Third Notice BLD | 3/5/2008 | 3/5/2008 | 3/5/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 2/6/2008 | 2/6/2008 | 3/5/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/4/2008 | 2/6/2008 | | DONE |
|
|
|
|
BLD-Final | 1/3/2008 | 1/4/2008 | 1/4/2008 | A | PASS |
Tom Arcoraci
|
|
|
rick - please call 1/2 hr prior to inspection Phone #: ###-#### ok for perm
|
Permanent Occupancy UNPAID FEE | | | 1/4/2008 | | DONE |
|
|
|
|
BLD-Final | 11/29/2007 | 11/30/2007 | 12/3/2007 | P | PART |
Dave Hannah
|
|
|
rick Phone #: ###-#### Note: please call 1/2 hr prior to inspection ok for temp occ needs plumbing to go perm needs ada stoves in a units and fix water closit
|
Temporary Occupancy UNPAID FEE | | | 12/3/2007 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/29/2007 | 11/30/2007 | 11/30/2007 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
FIRE-Final Inspection | 11/27/2007 | 11/28/2007 | 11/28/2007 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire sprinkler permit needs finaled first. I went over the life safety requirements with Rick.
|
Code Occupancy Approval | 11/28/2007 | 11/28/2007 | 11/28/2007 | P | PASS |
Dena Gambrel
|
|
|
|
Code Occupancy Approval | 11/21/2007 | 11/21/2007 | 11/21/2007 | P | FAIL |
Dena Gambrel
|
|
|
11-21-07 Need striping and wheel stops installed.
|
BLD-Energy code compliance | 9/20/2007 | 9/21/2007 | 9/21/2007 | P | PASS |
Tom Arcoraci
|
|
|
RICK Phone #: ###-####
|
BLD-Conference | 9/18/2007 | 9/18/2007 | 9/18/2007 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 9/17/2007 | 9/18/2007 | 9/18/2007 | P | CANC |
Tom Arcoraci
|
|
|
rick Phone #: ###-####
|
BLD-Framing/Rough-in | 9/17/2007 | 9/18/2007 | 9/18/2007 | P | PASS |
Tom Arcoraci
|
|
|
rick Phone #: ###-####
|
BLD-Framing/Rough-in | 8/15/2007 | 8/16/2007 | 8/16/2007 | A | PART |
Tom Arcoraci
|
|
|
RICK NOTE: PARTIAL Phone #: ###-####
|
BLD-Other | 8/9/2007 | 8/10/2007 | 8/10/2007 | A | PASS |
Jim Sly
|
|
|
rick Note: shear Phone #: ###-#### Ext shear nailing, flr/flr straps OK. holdowns....including ones for 4x4's at cantilever in breezeway ....inspected by MTI.
|
BLD-Conference | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PASS |
Tom Arcoraci
|
|
|
rick Phone #: ###-####
|
BLD-Foundation | 6/15/2007 | 6/18/2007 | 6/18/2007 | A | PASS |
Tom Arcoraci
|
|
|
RICK; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles mti on site
|
BLD-Footing | 6/14/2007 | 6/15/2007 | 6/15/2007 | A | PASS |
Mike Jordan
|
|
|
rick ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. footings for breezeway and alt for additional bedroom. breezeway will be enclosed. Reviewed special insp. reports for soils issues and RFI from engineer. ok.
|
BLD-Footing | 6/4/2007 | 6/5/2007 | 6/5/2007 | A | CANC |
Tom Arcoraci
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Conference | 6/5/2007 | 6/5/2007 | 6/5/2007 | P | PASS |
Tom Arcoraci
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
Routing - PLAN CHECK | 4/20/2007 | | 5/4/2007 | | PASS |
|
|
|
4/20/07 - Received final approved accessibility review from ICC, sent copy to architect, and attached copy to documents section of this permit. Waiting for final structural/nonstructural review from ICC. (msouthard)
5/4/07 - All reviews by ICC approved on this date. Plans prepared for issuance.
|
Plan assigned to (MYS) | 3/1/2007 | | 5/4/2007 | | PASS |
|
|
|
5/4/2007 09:18:20 MYS - activity updated through activity BLDA022 from case BLD06-03598.
|
Routing - PLANNING | 5/4/2007 | | 5/4/2007 | | PASS |
|
|
|
Rereviewed the changes to balconies and approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/4/2007 | | |
|
|
|
|
Permit Ready to Issue | | | 5/4/2007 | | |
|
|
|
|
Telephone call | | | 5/4/2007 | | DONE |
|
|
|
left mess for randy with ekc at ###-#### that permit is ready
|
Issue PAID IN FULL permit | | | 5/4/2007 | | DONE |
|
|
|
|
Routing - PLANNING | 4/17/2007 | | 4/20/2007 | | PASS |
|
|
|
Sarah. Plans revised per architect's letter of 4/13/07: exterior elevations, new concrete patios and wood balconies, living room window changed to a doors, change of bedroom window in unit #106 to east wall.
Approved. Staff updated the planning file.
|
Plan resubmittals received | | | 4/17/2007 | | |
|
|
|
Received 3 copies of the following: 3pg. response letter, 1pg. structural response, structural calcs, copy of plan review report dated 3/9/07, copy of plan review report dated 4/4/07, a0.11, a0.21, a0.22, a1.11, a1.12, a2.11, a2.12, a2.13, a2.21, a3.11, a3.12, a4.11, a5.11, a5.12, a5.13, a5.14, a5.21, a7.11, a7.21, a8.11, a8.21, en0.10a, en0.10b, s1.00, s2.00, s3.00, s4.00, s5.00, s6.00, s7.00, m0.11, m2.11, m3.11, p0.11, p2.11, p2.12, p3.11, e0.11, e1.11, e2.11; also received original copy of full set of plans, original structural calcs, and original project manual that was submitted; took to Marlene S.
|
Routing - PLAN CHECK | 3/1/2007 | | 4/5/2007 | | FAIL |
|
|
|
4/17/07 - Sent resubmitted plans and architect's responses to ICC via FedEx.
4/5/07 - Failed, Marlene faxed correction report to the architect requesting additional information to be submitted for further review. See copies of accessibility & structural/nonstructural reviews by ICC attached to documents section of this permit.
3/2/07 - Plan outsourced to ICC for plan review. Plans shipped via Fed-Ex by M. Southard.
|
Routing - PLAN CHECK | 1/16/2007 | | 4/5/2007 | | FAIL |
|
|
|
Plan review will be done by an outside review firm (ICC), routing to fire for their review.
|
Plan assigned to (M_P) | 12/22/2006 | | 3/1/2007 | | DEFR |
|
|
|
Plan outsourced to ICC for plan review. Plans shipped via Fed-Ex on 3/2/07 by M. Southard
|
Routing - FIRE | 2/26/2007 | | 3/1/2007 | | PASS |
|
|
|
Attached review comments to plans. Emailed review comments to architect.
|
1st review completed | | | 3/1/2007 | | FAIL |
|
|
|
ICC plan check review failed. Architect notified.
|
Routing - PLANNING | 1/4/2007 | | 1/16/2007 | | PASS |
|
|
|
Approved.
|
Routing - Erosion and Sediment | 1/3/2007 | | 1/4/2007 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Plans ACCEPTED BY PLAN TECH | | | 1/3/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/3/2007 | | DONE |
|
|
|
|
Application received | | | 12/22/2006 | | |
|
|
|
|