Third Notice BLD | 6/21/2007 | 6/21/2007 | 10/1/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/25/2007 | 5/25/2007 | 6/21/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/11/2007 | 5/25/2007 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/11/2007 | 5/11/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/11/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11585 issued 5-11-07 to Andrade's.
|
BLD-Final | 5/8/2007 | 5/9/2007 | 5/9/2007 | P | PASS |
Tom Arcoraci
|
|
|
javier; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
FIRE-Final Inspection | 5/8/2007 | 5/9/2007 | 5/9/2007 | A | PASS |
Troy Cobbley
|
|
|
life safety has been passed.
|
FIRE-Final Inspection | 5/7/2007 | 5/8/2007 | 5/9/2007 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Conference | 4/27/2007 | 4/27/2007 | 4/27/2007 | P | PASS |
Tom Arcoraci
|
|
|
Javier Andrade ###-####
|
Inspection Record Card- Bld | | | 4/27/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/27/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/27/2007 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/21/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/20/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/20/2007 | | DONE |
|
|
|
t/c w amber at patrick mckeegan architects - ###-#### - permit ready and fees given - need gc and rce#
|
Permit Ready to Issue | | | 2/20/2007 | | |
|
|
|
|
Plan assigned to (R_H) | 1/12/2007 | | 2/16/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/16/2007 | | |
|
|
|
rec'd response letter from patrick mckeegan architects - 2 sets of sheet #s A1.2, A1.3 - taken to ron hill
|
Case Summary (BLD) | | | 2/16/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/14/2007 | | 2/15/2007 | | FAIL |
|
|
|
Reviewed resubmittals, called and talked to architect on additional information required, faxed corrections list to architect at 3:00 pm on thursday.
|
Plan resubmittals received | | | 2/15/2007 | | |
|
|
|
rec'd response letter from Patrick McKeegan Architects - copy of letter from Robert Peters Engineering to McKeegan Architects - structural calculations - 2 sets of sheet #s A1.1, A1.2, A1.3
|
Routing - FIRE | 2/8/2007 | | 2/14/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
1st review completed | | | 2/14/2007 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 2/8/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/26/2007 | | 2/8/2007 | | FAIL |
|
|
|
Faxed and mailed requirements to the architect and routed plans to the fire department for review.
|
Routing - PLANNING | 1/25/2007 | | 1/26/2007 | | PASS |
|
|
|
Tenant Improvement to an existing restaurant building in a C-2D zone.
|
Routing - PLUMBING | 1/16/2007 | | 1/25/2007 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 1/12/2007 | | 1/16/2007 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 1/16/2007 | | 1/16/2007 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Pending Assignment by MYS | 1/8/2007 | | 1/12/2007 | | DONE |
|
|
|
1/12/2007 12:16:40 MYS - activity updated through activity BLDA175 from case BLD07-00049.
|
Plans ACCEPTED BY PLAN TECH | | | 1/8/2007 | | |
|
|
|
|
Application received | | | 1/5/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/5/2007 | | |
|
|
|
|