Permit Information
Permit NumberBLD06-03634
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 415 S 8TH ST
Project NameO W SMITH/R GREY BLDG
Customer Number 
ePlanReviewNo
Description
(R GREY GALLERY - SMITH/GREY BLDG - 1ST STORY AND BASEMENT) This building is fire sprinklered to substitute for the 1-hr fire-resistance-rated construction of the building. To construct a retail sales gallery tenant space on the first story and basement of the Smith/Grey building. The entire tenant space will have a floor area of about 5,702 square feet (2,700 square foot 1st story retail, 917 square foot 1st story work area, 802 square foot 1st story office/restroom/breakroom, and 1,283 square foot basement storage). Work is to include interior nonbearing walls, suspended ceilings, a new recessed entry, a new interior stairway, and finishes. The basement stairways, elevator, wheelchair platform lift, and back stairway were constructed under the shell permit (BLD06-00845). The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  5/10/2010 DONE
BLD-Final4/30/20105/3/20105/6/2010APASS
DetailsDave Hannah
Status update please for Barb please? Phone #: ###-####
FIRE-Final Inspection3/25/20103/25/20103/25/2010APASS
DetailsForrest France
Fire life safety finaled.
FIRE-Final Inspection3/24/20103/24/20103/24/2010PPASS
DetailsForrest France
Noted corrections are finished per activity notes on project related FIR and BLD permits.
BLD-Final5/4/20095/5/20095/6/2009PNR
DetailsDave Hannah
marva Phone #: ###-####
FIRE-Final Inspection5/4/20095/5/20095/5/2009PFAIL
DetailsForrest France
See correction notice items for shell permit BLD06-00845.
FIRE-Conference1/14/20091/14/20091/14/2009PDONE
DetailsForrest France
Regarding project related fire sprinkler permit work finals.
Case Summary (BLD)  12/22/2008  
Case Summary (BLD)  9/30/2008 DONE
FIRE-Final Inspection8/11/20088/12/20088/18/2008AFAIL
DetailsForrest France
Failed per inspection comments 7/6/07.
BLD-Final8/11/20088/12/20088/14/2008APART
DetailsDave Hannah
Barb----Forrest/Dave this was given temp on 7-6-07 and I need to know if they did what was required to give them perm? See activity notes regarding inspection on 7-6-07. Please let me know...thanks Phone #: ###-####
Office Staff conference/action  8/14/2008 DONE
DetailsBarbara Stitt
Per Phone call from Dave Hannah-this permit needs to remain in the temp status as part of the Gem Noble Building///8/14/08 BAS
CHANGE STATUS TO (TMP)  7/22/2008 DONE
DetailsTisha Gallop
change status to TMP under temp occ. until issued resolved for the shell permit Bld06-00845//7/22/08 LEG
DOC - Permit Expired  7/9/2008  
DetailsTisha Gallop
Spoke with Tammy from McAlvain Construction; they are no longer doing this project and do not plan on continuing with this project. No other contractor has taken over. The project has stopped for financial reasons and there has been no activity out there past the expiration date. There cannot be a perm. occupancy issued because the shell permit Bld06-00845 has also expired and stopped work.//7/8/08 LEG
BLD-Final7/5/20077/6/20077/6/2007APART
DetailsJim Storey
Dennis ; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok per 425
FIRE-Final Inspection7/5/20077/6/20077/6/2007AFAIL
DetailsTroy Cobbley
This inspection was for the tenant only. The fire alarm and fire sprinkler permits need finaling. Also the doors and hardware need to be installed for verification and the plans indicate the second exit out of the south side of the building through an egress corridor. The exit sign does not point the way and there has been a barrier installed. Per the contractor there is documentation coming that will allow the second exit through the back (west end) of the tenant.
Temporary occupancy7/18/200710/16/20077/6/2007 DONE
Temp. Occ. Cert. # 5616 issued 7-6-07 to the R. Grey Gallery.
BLD-Final7/2/20077/3/20077/3/2007PNR
DetailsDave Hannah
###-#### Dennis Coleman- Temp only please needs other trades to signoff
FIRE-Final Inspection7/2/20077/3/20077/3/2007ANR
DetailsForrest France
Pending shell related permit finals.
BLD-Final7/1/20077/2/20077/2/2007PNR
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Alex Monge
BLD-Framing/Rough-in6/18/20076/19/20076/19/2007APASS
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Alex Monge
Issue PAID IN FULL permit  3/29/2007 DONE
Routing - PLAN CHECK3/27/2007 3/28/2007 DONE
Checked with Julie Archambeault to confirm that the recessed entry was previously approved by zoning.
PLANS/APPL TAKEN TO FRONT DESK  3/28/2007 DONE
Print Occupancy Form  3/28/2007 DONE
Telephone call  3/28/2007 DONE
left message for robert kaylor with emily at ###-#### - permit ready and fees given
Permit Ready to Issue  3/28/2007  
Plan assigned to (CJW)1/4/2007 3/28/2007 PASS
3/28/2007 10:32:03 CJW - activity updated through activity BLDA022 from case BLD06-03634.
Routing - FIRE3/26/2007 3/27/2007 PASS
Attached updated review comments to plans.
Routing - PLAN CHECK2/5/2007 3/26/2007 PASS
Completed the IBC plan review of the resubmitted drawings. Drawings approved as noted and attached.
Plan resubmittals received  3/15/2007 DONE
rec'd transmittal cover - response letter from doug cooper with revisions - 2 sets of sheet #s A0.1, A2.0, A3.0, A3.1, A5.0, A6.0, A6.1, A6.2, A7.0, A8.0, MC1.0, M1.0, M2.0, P1.0, E1.0, E1.1, E1.2 - taken to carl westfall
Routing - FIRE2/2/2007 2/5/2007 FAIL
Emailed architect resubmittal requirements and attached Haz Mat consultants list. Attached review comments to plans.
1st review completed  2/5/2007 FAIL
Failed plan check and fire.
Routing - PLAN CHECK1/5/2007 2/2/2007 FAIL
The IBC plan review was started on January 31, 2007 and was finished on February 2, 2007. Revised drawings were required. See the plan review report.
Routing - PUBLIC WORKS1/4/2007 1/5/2007 PASS
Pending Assignment by MYS1/2/2007 1/4/2007 DONE
1/4/2007 16:01:21 MYS - activity updated through activity BLDA172 from case BLD06-03634.
Plans ACCEPTED BY PLAN TECH  1/2/2007  
Application received  12/29/2006  
Recd Pcfee & Taken To Pln CK  12/29/2006 DONE