BLD-Final | 9/13/2007 | 9/14/2007 | 9/14/2007 | A | PASS |
Jim Storey
|
|
|
aaron Phone #: ###-####
|
DOC - Permit Finaled | 9/14/2007 | 9/14/2007 | 9/14/2007 | P | PASS |
Jim Storey
|
|
|
|
BLD-Grading Inspection | 9/13/2007 | 9/13/2007 | 9/13/2007 | | DONE |
|
|
|
final grading and drainage approved
|
BLD-Final | 8/27/2007 | 8/28/2007 | 8/28/2007 | A | NR |
Mike Jordan
|
|
|
Aaron; Phone #: ###-#### Internet Inspection Request from: Hattie James. Needs public works.
|
FIRE-Final Inspection | 5/24/2007 | 5/29/2007 | 5/29/2007 | A | NH |
Jim Storey
|
|
|
aaron - fire life safety ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Energy code compliance | 5/29/2007 | 5/29/2007 | 5/29/2007 | P | PASS |
Jim Storey
|
|
|
aaron - fire life safety ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PASS |
Jim Storey
|
|
|
aaron; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Foundation | 4/10/2007 | 4/12/2007 | 4/12/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/10/2007 at 7:22:59 PM. Contact: ###-####.
|
BLD-Footing | 4/10/2007 | 4/11/2007 | 4/11/2007 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/10/2007 at 7:22:39 PM. Contact: ###-####.
|
BLD-Footing | 3/26/2007 | 3/27/2007 | 3/27/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/26/2007 at 5:39:21 PM. Contact: ###-####. wall back of lot ok
|
BLD-Footing | 3/23/2007 | 3/23/2007 | 3/23/2007 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/23/2007 at 7:56:58 AM. Contact: ###-####.
|
BLD-Foundation | 3/21/2007 | 3/23/2007 | 3/23/2007 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/21/2007 at 6:21:31 AM. Contact: ###-####.ft for back retaining wall ok
|
BLD-Footing | 3/21/2007 | 3/21/2007 | 3/21/2007 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/21/2007 at 7:07:30 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Mar 21 2007 10:44AM.
|
BLD-Footing | 3/21/2007 | 3/21/2007 | 3/21/2007 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/21/2007 at 6:20:37 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Mar 21 2007 8:13AM.
|
PubWorks Subgrade Approval | 3/20/2007 | 3/20/2007 | 3/20/2007 | | PART |
|
|
|
SUBGRADE FOR RETAINING WALL FOOTING IS APPROVED BY THE GEOTECHNICAL ENGINEER
|
BLD-Footing | 3/9/2007 | 3/9/2007 | 3/9/2007 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/9/2007 at 9:34:03 AM. Contact: ###-####.
|
PubWorks Subgrade Approval | 3/9/2007 | 3/9/2007 | 3/9/2007 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 3/6/2007 | | |
|
|
|
|
Plan assigned to (SRZ) | 2/28/2007 | 2/28/2007 | 2/28/2007 | | PASS |
|
|
|
2/28/2007 15:32:12 SRZ - activity updated through activity BLDA022 from case BLD07-00112.
|
Case Summary (BLD) | | | 2/28/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/28/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/28/2007 | | DONE |
|
|
|
left vm for aaron mcgee at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/28/2007 | | |
|
|
|
|
Pending Assignment by SRZ | 1/12/2007 | | 2/28/2007 | | DONE |
|
|
|
2/28/2007 15:02:43 SRZ - activity updated through activity BLDA160 from case BLD07-00112.
|
Routing - PLAN CHECK | | | 2/28/2007 | | PASS |
|
|
|
|
Telephone call | | | 2/22/2007 | | DONE |
|
|
|
shane called and asked about time frame.
|
Routing - Erosion and Sediment | 1/17/2007 | | 1/18/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 1/18/2007 | | 1/18/2007 | | PASS |
|
|
|
No fire sprinklers are required. (No info from FD on this sub)
|
Routing - PLANNING | 1/17/2007 | | 1/17/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 1/17/2007 | | 1/17/2007 | | PASS |
|
|
|
|
Routing - PLANNING | 1/12/2007 | | 1/17/2007 | | PASS |
|
|
|
Routed to T.R. - Hillside
|
Routing - PUBLIC WORKS GRADING | 1/16/2007 | | 1/16/2007 | | PASS |
|
|
|
Approved as category 3
|
Routing - Addressing | 1/12/2007 | | 1/12/2007 | | PASS |
|
|
|
|
Application received | | | 1/12/2007 | | |
|
|
|
|