Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-00427
StatusFinaled
Name LITZINGER CONSTRUCTION CO
Site Address 3301 W MURANO CT
Project NameMANDOLIN PARK 4 PLEX lot 2
Customer Number 
ePlanReviewNo
Description
Mandolin Park - Four-Plex Apartment - To construct a new 4,452 square feet, two story, four unit, apartment building. The first floor is 2,284 square feet, the second floor is 2,156 square feet. Each unit is two bedroom and two bath, with a 100 square feet covered patio at 1,068 square feet each. All construction shall be per the approved plans and attached comment list. NOTE: This building is not required to be fire sprinklered per B.C.C. 4-02-31. DRG05-00095 CUP05-00010
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD10/1/200710/1/200710/25/2007 DONE
This permit finaled on the web by Ken Litzinger
First Notice 9/7/200710/1/2007 DONE
BLD-Final9/6/20079/7/20079/7/2007APASS
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger per plan
FIRE-Final Inspection9/6/20079/7/20079/7/2007APASS
DetailsTroy Cobbley
Life safety passed. Contractor had a signed letter from dave hanniman for the fire hydrant relocation.
Permanent Occupancy  9/7/2007 DONE
Code Occupancy Approval9/6/20079/6/20079/6/2007PPASS
DetailsDena Gambrel
9-6-07 Final Occupancy Passed for this 4 plex.
FIRE-Final Inspection9/6/20079/6/20079/6/2007PCANC
DetailsTroy Cobbley
Overbooked
FIRE-Final Inspection9/4/20079/4/20079/4/2007PFAIL
DetailsTroy Cobbley
Provide verification that the hydrant that has been relocated from murano ct. to owhyee street is approved to be in the new location. Provide the "compact" parking striping for fire dept access verification. Remove covers from the fire extinguishers. Provide the apartment numbers. Set up the exit doors to close from a partially open position. Provide the missing smoke alarms outside of the bedroom as shown on the plans.
BLD-Energy code compliance7/20/20077/20/20077/20/2007PPASS
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Framing/Rough-in7/18/20077/18/20077/18/2007APASS
DetailsTom Arcoraci
Tom...please inspect later in the morning...hopefully everything is right this time...please call 1/2 hour before inspection...thanks Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Framing/Rough-in7/17/20077/17/20077/17/2007AFAIL
DetailsTom Arcoraci
Please call 1/2 hour before inspection....thanks Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Framing/Rough-in7/16/20077/16/20077/16/2007ANR
DetailsTom Arcoraci
Please Call 1/2 hour before inspectiion....thanks Phone #: ###-#### Internet Inspection Request from: Ken Litzinger needs all fire stopping and fire stop repairs
BLD-Conference5/30/20075/30/20075/30/2007PPASS
DetailsTom Arcoraci
Please call 1/2 hour before....Thanks, Ken Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Foundation5/18/20075/18/20075/18/2007APASS
DetailsTom Arcoraci
Early inspection if possible..Thnaks Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Footing5/15/20075/16/20075/16/2007APASS
DetailsTom Arcoraci
Please inspect late in the morning if possible...Thanks Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
Telephone call  5/14/2007 DONE
t/c w george mclean at ###-#### - permit ready and fees given
Permit Ready to Issue  5/14/2007 DONE
Issue PAID IN FULL permit  5/14/2007 DONE
Print Occupancy Form  5/11/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/10/2007 DONE
Print Pending Permit.LaserJet4  5/10/2007 DONE
Case Summary (BLD)  5/10/2007 DONE
Routing - PLAN CHECK5/4/2007 5/10/2007 PASS
Plan assigned to (M_P)2/22/2007 5/10/2007 PASS
5/10/2007 15:25:47 M_P - activity updated through activity BLDA022 from case BLD07-00427.
Plan resubmittals received  5/9/2007  
Received 2 copies of pages A3, A4, A5, A9, A12, A13, A14; taken to Mike Phillips
Routing - PLAN CHECK5/3/2007 5/4/2007  
Routing to Planning.
Routing - PLANNING5/4/2007 5/4/2007 PASS
Routing - PLAN CHECK5/2/2007 5/3/2007 FAIL
Second review failed original comments were not answered. Having meeting with the owner and architect on 5/4/07. Additional plans must be submitted for further review prior to issuing permit.
Routing - FIRE5/1/2007 5/2/2007 PASS
Attached updated review comments to plans.
Routing - PLAN CHECK4/30/2007 5/1/2007  
Routing to fire.
Routing - PLUMBING4/27/2007 4/30/2007 PASS
per plans and 2003 upc
Routing - PLANNING4/25/2007 4/27/2007 FAIL
Applicant has no landscape plan in file. Left a message with Ken Litzinger.
Routing - PLANNING Land Div4/25/2007 4/25/2007 PASS
Routing - PLAN CHECK4/5/2007 4/25/2007  
Routing to Land Division.
Plan resubmittals received  4/24/2007  
Received cover transmittal, 2 copies of non-build agreement and 2 copies of the following sheets L-1, A-1, A-2, A-3, A-4, A-5, A-6, A-7, A-8, A-9, A-10, A-11, A-12, A-13, A-14, EN and taken to Mike Phillips
Routing - PLANNING3/30/2007 4/5/2007 FAIL
4/2/07 - Contacted architect about the landscape plans. BLDG set doesn't match conditions of approval.

I have contacted the architect three times and have had to leave messages. There has been no reply.
Routing - PLUMBING3/30/2007 3/30/2007 FAIL
no corrections made
Routing - PLAN CHECK3/21/2007 3/22/2007  
Routing to P.W.
Routing - PUBLIC WORKS3/22/2007 3/22/2007 PASS
1st review completed  3/21/2007 FAIL
Routing - FIRE3/16/2007 3/21/2007 FAIL
Faxed resubmittal items to architect. Attached review comments to plans.
Routing - PLAN CHECK3/7/2007 3/16/2007 FAIL
Plan review complete, sent correction report to the architect requesting additional information to be submitted for further review prior to issuing permit.
Case Summary (BLD)  3/16/2007  
Routing - PLANNING3/5/2007 3/7/2007 FAIL
DRH05-00045 Sarah Schafer, CUP05-00010 Karen Gallagher

Project does not comply with the requirements of the Design Review or the Conditional Use Permit as they pertain to the landscape requirements.
Routing - PLUMBING3/2/2007 3/5/2007 FAIL
complete plumbing plans required on 4 plexs
Routing - Erosion and Sediment3/1/2007 3/2/2007 PASS
ESC plan approved with attached conditions. Refer to ESC06-00304 as master ESC plan for project.
Routing - PUBLIC WORKS2/22/2007 3/1/2007 FAIL
Trash location not acceptable. Enclosure is also too small, interior gate opening must be 11'0". Contact Pam Williams ###-####
Routing - PLANNING Land Div2/22/2007 2/23/2007 PASS
Plans ACCEPTED BY PLAN TECH  2/22/2007  
Plan routing begun/NEW & ADDTN  2/22/2007  
Application received  2/21/2007