Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-00143
StatusFinaled
Name IND SCHOOL DIST OF BOISE CITY
Site Address 6411 W FAIRFIELD AVE
Project NameMcKinley Elementary School
Customer Number 
ePlanReviewNo
Description
(MCKINLEY ELEMENTARY SCHOOL) To construct a 59,007 sq ft one story type IIIB fully fire sprinkled elementary school. Other work includes site prep paving and landscaping with trash enclosure and storeroom. CUP06-00087. Separate permits required for demolition of the existing school building on the site. Fire sprinklers used for area. (MLO)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 10/12/200910/22/2009 DONE
faxed and mailed to school dist. attn: Chris Wendrowski
Telephone call  10/22/2009 DONE
DetailsTisha Gallop
left voice message for Chris Wendrowski need final values
Third Notice 9/8/200910/2/2009 DONE
faxed to School Dist. attn:Chris Wendrowski
Telephone call  10/2/2009 DONE
DetailsTisha Gallop
called and spoke with Dave/Kreizenbeck Const. he said should send to school district Chris Wendrowski because they kept track of all the fees.
Third Notice 8/11/20099/8/2009 DONE
Second Notice 7/22/20098/11/2009 DONE
First Notice 7/7/20097/22/2009 DONE
Routing for occupancy7/7/20097/7/20097/7/2009 DONE
DetailsBarbara Stitt
Verified with Mike Meloy for Code Enforcement, Tiffany Lowery with Public Works, Troy Cobbley with Fire, Tom Arcoraci with Building Department that all issues are resolved and has been approved for permanent certificate of occupancy///7-7-09 BAS
Permanent Occupancy UNPAID FEE  7/7/2009 DONE
DetailsBarbara Stitt
BLD-Aging Inspection6/24/20096/24/20096/25/2009 PASS
DetailsWm. Michael Meloy
Compliance met with landscaping.
BLD-Conference6/24/20096/24/20096/24/2009PPASS
DetailsTom Arcoraci
ok needs landscape signed off
BLD-Final4/24/20094/24/20094/24/2009PPASS
DetailsTom Arcoraci
ok for perm when landscape is signed off
Temporary Occupancy1/29/20094/29/20091/29/2009 DONE
DetailsBarbara Stitt
Temp occupancy extendend per Jenifer see scanned email///1-29-09 BAS
BLD-Aging Inspection1/19/20091/19/20091/26/2009 PASS
DetailsTroy Cobbley
Life safety passed
BLD-Aging Inspection11/17/200811/17/200811/17/2008 PASS
DetailsTom Arcoraci
Temporary Occupancy UNPAID FEE  10/29/2008 DONE
DetailsBarbara Stitt
PubWorks Occupancy Approval9/29/20089/29/20089/29/2008 DONE
DetailsTiffany Lowery
FIRE-Final Inspection9/17/20089/17/20089/18/2008PPASS
DetailsTroy Cobbley
LIfe safety passed.
Temporary Occupancy7/25/200810/23/20087/25/2008 DONE
DetailsBarbara Stitt
BLD-Final7/22/20087/23/20087/23/2008APART
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Mike Shain ok for temp cn posted
FIRE-Final Inspection6/4/20086/5/20086/5/2008ACANC
DetailsTroy Cobbley
Duplicate inspection.
FIRE-Final Inspection6/4/20086/5/20086/5/2008APART
DetailsTroy Cobbley
A temporary occupancy was given with Mark Sentenno's permission until the existing school has been demo'd and the new door hardware has been verified.
FIRE-Final Inspection5/30/20086/2/20086/2/2008PFAIL
DetailsTroy Cobbley
Provide the missing exit sign in the daycare room and repair the inoperative exit sign in the daycare. Provide an additional emergency light in the multipurpose room as discussed. Will also need the door hardware verified at the final inspection after it has been installed.
FIRE-Final Inspection5/28/20085/30/20085/30/2008AFAIL
DetailsTroy Cobbley
The hood suppression system permit needs to be finaled. Fire extinguisher placement is acceptable. The tumblers in all of the doors had not been installed yet so door operation could not be verified. Also the exit signs and emergency lighting still needs to be verified.
Code Occupancy Approval Temp  5/29/2008 PART
DetailsWm. Michael Meloy
Temp Occupancy is approved for only the newly constructed school. Additional work needs to be done, but cannot be completed until the old school is demolished.
FIRE-Hydro test above ground5/20/20085/21/20085/21/2008ACANC
DetailsTroy Cobbley
Wrong inspection type called in.
FIRE-Alarm Testing5/20/20085/21/20085/21/2008ADONE
DetailsTroy Cobbley
See the related fire alarm permit for notes
FIRE-Alarm Testing5/19/20085/20/20085/20/2008AFAIL
DetailsTroy Cobbley
No inspection was performed due to the DACT not reporting telephone troubles to the monitoring station and not annunciating at the site.
BLD-Conference4/10/20084/10/20084/10/2008PPASS
DetailsTom Arcoraci
ceiling cover area B Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Other3/20/20083/20/20083/20/2008PPASS
DetailsTom Arcoraci
Need ok to drop ceiling tile Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Other3/11/20083/11/20083/11/2008PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in3/6/20083/6/20083/6/2008PPASS
DetailsTom Arcoraci
BLD-Conference3/3/20083/3/20083/3/2008PPASS
DetailsTom Arcoraci
FIRE-Sprinkler Rough-in2/27/20082/28/20082/28/2008APASS
DetailsTroy Cobbley
The enclosed space that has been stuffed with insulation on both sides of the main entrance can be covered.
BLD-Wall cover2/26/20082/26/20082/26/2008PPASS
DetailsTom Arcoraci
BLD-Conference2/25/20082/26/20082/26/2008APASS
DetailsTom Arcoraci
BLD-Conference2/20/20082/21/20082/21/2008PPASS
DetailsTom Arcoraci
lee rice and jim johnson are requesting meeting with you in attendance at mckinley site to go over code issues regarding ADA compliance need a time that works for you Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Wall cover1/22/20081/23/20081/23/2008PPASS
DetailsMike Jordan
Wall cover admin. area Phone #: ###-#### Internet Inspection Request from: Mike Shain. Interior steel stud framed walls for cetral core area (Amin).
BLD-Wall cover1/21/20081/22/20081/22/2008PCANC
DetailsJim Storey
Wall cover administration area Phone #: ###-#### Internet Inspection Request from: Mike Shain Inspection cancelled from web by: Mike Shain
BLD-Framing/Rough-in12/31/20071/2/20081/2/2008PPASS
DetailsTom Arcoraci
Framing area A and C Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Conference12/31/20071/2/20081/2/2008PPASS
DetailsTom Arcoraci
Roof nailing area B Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Framing/Rough-in12/17/200712/18/200712/18/2007APASS
DetailsTom Arcoraci
roof nailing area C Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Framing/Rough-in11/20/200711/21/200711/21/2007APASS
DetailsTom Arcoraci
Roof nailing inspection area A Phone #: ###-#### Internet Inspection Request from: Mike Shain wip ok
BLD-Footing10/9/200710/10/200710/10/2007APASS
DetailsTom Arcoraci
special insp. onsite concrete 10:00am ###-#### Internet Inspection Request from: Mike Shain wip
BLD-Concrete9/25/20079/26/20079/26/2007APASS
DetailsTom Arcoraci
Masonry reinforcing special inspector on site Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Concrete9/14/20079/17/20079/17/2007APASS
DetailsTom Arcoraci
Masonry reinforcing 10:30 am grout Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Aging Inspection9/14/20079/14/20079/14/2007 NR
DetailsTom Arcoraci
BLD-Foundation7/10/20077/12/20077/12/2007PPART
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Footing7/2/20077/3/20077/3/2007APART
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Mike Shain spec insp
BLD-Footing6/25/20076/26/20076/26/2007APART
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Mike Shain
BLD-Footing6/19/20076/20/20076/20/2007PPART
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Mike Shain strata on site
(F) Reprint permit  5/22/2007  
Issue PAID IN FULL permit  5/21/2007 DONE
Print Occupancy Form  4/11/2007 DONE
Telephone call  4/11/2007 DONE
t/c w nancy at kreizenbeck constructors ###-#### - permit ready and fees given - also need ACHD - RP license has expired
Permit Ready to Issue  4/11/2007  
Routing - PLAN CHECK4/2/2007 4/10/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  4/10/2007 DONE
Plan assigned to (MLO)1/17/2007 4/10/2007 PASS
4/10/2007 15:16:14 MYS - activity updated through activity BLDA022 from case BLD07-00143.
Routing - PUBLIC WORKS3/30/2007 4/2/2007 PASS
Routing - PLANNING3/28/2007 3/29/2007 PASS
Plans indicate compliance with conditions of CUP.
Plan resubmittals received  3/29/2007 DONE
Received 1 letter of transmittal, and 2 copys of sheet A2.04 taken to Mike Otto
Routing - FIRE3/29/2007 3/29/2007 PASS
Attached updated review comments to plans.
Routing - FIRE3/23/2007 3/27/2007 FAIL
Emailed and faxed resubmittal item to architect. Inserted updated review comments to plans.
Routing - PLAN CHECK3/22/2007 3/23/2007 PASS
Plan resubmittals received  3/21/2007  
Received 1 Cover transmittal, 2 copies of response letter (2pgs) from Hummel Architects, 2 copies of door hardware info pgs 087100-18, 1 copy of 087100-19, 087100-20, 087100-21, 087100-21, 087100-22, 087100-23, 087100-24, 087100-25, 087100-26, 087100-27, 087100-28, 087100-29, 2 copies of 087100-31, 1 copy of 087100-30, lock levers info, 1 copy(4pgs) of parking agreement, 4 copies of sheets L-1, A1.01, A1.02, A20.3, A5.00, A8.01, M1.1, M1.2, P1.2, P2.2, E2.01L, E2.02F, E2.02L, E2.02P, E2.02S, E2.03L, 3 copies of easch sheet- A0.10, A1.01, A2.03, A2.04, A2.22, C4.01A, C4.02A and taken to Mike Otto
Routing Off Site - STRUCTURAL3/16/2007 3/20/2007 PASS
plans sent to outside engineers for pickup per mike otto
Plan resubmittals received  3/8/2007  
Received transmittal sheet, 1pg. joist loads, three copies of the following: 2pg. response letter, 1pg. Boise City Structural Review Comments, Supplemental Calculations, S0.1, S1.02, S1.02A, S1.02C, S2.02, S6.04; taken to Mike Otto
Routing - FIRE3/2/2007 3/7/2007 FAIL
Emailed resubmittal comments to architect.
1st review completed  3/7/2007 FAIL
Routing Off Site - STRUCTURAL1/31/2007 3/2/2007 FAIL
corrections sent to architect
Plan resubmittals requested  3/2/2007 DONE
IBC corrections
Routing - PLAN CHECK2/14/2007 3/2/2007 FAIL
corrections sent to architect
Plan resubmittals received  2/14/2007  
rec'd transmittal letter - 4 sets of sheet # A2.03 - taken to Mike Otto
Routing - PLUMBING1/25/2007 1/30/2007 PASS
120 deg. max hot water to public lavs and hand sinks in the kitchen. add a hand sink by the 3 comp. sink per cdhd review. hub drains on the mezzanine may need to be primed.
Routing - PLANNING1/30/2007 1/30/2007 FAIL
Plans fail to comply with conditions of approval. Emailed necessary corrections to architect.
Plan resubmittals received  1/30/2007  
rec'd letter of transmittal, geotechnical engineering evaluation, 3 sets of sheet #s A4.01 - taken to Mike Otto
Routing - Erosion and Sediment1/25/2007 1/25/2007 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS1/22/2007 1/25/2007 FAIL
Inaccessible trash; Contact Pam Williams ###-####
Routing - PLANNING Land Div1/18/2007 1/22/2007 PASS
Parcel over 5 acres in size - OK per DA
Routing - PLANNING  1/22/2007 PASS
cup06-00087 cody riddle
Routing - Addressing1/22/2007 1/22/2007 PASS
Plan resubmittals received  1/19/2007  
received A1.O1, A1.O2, A1.O3 & A8.O5 & inserted in plans. called action courier for pickup on resubmittal plans & included (2)project manuels
Plan routing begun/NEW & ADDTN  1/18/2007  
Plans ACCEPTED BY PLAN TECH  1/18/2007 FAIL
Need 4 copies stamped & signed sheets, A1.01, A1.02, A1.03, A8.05. Called Margie @ Hummel to let her know///1/18/07 @10:00
Recd Pcfee & Taken To Pln CK  1/17/2007  
Telephone call  1/17/2007  
called action courier for pickup
Application received  1/17/2007  
Pending Assignment by MYS1/17/2007 1/17/2007 DONE
1/17/2007 14:33:44 JCM - activity updated through activity BLDA174 from case BLD07-00143.