Permit Information
Permit NumberBLD07-00349
StatusFinaled
Name WILLIAM SMITH
Site Address 6401 S EISENMAN RD
Project NameQUARRY BUSINESS PARK CONDOS
Customer Number 
ePlanReviewNo
Description
Gowen Group Warehouse/Office shell building. Grading and Drainage Permit submitted under BLD07-00289. To construct a 20,268 sq. ft. one story Type V-B fully fire sprinklered office/warehouse shell building. Other work includes site finish work and landscaping per approved plans, CUP06-00039, DRH06-00277. Fire sprinklers used for area. No Occupancy is authorized by this permit. Separate plans and permits for each tenant space are required. Fire sprinklers are regulated by Boise Fire. A verification of adequacy letter and new engineering detail for the rock retaining walls are to be provided by the structural design engineer to the Building Inspector.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/11/200712/11/200712/26/2007 DONE
Second Notice has not been responded to.
Second Notice BLD11/13/200711/13/200712/11/2007 DONE
First Notice has not been responded to.
First Notice11/2/200711/2/200711/13/2007 DONE
DetailsJim Storey
FIRE-Final Inspection11/1/200711/2/200711/2/2007APASS
DetailsForrest France
Necessary corrections have been completed, fire life safety inspection passed.
BLD-Final11/1/200711/2/200711/2/2007APASS
DetailsJim Storey
bob Phone #: ###-####
DOC - Permit Finaled11/2/200711/2/200711/2/2007PPASS
DetailsJim Storey
BLD-Final10/16/200710/17/200710/17/2007PPART
DetailsJim Storey
SMITH Phone #: ###-#### ok pending fire foe riser rm const. as noted .
BLD-Final10/17/200710/17/200710/17/2007PPASS
DetailsJim Storey
Bob Phone #: ###-#### temp
FIRE-Final Inspection10/17/200710/18/200710/17/2007APART
DetailsTroy Cobbley
A temporary occupancy is being issued with sam rogers permission until the room at the riser and facp is constructed within the next 60 days.
Code Occupancy Approval10/12/200710/12/200710/12/2007PPASS
DetailsJoe R Venneman
Meets requirements of BLD07-0349
Code Occupancy Approval  10/12/2007 DONE
BLD-Final10/8/200710/9/200710/11/2007PCANC
DetailsJim Storey
bob Phone #: ###-####
BLD-Final10/11/200710/11/200710/11/2007PCANC
DetailsJim Storey
william Phone #: ###-####
FIRE-Final Inspection10/8/200710/9/200710/9/2007AFAIL
DetailsForrest France
Missing fire dept. access marking, need to final fire sprinkler permit, need to provide dust control at the vicinity of the FACP as promised.
BLD-Conference9/27/200710/1/200710/1/2007APASS
DetailsJim Storey
bill Phone #: ###-####
Meeting  9/27/2007 DONE
Onsite meeting with Bob Smith at his request, to discuss lack of sprinklers in two large "over-build" roof areas. Observed concrete floor being poured as required by Fire Marshal between exterior door and sprinkler riser/FAC panel area, which is not to be enclosed at this shell stage. The "overbuild" areas definitely require sprinklers, neither area was shown on sprinkler drawings and they were not reported by sprinkler installer; deficiency was discovered by Fire inspector at 1st sprinkler rough-in inpection on 9/25/07. Suggested providing antifreeze protection in the overbuild areas or possibly installing insulation at roof deck and creating sufficient openings in the lower OSB boards to allow adequate heat into the area for wet sprinklers. I expressed concern that heat may not be adequate after suspended ceilings are installed which will further restrict heat migration into the upper level overbuild areas, so it may require supplemental heating. If wet sprinklers are installed, we would need to have low temp monitoring within those overbuild spaces, monitored by the fire alarm system. I subsequently called sprinkler contracotr and learned they are already looking into both design options with the building contractor and truss manufacturere; I repeated my concern that heat may not be adequate, especially after suspended ceilings are installed which will further restrict heat migrating into these upper level overbuild areas, and supplemental heating may bwe required but the contractor did not feel that would be a problem. I pointed out if wet sprinklers are used, we will need to have low temp monitoring of teh overbuild space by the fire alarm system.
FIRE-Conference9/6/20079/10/20079/10/2007PDONE
DetailsForrest France
On site conference regarding general contractors intent to pursue a temporary occupancy approval. Noted no fire alarm permit work inspections have been requested or performed to date, also no overhead fire sprinkler rough-in inspections for the AG system have been done or scheduled except for two concealed spaces at two roof dormers, informed GC that TCO's are only approved with the permission of the fire chief.
FIRE-Conference8/28/20078/30/20079/6/2007ADEFR
DetailsForrest France
william Phone #: ###-####
Plan resubmittals received  8/28/2007 DONE
Resubmitted Landscape Plan sheet L3.0 submitted and approved by Sarah Schafer in Design Review Planning. A copy will be made available in the job site approved plans and a copy will be scanned in under the this BLD in Records. A copy is also in the DR file.
FIRE-Final Inspection8/16/20078/17/20078/17/2007APART
DetailsForrest France
Inspection site visit intended for a conference regarding knox box locations and fire sprinkler permit rough-in inspection for sprinklers at the first two roof dormers due to access issues.
BLD-Energy code compliance8/10/20078/10/20078/10/2007PPART
DetailsJim Storey
bill - insulation Phone #: ###-#### north space ok
Plan resubmittals received  8/6/2007  
Received deferred submittal; two copies of page A4.2; taken to Marlene S.
8/8/07 - Permit is issued. Gave resubmittals to Jim Storey. (msouthard)
BLD-Energy code compliance7/27/20077/27/20077/27/2007PPART
DetailsJim Storey
william - insulation Phone #: ###-#### ok to cover walls.
BLD-Conference7/25/20077/25/20077/25/2007PPASS
DetailsJim Storey
bob; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang conf.
Meeting  7/16/2007 DONE
Meeting held today with Bryan Johnson, Sam Rogers and Jason Blais, and Matt Kahn, sprinkler designer, at request of sprinkler designer to discuss field modifications of the building shell, which affect the sprinkler design. The building has been built without ceilings and the insulation has been installed on underside of the roof deck. (The approved plans show ceilings and insulation directly on the ceiling). The project manager, Jason Blais, will advise the contractor, Bob Smith, of the need to obtain Building Dept approval for the field modification to the shell building energy envelope. The sprinkler system will be designed with wet sprinklers at the roof level designed for light hazard and will have capped drops for future sprinklers (below future ceilings) capable of protecting high piled storage of Class IV commodities on racks storage to 15' high with in-rack sprinklers. (Max clear height to bottom of trusses is 18'). Any future tenant high piled storage will require a flat ceiling to be installed for adequate sprinkler design. It will be the responsibility of any future tenants who install ceilings, to provide an approved means of maintaining their attic space above 40F.
BLD-Other7/13/20077/13/20077/13/2007PDONE
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/11/2007 at 8:57:23 AM. Contact: ###-####.
Plan resubmittals received  6/29/2007 DONE
Concrete retaining wall portion has now changed to CMU design. Updated detail is attached to this case under "Documents" and a copy will be provided to Records.
BLD-Conference6/25/20076/25/20076/25/2007PPART
DetailsJim Storey
bill Phone #: ###-#### north end of roof diaphram ok for cover / need to verify draft stop at eaves.
(F) Reprint permit  5/30/2007  
BLD-Conference5/23/20075/24/20075/24/2007APASS
DetailsJim Storey
BOB; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
(F) Reprint permit  4/24/2007  
Plan assigned to (MLO)2/12/2007 4/23/2007 PASS
4/23/2007 08:16:47 JCB - activity updated through activity BLDA022 from case BLD07-00349.
Routing - PLANNING3/30/2007 4/23/2007 PASS
Plans approved per DRH06-00277, DRH07-00136, and attached red marks.
Routing - PLAN CHECK4/18/2007 4/23/2007 PASS
Mike Otto has left employment at the City. As Project Manager, Jason is issuing based on all approvals passing. Plans and Permit taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  4/23/2007 PASS
Inspection Record Card- Bld  4/23/2007 DONE
Telephone call  4/23/2007 DONE
called bob smith ###-#### and told him permit is ready, fees and need ACHD receipt
Permit Ready to Issue  4/23/2007 DONE
Issue PAID IN FULL permit  4/23/2007 DONE
Routing - FIRE3/28/2007 3/29/2007 PASS
Attached updated review comments to plans.
Routing - PUBLIC WORKS3/22/2007 3/27/2007 PASS
Plan resubmittals received  3/22/2007  
Received 3 copies of 5g. Site concrete retaining wall info and calculations, and two copies of pages C1.0, C2.0, C3.0, C4.0, C5.0, C6.0, L1.0; took to Mike Otto
1st review completed  3/14/2007 FAIL
Failed planning and fire.
Routing - FIRE3/8/2007 3/13/2007 FAIL
Attached IFC review comments to plans. Emailed MDT pilot project manager to discuss resubmittal item. Sent resubmittal items to architect for review.
Routing Off Site - STRUCTURAL2/12/2007 3/8/2007 PASS
Routing - PLAN CHECK2/28/2007 3/8/2007 PASS
Plans approved.

All resubmittal plans and documents attached for issuance.
Case Summary (BLD)  3/8/2007  
Meeting  3/8/2007  
Staff is aware of a change to the building set, not previously approved through the Design Review submittal. The applicant has added a 9' tall wall that is five feet thick.
Meeting  3/8/2007 DONE
Met with Building Official regarding 9 foot high rock retaining wall along east property line. Engineered design has been accepted by Building Official.
Telephone call  3/8/2007 DONE
Phone call with Kolby Orcher on the design of the rock retaining wall. As part of the building permit, the City will require him to witness installation and provide a written letter of verification for adequacy for the installation of the wall prior to final of the shell building.
Routing Off Site - STRUCTURAL3/1/2007 3/6/2007 PASS
Called action Courier for pick up on 3//1/07 at 8:55am BAS Rock retaining wall and calculations.
Plan resubmittals received  3/6/2007 DONE
Received 3 copies of A0.0, A2.1, A3.1, A4.1, A4.2, A4.3 and taken to Mike Otto
Plan resubmittals received  2/28/2007  
Received 4 copies of sheet C1.0 and 4 copies of retaining wall calcs and taken to Mike Otto
Telephone call  2/28/2007 DONE
called architect about plans and application having different types of construction which may or may not require fire rated construction. Architect informed me he would provide corrected plans asap for review.
Routing - PLANNING2/27/2007 2/28/2007 FAIL
Approved per DRH06-00277 and CUP06-00039

Building plan documents have changes since staff's original review. Applicant must submit a Design Review modification, obtain approval and comply with any conditions prior to Planning sign off.
Routing - PLUMBING2/21/2007 2/27/2007 PASS
per plans and 2003 upc
Routing - Erosion and Sediment2/16/2007 2/21/2007 PASS
Refer to ESC07-00131 --- ESC plan approved with attached conditions.
Routing - PUBLIC WORKS2/13/2007 2/16/2007 PASS
Routing - PLANNING Land Div2/12/2007 2/13/2007 PASS
Plan resubmittals received  2/13/2007 DONE
Resubmittal sheets A2.1 provided. Will add to shell plans routing.
Plan routing begun/NEW & ADDTN  2/12/2007  
Telephone call  2/12/2007  
called Bob Smith regarding 2 cert of values submitted, he said the one dated 2/8/07 is the correct one with the project value of $1,370,000.
Plans ACCEPTED BY PLAN TECH  2/12/2007  
Telephone call  2/12/2007 DONE
Called Action Couriers for pick up to outside engineering
Pending Assignment by MYS2/9/2007 2/12/2007 DONE
2/12/2007 11:57:39 JCM - activity updated through activity BLDA174 from case BLD07-00349.
Application received  2/9/2007  
Recd Pcfee & Taken To Pln CK  2/9/2007