BLD-Final | 1/17/2008 | 1/18/2008 | 1/19/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/17/2008 at 6:33:15 PM. Contact: ###-####.
|
DOC - Permit Finaled | 1/19/2008 | 1/19/2008 | 1/19/2008 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 1/11/2008 | 1/14/2008 | 1/15/2008 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/11/2008 at 5:18:25 PM. Contact: ###-####. needs fire sprinkler final and temp glass at side door and bathrooms
|
BLD-Final | 1/10/2008 | 1/11/2008 | 1/11/2008 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/10/2008 at 5:06:51 PM. Contact: ###-####. Need P/W and Fire finals.
|
BLD-Grading Inspection | 1/10/2008 | 1/10/2008 | 1/10/2008 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/19/2007 at 5:14:51 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/13/2007 | 9/13/2007 | 9/14/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/12/2007 at 4:45:54 PM. Contact: ###-####. ok to insulate after fire sprinckler oks
|
BLD-Framing/Rough-in | 9/12/2007 | 9/13/2007 | 9/13/2007 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/12/2007 at 4:45:54 PM. Contact: ###-####. no plans or truss eng on site
|
BLD-Framing/Rough-in | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | FAIL |
Mike Jordan
|
|
|
mike - exterior nailing Phone #: ###-####. Interior shear walls not completed. Noted to framing contractor that interior shear walls need to be continous to cripple walls below with mstc strap in place of holdown as per approved plans. (detail 22, S1) Install floor to floor straps from 1st floor to 2nd floor. c/n posted.
|
Case Summary (BLD) | | | 8/8/2007 | | DONE |
|
|
|
|
BLD-Foundation | 6/11/2007 | 6/11/2007 | 6/11/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/11/2007 at 11:18:10 AM. Contact: ###-####.
|
BLD-Footing | 6/4/2007 | 6/4/2007 | 6/4/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/4/2007 at 7:22:36 AM. Contact: ###-####.
|
PubWorks Subgrade Approval | 6/4/2007 | 6/4/2007 | 6/4/2007 | | DONE |
|
|
|
footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 5/17/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 5/1/2007 | | DONE |
|
|
|
|
Telephone call | | | 5/1/2007 | | |
|
|
|
Called let Sharon, know permit ready and fee given
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2007 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/30/2007 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/30/2007 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 4/16/2007 | | 4/30/2007 | | DONE |
|
|
|
Reviewed revised set of plans and all corrections were made/ plans are ok.
|
Routing - PLAN CHECK | 4/9/2007 | | 4/30/2007 | | PASS |
|
|
|
Reviewed revised set of plans and all corrections were made/ plans are ok.
|
Telephone call | | | 4/27/2007 | | DONE |
|
|
|
Mike Henry has called on the 24, 25, 26, and 27 of Aril 2007 asking if I have recieved the resubmittals from his builder/designer. I informed him I have not and he seems to be getting very frustrated. I have made curtousy calls to Dale Behrman to inform him of my conversations with Mike Carey and have not got an answer in my 3 attempts to call. TLW
|
Plan resubmittals received | | | 4/27/2007 | | |
|
|
|
Dale Behrman delivered resubmittals as requested. TLW
|
Pending Assignment by SRZ | 3/16/2007 | | 4/16/2007 | | DONE |
|
|
|
4/16/2007 15:41:58 TLW - activity updated through activity BLDA185 from case BLD07-00666.
|
Plan resubmittals requested | | | 4/16/2007 | | DONE |
|
|
|
Called Todd Henry from Media one left message to call me back need new plans from him to proceed with plan review. TLW
|
Telephone call | | | 4/12/2007 | | |
|
|
|
Called Kim Rost, was informed that roof pitch is changeing and will need all new calcs. for building. Also went over redlines I had need new foundation page and calcs. to proceed. TLW
|
Routing - FIRE | 4/3/2007 | | 4/9/2007 | | PASS |
|
|
|
This house requires a modified NFPA 13D fire sprinkler system; in addition the the requirements of NFPA 13D, sprinklers shall be installed in all closets, baths and garages. (Boulder Heights Estates Sub #1)
|
Routing - Erosion and Sediment | 4/2/2007 | | 4/3/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 3/16/2007 | | 4/2/2007 | | PASS |
|
|
|
Before final approval is granted a letter is required for work on neighbor's property to the east.
|
Routing - Addressing | 3/16/2007 | | 3/16/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2007 | | 3/16/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 3/16/2007 | | 3/16/2007 | | PASS |
|
|
|
Approved as Category 1 by CFH07-00007 (Josh Johnson)
|
Application received | | | 3/16/2007 | | |
|
|
|
|