Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-00111
StatusFinaled
Name IDAHO TRUST NATIONAL BANK
Site Address 777 W BROAD ST
Project NameBODO BLDG #8
Customer Number 
ePlanReviewNo
Description
**(IDAHO TRUST NATIONAL BANK - BODO BLDG #8) To construct a 372 sq.ft. space for bank storage and indoor ATM lobby per approved plans & DRH06-00497. Work to include, construction of a new glass storefront and new attached awning, construction of a new partition, installation of ATM Machines, installation of new ceiling and lighting, and miscellaneous related finishes. This building is fully fire sprinkled any alterations or modifications to the sprinkler system shall be per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  6/13/2007  
Letter of Compliance issued 6-13-07 per Dave Hannah.
BLD-Final5/22/20075/22/20075/23/2007PPASS
DetailsDave Hannah
kerry - please call for access ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for perm occ
FIRE-Final Inspection5/22/20075/22/20075/22/2007PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Framing/Rough-in3/28/20073/29/20073/29/2007PPASS
DetailsDave Hannah
steve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok to cover
BLD-Framing/Rough-in3/19/20073/19/20073/19/2007PFAIL
DetailsDave Hannah
eve ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs weling sign off and patch fire proofing
Print Occupancy Form  3/7/2007 DONE
CHANGE STATUS TO (RDY)  3/7/2007 DONE
Telephone call  3/7/2007 DONE
Called Elizabeth permit ready and fee given Need G.C. and RCE # ///DLD
Issue PAID IN FULL permit  3/7/2007 DONE
Routing - PLAN CHECK2/25/2007 3/6/2007 PASS
Plan resubmittals received  3/6/2007  
received letter from the architects office & (7) pages each from idaho trust national bank canopy calcs--"3" sets of plans with (2) each sheet of A1.O & A3.O--plans taken to ron hill
Case Summary (BLD)  3/6/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/6/2007 DONE
Plan assigned to (R_H)1/16/2007 3/6/2007 PASS
3/6/2007 13:48:21 RMH - activity updated through activity BLDA022 from case BLD07-00111.
Routing - FIRE2/20/2007 2/25/2007 PASS
Attached review comments to plans.
1st review completed  2/25/2007 FAIL
Case Summary (BLD)  2/20/2007 DONE
Routing - PLAN CHECK1/18/2007 2/20/2007 FAIL
Faxed and Mailed requirements to the architect, 2/20/07 routed plans to fire.
Routing - PUBLIC WORKS1/16/2007 1/18/2007 PASS
Routing - PLANNING1/18/2007 1/18/2007 PASS
Josh Wilson DRH06-00497
Pending Assignment by MYS1/11/2007 1/16/2007 DONE
1/16/2007 10:48:13 MYS - activity updated through activity BLDA175 from case BLD07-00111.
Plans ACCEPTED BY PLAN TECH  1/11/2007  
Application received  1/11/2007