Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD07-00571
StatusFinaled
Name THE CHRISTENSEN CORP
Site Address 950 W BANNOCK ST Unit: 520
Project Name10TH & BANNOCK
Customer Number 
ePlanReviewNo
Description
This building is fire sprinklered for high rise. To expand an existing 4,279 square foot office tenant space located on the 5th story of a high-rise building by about 659 square feet. After the expansion, this tenant space will have a total floor area of about 4,938 square feet. Work is to include interior Nordwall demountable nonbearing partitions, doors, and sidelights. The access floor system, the suspended ceilings, and the 1-hr fire-resistance-rated corridor were installed under permit BLD05-02939. The original tenant space was created under permit BLD06-00324. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  11/6/2015 DONE
FIRE-Final Inspection6/17/20106/17/20106/17/2010PPASS
DetailsForrest France
Fire life safety finaled.
Permanent Occupancy  6/17/2010 DONE
Print Occupancy Form  6/17/2010 DONE
BLD-Conference6/10/20106/10/20106/10/2010APASS
DetailsDave Hannah
marva will take care of this
BLD-Aging Inspection6/10/20106/10/20106/10/2010 PASS
DetailsDave Hannah
FIRE-Final Inspection2/1/20102/1/20102/1/2010PPART
DetailsForrest France
Project related fire alarm and sprinkler permits have been finaled.
BLD-Final6/25/20076/26/20076/26/2007APASS
DetailsDave Hannah
STEVE Phone #: ###-#### ok for perm occ
BLD-Final6/11/20076/12/20076/12/2007ANR
DetailsDave Hannah
steve; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
BLD-Framing/Rough-in5/31/20076/4/20076/4/2007APASS
DetailsJim Storey
mario; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
Issue PAID IN FULL permit  4/23/2007 DONE
Plan assigned to (CJW)3/16/2007 4/20/2007 PASS
4/20/2007 10:25:51 CJW - activity updated through activity BLDA022 from case BLD07-00571.
Routing - FIRE4/19/2007 4/20/2007 PASS
Attached review comments to plans.
1st review completed  4/20/2007 PASS
Routing - PLAN CHECK4/20/2007 4/20/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/20/2007 DONE
Print Occupancy Form  4/20/2007 DONE
Telephone call  4/20/2007  
Permit Ready to Issue  4/20/2007 DONE
Routing - PLAN CHECK3/16/2007 4/19/2007 PASS
The IBC plan review was started and finished on April 19, 2007. With the attached plan review report, the drawings were approved.
Routing - PUBLIC WORKS3/16/2007 3/16/2007 PASS
Pending Assignment by MYS3/8/2007 3/16/2007 DONE
3/16/2007 10:05:22 MYS - activity updated through activity BLDA172 from case BLD07-00571.
Plans ACCEPTED BY PLAN TECH  3/8/2007  
Application received  3/7/2007  
Recd Pcfee & Taken To Pln CK  3/7/2007 DONE