Third Notice BLD | 10/1/2007 | 10/1/2007 | 11/9/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/13/2007 | 9/13/2007 | 10/1/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/10/2007 | 9/13/2007 | | DONE |
|
|
|
|
BLD-Final | 8/9/2007 | 8/10/2007 | 8/10/2007 | A | PASS |
Jim Storey
|
|
|
robert - call for access Phone #: ###-####
|
PubWorks Occupancy Approval | 8/10/2007 | 8/10/2007 | 8/10/2007 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 8/10/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 8/9/2007 | | DONE |
|
|
|
Landscaping and other improvements meet BLD 07-00581
|
FIRE-Final Inspection | 8/6/2007 | 8/6/2007 | 8/6/2007 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
BLD-Energy code compliance | 6/25/2007 | 6/25/2007 | 6/25/2007 | P | PASS |
Jim Storey
|
|
|
janet - insulation Phone #: ###-####
|
BLD-Framing/Rough-in | 6/21/2007 | 6/22/2007 | 6/22/2007 | A | PASS |
Jim Storey
|
|
|
janet; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
BLD-Footing | 5/21/2007 | 5/22/2007 | 5/22/2007 | P | PART |
Jim Storey
|
|
|
santos ; Phone #: ###-#### Internet Inspection Request from: Patricia Smithpwoi
|
(F) Reprint permit | | | 5/16/2007 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/10/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/10/2007 | | DONE |
|
|
|
t/c w patrick mckeegan at ###-#### - permit ready and fees given - also need gc name and rce# - rp - and ACHD
|
Permit Ready to Issue | | | 4/10/2007 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 3/9/2007 | | 4/9/2007 | | PASS |
|
|
|
4/9/2007 11:07:29 JCM - activity updated through activity BLDA022 from case BLD07-00581.
|
Routing - FIRE | 4/3/2007 | | 4/9/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 4/9/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/9/2007 | | 4/9/2007 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/9/2007 | | DONE |
|
|
|
|
Routing - PLANNING | 3/27/2007 | | 4/3/2007 | | PASS |
|
|
|
Approved per DRH05-00357 Andrea Tuning. Passed to CR 3-28-07
CUP05-00135-Susan Riggs for Carl Miller. The file is missing from records so we are approving based on Design Review sign-off. Carl Miller was the planner and is no longer with the city.
|
Routing - PLAN CHECK | 4/3/2007 | | 4/3/2007 | | PASS |
|
|
|
John Menard
|
Plan Reviewer's activity | | | 4/3/2007 | | PASS |
|
|
|
Reviewed and approved resubmitted plan sheets.
|
Plan resubmittals received | | | 4/2/2007 | | |
|
|
|
received letter from patrick mekeegan arch & (9 pages) including fax cover sheet & "2" sheets each of A2.1 & A4.1-plans taken to John Menard
|
Routing - PLUMBING | 3/20/2007 | | 3/27/2007 | | PASS |
|
|
|
vent all traps. 1 1/2" min. waste below grade. install premise R.P. over 3" floor sink or install a dcva. mount espresso R.P. over floor sink. additional cross connection protection may be required. 2" cold water to a toilet?
|
Routing - Erosion and Sediment | 3/16/2007 | | 3/20/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals requested | | | 3/19/2007 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PUBLIC WORKS | 3/14/2007 | | 3/16/2007 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 3/9/2007 | | 3/14/2007 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2007 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/9/2007 | | |
|
|
|
|
Pending Assignment by MYS | 3/8/2007 | | 3/9/2007 | | DONE |
|
|
|
3/9/2007 08:36:05 JCM - activity updated through activity BLDA166 from case BLD07-00581.
|
Recd Pcfee & Taken To Pln CK | | | 3/8/2007 | | DONE |
|
|
|
|
Application received | | | 3/8/2007 | | |
|
|
|
|