Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/4/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/18/2008 | 8/11/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/18/2008 | | DONE |
|
|
|
|
BLD-Conference | 4/16/2008 | 4/17/2008 | 4/17/2008 | A | PEND |
Jim Sly
|
|
|
Talked to angie? at ###-####.......Contr. or owner may have failed to take signature card to the city and obtain C/O.......
|
BLD-Final | 4/15/2008 | 4/16/2008 | 4/16/2008 | A | CANC |
Jim Sly
|
|
|
Willy ###-####
|
BLD-Final | 4/15/2008 | 4/15/2008 | 4/15/2008 | P | CANC |
Jim Sly
|
|
|
Re-scheduled.......
|
BLD-Final | 5/16/2007 | 5/17/2007 | 5/17/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/16/2007 at 9:49:24 AM. Contact: ###-####. OK for Perm Occ.
|
FIRE-Final Inspection | 5/16/2007 | 5/17/2007 | 5/17/2007 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Energy code compliance | 3/30/2007 | 4/2/2007 | 4/2/2007 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/30/2007 at 3:29:20 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/28/2007 | 3/29/2007 | 3/29/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/28/2007 at 1:26:08 PM. Contact: ###-####.
|
Print Occupancy Form | | | 3/22/2007 | | DONE |
|
|
|
|
Telephone call | | | 3/22/2007 | | DONE |
|
|
|
left vm for willy at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/22/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/22/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2007 | | |
|
|
|
|
Routing - PLAN CHECK | 3/5/2007 | | 3/20/2007 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan assigned to (CJW) | 1/30/2007 | | 3/20/2007 | | PASS |
|
|
|
3/20/2007 15:18:59 CJW - activity updated through activity BLDA022 from case BLD07-00181.
|
Plan resubmittals received | | | 3/8/2007 | | |
|
|
|
Received 1 cover transmittal, and 2 copies of H1.0 and taken to Carl Westfall
|
Routing - FIRE | 2/28/2007 | | 3/5/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
1st review completed | | | 3/5/2007 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PLAN CHECK | 1/31/2007 | | 2/28/2007 | | FAIL |
|
|
|
The IBC plan review was started on Feb. 23, 2007 and was finished on Feb. 28, 2007. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 1/30/2007 | | 1/31/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 1/22/2007 | | 1/30/2007 | | DONE |
|
|
|
1/30/2007 15:59:22 MYS - activity updated through activity BLDA172 from case BLD07-00181.
|
Plans ACCEPTED BY PLAN TECH | | | 1/24/2007 | | DONE |
|
|
|
|
Application received | | | 1/22/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/22/2007 | | DONE |
|
|
|
|