Second Notice BLD | 1/9/2008 | 1/9/2008 | 1/10/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/26/2007 | 1/9/2008 | | DONE |
|
|
|
|
Meeting | | | 12/28/2007 | | DONE |
|
|
|
Attended meeting with the Applicant, Jenifer, and George Slane the Building Official. Discussed the need for the Fire rated doors to be self closing per 2003 IBC 715.3.7 Fire doors shall be self-closing or automatic-closing per this code section. I stated the code requirement. The Applicant requested a code interpretation from the building official for the closet doors being required to be self-closing due to the failure to correctly close. The descision was made by the Building official to require the doors to have the self closing hardware even though they were not self-closing because of poor design. He stated the walls and ceiling of the closets were a One-hour assembly and would meet the intent of the fire rated assembly for the Entry. (SRZ)
|
BLD-Final | 12/26/2007 | 12/26/2007 | 12/26/2007 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: paul thornton
|
FIRE-Final Inspection | 12/26/2007 | 12/26/2007 | 12/26/2007 | A | PASS |
Troy Cobbley
|
|
|
All repairs corrected per Troys notes. KR
|
Permanent Occupancy | | | 12/26/2007 | | DONE |
|
|
|
|
BLD-Final | 12/21/2007 | 12/21/2007 | 12/21/2007 | P | CANC |
Mike Jordan
|
|
|
paul Phone #: ###-####
|
FIRE-Final Inspection | 12/20/2007 | 12/21/2007 | 12/21/2007 | A | FAIL |
Troy Cobbley
|
|
|
Out of the total 56 doors, of the 6 doors that I tried, only 2 closed/latched completely. One of the general contractors workers became ignorant with me so I stopped the inspection and left. I notified jennifer.
|
Code Occupancy Approval | 12/20/2007 | 12/20/2007 | 12/20/2007 | P | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
FIRE-Final Inspection | 12/19/2007 | 12/20/2007 | 12/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide self closers on all doors in the fire rated wall.
|
BLD-Energy code compliance | 10/5/2007 | 10/5/2007 | 10/5/2007 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 10/4/2007 | 10/5/2007 | 10/5/2007 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: paul thornton
|
BLD-Framing/Rough-in | 10/2/2007 | 10/2/2007 | 10/2/2007 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: paul thornton. Needs to complete firestopping- sprinkler lines and all floor penetrations. Provide squash blocking and additional studs to carry point load from above at lower unit east side, front bedroom. c/n posted. ok to insul.
|
BLD-Other | 8/8/2007 | 8/8/2007 | 8/8/2007 | A | PART |
Mike Jordan
|
|
|
paul - ###-#### - shear . Exterior shear only.
|
Plan resubmittals received | | | 7/20/2007 | | |
|
|
|
Received two copies of pages A2.0, A2.1, A4.0; taken to Marlene
|
Plan resubmittals received | | | 7/18/2007 | | |
|
|
|
Revieved two copies of page A4.0; taken to Marlene S.
|
Plan resubmittals received | | | 7/17/2007 | | |
|
|
|
Per Marlene ok to taken in as resubs; Received two copies of pages A2.0, A2.1, A4.0, S2.0, S3.0; taken to Marlene S.
|
BLD-Other | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PART |
Mike Jordan
|
|
|
paul - look at blue board for inspection Phone #: ###-####. Rigid foam insul.
|
BLD-Other | 6/26/2007 | 6/27/2007 | 6/27/2007 | A | PART |
Mike Jordan
|
|
|
a look at the blueboard Phone #: ###-#### Internet Inspection Request from: paul thornton. rigid foam insul at stemwall.
|
BLD-Foundation | 6/19/2007 | 6/20/2007 | 6/20/2007 | P | PART |
Mike Jordan
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
BLD-Footing | 6/18/2007 | 6/19/2007 | 6/19/2007 | P | PASS |
Mike Jordan
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
Issue PAID IN FULL permit | | | 6/12/2007 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/8/2007 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/8/2007 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/14/2007 | 3/14/2007 | 6/7/2007 | | PASS |
|
|
|
6/7/2007 16:44:37 MYS - activity updated through activity BLDA022 from case BLD07-00608.
|
Routing - PLAN CHECK | 6/4/2007 | | 6/7/2007 | | PASS |
|
|
|
Waiting for parcel numbers. Sub recorded on 6/4/2007.
Received parcel number on 6/7/2007 and prepared for issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2007 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 6/4/2007 | | 6/4/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/14/2007 | | 5/31/2007 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/11/2007 | | 5/24/2007 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Routing - PLAN CHECK | 5/24/2007 | | 5/24/2007 | | |
|
|
|
Routing to P.W.
|
Routing - PUBLIC WORKS | 5/24/2007 | | 5/24/2007 | | FAIL |
|
|
|
See solid waste notes
|
Plan resubmittals received | | | 5/18/2007 | | |
|
|
|
received letter from houston bugatsch arch(5) pages & 1 letter from houston bugatsch arch & (2) sets of plans with each sheet A1.O, A1.1, A2.O, A2.1, A4.O, & E1.1--plans taken to Mike Phillips
|
Routing - PUBLIC WORKS | 5/9/2007 | | 5/11/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 4/20/2007 | | 5/9/2007 | | FAIL |
|
|
|
Second review failed, called architect and requested additional details to be submitted to reflect a rated assembly for the corridor/stairs.
|
Routing - PLANNING | 4/16/2007 | | 4/20/2007 | | PASS |
|
|
|
(AW delegated plans today b/c SAR out sick)
Bld07-599, 602, 606, 607, 608, 609, 610, 611..
Mike Phillips rtd. to planning 4/16 b/c the computer indicated pass but the plans did not have a pass signature.
|
Routing - PLAN CHECK | 4/10/2007 | | 4/16/2007 | | |
|
|
|
Routing to Planning
|
Routing - PLANNING | 4/13/2007 | | 4/13/2007 | | PASS |
|
|
|
|
Routing - FIRE | 4/5/2007 | | 4/10/2007 | | PASS |
|
|
|
Attached review comments to plans.
|
1st review completed | | | 4/10/2007 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 4/3/2007 | | 4/5/2007 | | FAIL |
|
|
|
Sent correction report to the architect, requesting additional information to be submitted for further review prior to issuing permit.
|
Routing - PLANNING | 3/30/2007 | | 4/3/2007 | | FAIL |
|
|
|
CUP05-00056- Susan Riggs/waiting for croass access agreement
Approved per DRH07-00082- Greg Johnson
|
Routing - PLUMBING | 3/20/2007 | | 3/30/2007 | | PASS |
|
|
|
see bld07-00599
|
Routing - Erosion and Sediment | 3/19/2007 | | 3/20/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions. Refer to ESC07-00288 as master ESC plan for project.
|
Routing - PLANNING Land Div | 3/14/2007 | | 3/14/2007 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/14/2007 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/13/2007 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/13/2007 | | |
|
|
|
|
Application received | | | 3/9/2007 | | |
|
|
|
|