CSHQA, regarding s mechanical smoke control approach designed by Steve Bastian, Elkhorn Engr's. We indicated we will use a 3rd party engineering review of the design and also special inspections for acceptance testing per 910.18. Layton indicated they may also consider a passive design option if the mechanical system proves to be too costly.
|
BLD-Footing | 3/6/2007 | 3/7/2007 | 3/7/2007 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/6/2007 at 11:01:39 AM. Contact: ###-####. spec on site
|
BLD-Footing | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/27/2007 at 11:04:44 AM. Contact: ###-####. pending mti spec insp
|
Inspection Record Card- Bld | | | 2/27/2007 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/21/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/20/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/16/2007 | | DONE |
|
|
|
left vm with katie butler at ###-#### - permit ready and fees given - also called tom coughlin (GC) at ###-#### and gave the same information
|
Permit Ready to Issue | | | 2/16/2007 | | |
|
|
|
|
Telephone call | | | 2/15/2007 | | DONE |
|
|
|
t/c w Tom Couthlin at Layton Construction - he said the project value listed on the initial c of v was right - i asked him about the ACHD issue and he is faxing me a letter regarding that. 2/15/07ps
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/13/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/3/2007 | | 2/13/2007 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 12/18/2006 | | 2/13/2007 | | PASS |
|
|
|
2/13/2007 14:50:39 JCM - activity updated through activity BLDA022 from case BLD06-03515.
|
Plan resubmittals requested | | | 2/9/2007 | | DONE |
|
|
|
E-mailed the architect a request for additional information on the smoke control system. JCM
|
Plan resubmittals received | | | 2/5/2007 | | |
|
|
|
rec'd transmittal letter - 2 sets of sheet #s M0.1, M1.0, M2.0 - taken to John Menard
|
Routing - FIRE | 1/31/2007 | | 2/3/2007 | | PASS |
|
|
|
Emailed architect updated review comments and attached review comments to plans.
|
Plan resubmittals received | | | 2/1/2007 | | |
|
|
|
rec'd transmittal letter, response letter from CSHQA - 2 sets of sheet #s G1.1, A9.2 - taken to John Menard
|
Plan resubmittals requested | | | 1/31/2007 | | DONE |
|
|
|
E-mailed the architect a letter requesting additional revisions. JCM
|
Routing - PLAN CHECK | 1/12/2007 | | 1/31/2007 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 1/25/2007 | | |
|
|
|
rec'd transmittal letter, response letter from CSHQA, 2 sets of sheet #s G1.1, A2.0, A9.1, A9.2, A9.3, A9.5 - taken to John Menard
|
Plan resubmittals received | | | 1/22/2007 | | DONE |
|
|
|
rec'd 1 transmittal cover - 1 response letter - 2 copies of sheet #s C1.2, C1.3, A2.1 - taken to Scott Arellano
|
Routing - FIRE | 1/11/2007 | | 1/12/2007 | | FAIL |
|
|
|
Emailed resubmittal items to architect.
|
1st review completed | | | 1/12/2007 | | FAIL |
|
|
|
Failed plan check and fire.
|
Plan resubmittals requested | | | 1/11/2007 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review requesting clarification and revisions. JCM
|
Routing - PLAN CHECK | 12/27/2006 | | 1/11/2007 | | FAIL |
|
|
|
|
Telephone call | | | 1/9/2007 | | |
|
|
|
katie from CSHQA called and needed help online to look up status and activities of permit
|
Routing Off Site - STRUCTURAL | 12/18/2006 | | 1/3/2007 | | PASS |
|
|
|
Called Action Courier for pick up @ 1:25on 12/18/06 BAS - Received a letter from the consulting structural engineer approving the structural documents for this project. JCM
|
Routing - PLANNING | 12/26/2006 | | 12/27/2006 | | PASS |
|
|
|
Approved per DRH03-00018 and CUP02-00153.
|
Routing - PLUMBING | 12/21/2006 | | 12/26/2006 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 12/19/2006 | | 12/21/2006 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 12/21/2006 | | 12/21/2006 | | PASS |
|
|
|
Refer to ESC06-01634 as master ESC plan for project.adh.
|
Routing - PLANNING Land Div | 12/19/2006 | | 12/20/2006 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/15/2006 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/15/2006 | | |
|
|
|
|
Application received | | | 12/14/2006 | | |
|
|
|
|
Routing - PLAN CHECK | 6/11/2007 | | | | |
|
|
|
|