Permit Information
Permit NumberBLD06-03545
StatusFinaled
Name ST LUKES REG MED CNTR
Site Address 190 E BANNOCK ST
Project NameST LUKES
Customer Number26-117
ePlanReviewNo
Description
(ST LUKES - 2 SOUTH - LABOR & DELIVERY - PHASE 1) This building is fully sprinklered based on occupancy use group requirements. To remodel within existing Labor and Delivery Patient Rooms as per approved plans. Work includes select demolition within rooms and above ceiling areas to prepare for installation of new water closets, tubs, sinks, cabinetry, and interior finishes; to replace existing ceiling radiant heat units with new units; and upgrade electrical, mechanical, plumbing and sprinkler systems to meet tenant needs and comply with minimum adopted codes and ordinances of Boise City. A "Certificate of Compliance" is required for final approval for this project scope of work. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/22/20099/8/2009 DONE
First Notice4/7/20094/7/20097/22/2009 DONE
DetailsDave Hannah
BLD-Final4/3/20094/7/20094/7/2009APASS
DetailsDave Hannah
Clean up of old permits
DOC - Permit Finaled4/7/20094/7/20094/7/2009PPASS
DetailsDave Hannah
Letter of compliance  4/7/2009 DONE
DetailsBarbara Stitt
BLD-Final3/14/20073/15/20073/20/2007PCANC
DetailsTom Arcoraci
Rod; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
FIRE-Final Inspection3/14/20073/15/20073/15/2007APASS
DetailsForrest France
Fire life safety inspection passed, noted two missing doors at the bathrooms to be installed prior to structural final.
Issue & PRINT to be Invoiced  2/2/2007 DONE
Routing - PLAN CHECK1/24/2007 1/30/2007 PASS
Plans provided showing locations of two fully accessible Labor and Delivery patient rooms that serve this floor area of the hospital. Routing to permit desk to issue.
Plan resubmittals received  1/30/2007 DONE
Plan clarification received with 8-1/2" x 11" floor plan showing previously created accessible patient rooms for L & D.
PLANS/APPL TAKEN TO FRONT DESK  1/30/2007 PASS
Inspection Record Card- Bld  1/30/2007 DONE
CHANGE STATUS TO (RDY)  1/30/2007  
Telephone call  1/30/2007 DONE
sent fax to Curtis ///dld
Plan assigned to (DRS)12/22/2006 1/30/2007 PASS
1/30/2007 12:56:23 DRS - activity updated through activity BLDA022 from case BLD06-03545.
Routing - FIRE1/22/2007 1/24/2007 PASS
Attached review comments to plans.
1st review completed  1/24/2007 FAIL
Failed plan check.
Plan resubmittals requested  1/22/2007 DONE
Faxed copy of plan review conditions needing response to Tom Zabala, ZGA.
Routing - PLAN CHECK12/27/2006 1/22/2007 FAIL
Resubmittals required for accessibility compliance for one patient room. Routing to fire code analyst for review.
Routing - PLUMBING  12/27/2006 PASS
120 deg. max hot water to public lavs.
Routing - PUBLIC WORKS12/22/2006 12/26/2006 PASS
Routing - Addressing12/26/2006 12/26/2006 PASS
Pending Assignment by MYS12/15/2006 12/22/2006 DONE
12/22/2006 10:46:55 MYS - activity updated through activity BLDA168 from case BLD06-03545.
Plans ACCEPTED BY PLAN TECH  12/18/2006  
Application received  12/15/2006