Case Summary (BLD) | | | 2/7/2008 | | DONE |
|
|
|
|
Second Notice BLD | 7/5/2007 | 7/5/2007 | 7/17/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/20/2007 | 7/5/2007 | | DONE |
|
|
|
|
BLD-Final | 6/20/2007 | 6/20/2007 | 6/20/2007 | P | PASS |
Jim Storey
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
Permanent Occupancy | | 6/20/2007 | 6/20/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/20/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11672 issued 6-20-07 to Papa Murphy's in Vista Village.
|
FIRE-Final Inspection | 6/19/2007 | 6/19/2007 | 6/19/2007 | P | PASS |
Forrest France
|
|
|
One emergency light repaired while on site, the provided PFE attatched as agreed, fire life safety inspection passed.
|
BLD-Framing/Rough-in | 5/8/2007 | 5/8/2007 | 5/8/2007 | P | PASS |
Jim Storey
|
|
|
dennis ; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Framing/Rough-in | 5/7/2007 | 5/7/2007 | 5/7/2007 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/7/2007 at 7:04:47 AM. Contact: ###-####. no access
|
BLD-Framing/Rough-in | 4/17/2007 | 4/18/2007 | 4/18/2007 | A | PART |
Jim Storey
|
|
|
Dennis; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
Issue PAID IN FULL permit | | | 4/16/2007 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/18/2007 | | 4/13/2007 | | PASS |
|
|
|
4/13/2007 10:33:31 CJW - activity updated through activity BLDA022 from case BLD07-00317.
|
Routing - PLAN CHECK | 3/27/2007 | | 4/13/2007 | | PASS |
|
|
|
Completed the resubmittal review. Drawings approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/13/2007 | | |
|
|
|
|
Telephone call | | | 4/13/2007 | | DONE |
|
|
|
t/c w dennis harmon at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/13/2007 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/6/2007 | | |
|
|
|
received "3" plan review reports (7) pages each & "3" sets of plans each sheet --index sheet, AS1.2, AO, A1, A1.1, A2, A2.3, A3, A4, EQ1, P1, E1, & E2--plans taken to Carl Westfall
|
1st review completed | | | 3/27/2007 | | FAIL |
|
|
|
Failed plan check.
|
Routing - FIRE | 3/23/2007 | | 3/27/2007 | | PASS |
|
|
|
Attached IFC review comments to plans.
|
Routing - PLAN CHECK | 2/26/2007 | | 3/23/2007 | | FAIL |
|
|
|
The IBC plan review was started on March 22, 2007 and was finished the next day. Revised drawings were required. See the plan review report.
|
Telephone call | | | 3/23/2007 | | DONE |
|
|
|
Called the owner to get his Architect's E-mail address.
|
Routing - PLUMBING | 2/20/2007 | | 2/26/2007 | | PASS |
|
|
|
ADD HAND SINK PER CDHD NOTE PAGE P1, FLOOR SINK FOR WALK IN COOLER CONDENSATE MUST BE PROVIDED WITH A FUNNEL. PROVIDE A FLOOR SINK AT THE 3- COMPARTMENT SINK 3" MIN. DRAIN.
|
Routing - PUBLIC WORKS | 2/18/2007 | | 2/20/2007 | | PASS |
|
|
|
|
Pending Assignment by MYS | 2/13/2007 | | 2/18/2007 | | DONE |
|
|
|
2/18/2007 12:22:56 MYS - activity updated through activity BLDA172 from case BLD07-00317.
|
Plans ACCEPTED BY PLAN TECH | | | 2/13/2007 | | |
|
|
|
3 sets of plans brought back with CDH signatures
|
Telephone call | | | 2/7/2007 | | |
|
|
|
called Dennis Harmon ###-#### and told him need to pick up plans per need CDHD stamp and sign every set of plans before can submit, also need 3 sets of plans. He said will come down to pick them up
|
Application received | | | 2/6/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/6/2007 | | DONE |
|
|
|
|