Third Notice BLD | 10/1/2007 | 10/1/2007 | 10/25/2007 | | DONE |
|
|
|
This permit finaled on the web by Anna Buschbacher
|
Second Notice BLD | 9/13/2007 | 9/13/2007 | 10/1/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/10/2007 | 9/13/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/10/2007 | | DONE |
|
|
|
|
BLD-Final | 8/3/2007 | 8/6/2007 | 8/6/2007 | A | PASS |
Tom Arcoraci
|
|
|
matt Phone #: ###-####
|
FIRE-Final Inspection | 8/3/2007 | 8/3/2007 | 8/6/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 8/1/2007 | 8/2/2007 | 8/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need to provide an exit sign at the main exit and provide the exit discharge lighting as per the plans. See sheet A4.0
|
FIRE-Final Inspection | 8/1/2007 | 8/1/2007 | 8/1/2007 | P | CANC |
Troy Cobbley
|
|
|
matt called and said that he would not be ready today due to a indicator issue
|
BLD-Other | 7/16/2007 | 7/16/2007 | 7/16/2007 | P | PASS |
Tom Arcoraci
|
|
|
matt Note: ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 5/15/2007 | 5/16/2007 | 5/16/2007 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/15/2007 at 5:01:35 PM. Contact: ###-####. ok pending elec ok
|
CHANGE ISSUED DATE | | | 4/4/2007 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/4/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 4/4/2007 | | DONE |
|
|
|
need G.C. number check is in the safe ///dld
|
Routing - PLAN CHECK | 3/30/2007 | | 4/3/2007 | | PASS |
|
|
|
Routing to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2007 | | PASS |
|
|
|
|
Print Occupancy Form | | | 4/3/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/3/2007 | | DONE |
|
|
|
t/c w matt rhees at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 4/3/2007 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 1/9/2007 | | 4/3/2007 | | PASS |
|
|
|
4/3/2007 07:05:49 DRS - activity updated through activity BLDA022 from case BLD07-00014.
|
Routing - FIRE | 3/29/2007 | | 3/30/2007 | | PASS |
|
|
|
Attached updated review comments to plans.
|
Routing - PLAN CHECK | 3/28/2007 | | 3/29/2007 | | PEND |
|
|
|
Inserted new sheet A1.0 into plans showing fire extinguisher locations proposed. Routed back to fire for re-review.
|
Plan resubmittals received | | | 3/29/2007 | | DONE |
|
|
|
Received 1 project letter,and 2 copys of sheet A1.0 taken to Dan S.
|
Routing - FIRE | 3/27/2007 | | 3/28/2007 | | FAIL |
|
|
|
Faxed resubmittal item to architect. Attached updated review comments to plans.
|
Routing - PUBLIC WORKS | 3/27/2007 | | 3/27/2007 | | PASS |
|
|
|
Project in West Boise Sewer District. They will assess fee's. Drinking fountain added to project and one hand sink deleted from project with new plan submittals.
|
Routing - PLAN CHECK | 1/30/2007 | | 3/27/2007 | | PEND |
|
|
|
New sets of plans submitted. Plans red-lined for code clarification. No further resubmittals required. Copy of final review conditions faxed to architect. Routing to fire code analyst for review.
|
Plan resubmittals received | | | 3/19/2007 | | |
|
|
|
Received transmittal letter, 2 pg. response letter, and two copies of the following pages: A0.0, A1.0, A2.0, A3.0, A4.0, P1.0; taken to Dan Stuart
|
Telephone call | | | 2/6/2007 | | DONE |
|
|
|
Received phone call from Matt Rhees, architect, stating that resubmittals for plan changes made by tenant will be submitted next week.
|
Plan Reviewer's activity | | | 1/30/2007 | | DONE |
|
|
|
Received e-mail notice from Matt Rhees, architect for Idaho Sleep Center, notifying me the project has been put on hold pending redeisgn of the tenant floor plan layout.
|
1st review completed | | | 1/30/2007 | | FAIL |
|
|
|
Failed fire.
|
Routing - FIRE | 1/29/2007 | | 1/30/2007 | | FAIL |
|
|
|
Faxed resubmittal items to architect. Attached review comments to plans.
|
Plan resubmittals requested | | | 1/29/2007 | | DONE |
|
|
|
Faxed copy of review to architect for response.
|
Routing - PLAN CHECK | 1/18/2007 | | 1/29/2007 | | FAIL |
|
|
|
Resubmittals required. Copy of plan review faxed to Matt Rhees, architect. Routing plans to fire code analyst for review.
|
Routing - PLUMBING | 1/10/2007 | | 1/18/2007 | | PASS |
|
|
|
120 deg. max hot water to public lavs. max. 3 fixture units on 1/2" water lines. 1 1/4" min. cold water. shell shows an existing 1 1/2" SERVICE.
|
Routing - PUBLIC WORKS | 1/9/2007 | | 1/10/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 1/4/2007 | | 1/9/2007 | | DONE |
|
|
|
1/9/2007 11:36:37 MYS - activity updated through activity BLDA168 from case BLD07-00014.
|
Plans ACCEPTED BY PLAN TECH | | | 1/5/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/5/2007 | | |
|
|
|
|
Application received | | | 1/4/2007 | | |
|
|
|
|