BLD-Final | 5/13/2008 | 5/14/2008 | 5/14/2008 | A | PASS |
Mike Jordan
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
DOC - Permit Finaled | 5/14/2008 | 5/14/2008 | 5/14/2008 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/12/2008 | 5/13/2008 | 5/13/2008 | P | FAIL |
Dave Hannah
|
|
|
mike Phone #: ###-#### c/n on site close risers to4inh max on spiral stairs gaurd rail on back deck needsmore suport and close up west end
|
BLD-Grading Inspection | 5/13/2008 | 5/13/2008 | 5/13/2008 | A | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Framing/Rough-in | 1/30/2008 | 1/31/2008 | 1/31/2008 | A | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-#### stair stringer and connection engineering on and instilled ok to cover
|
BLD-Energy code compliance | 1/9/2008 | 1/10/2008 | 1/14/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/9/2008 at 4:29:14 PM. Contact: ###-####.ok to cover after fire place r/is are completed
|
BLD-Framing/Rough-in | 12/27/2007 | 12/28/2007 | 12/31/2007 | A | PART |
Dave Hannah
|
|
|
mike Phone #: ###-#### ok to insukate walked project with framer needs to finish fire blocking also needs to finish fire places and get rough ins
|
BLD-Other | 11/28/2007 | 11/29/2007 | 11/29/2007 | A | PART |
Mike Jordan
|
|
|
mike Note: shear nailing Phone #: ###-####. Exterior shear nailing, and holdowns only.
|
BLD-Foundation | 7/31/2007 | 8/1/2007 | 8/2/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/31/2007 at 3:22:01 PM. Contact: ###-####.
|
PubWorks Subgrade Approval | 8/1/2007 | 8/1/2007 | 8/1/2007 | | DONE |
|
|
|
Crawl space footings approved by the geotechnical engineer
|
BLD-Footing | 7/16/2007 | 7/16/2007 | 7/16/2007 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/16/2007 at 7:22:42 AM. Contact: ###-####.
|
BLD-Foundation | 7/16/2007 | 7/16/2007 | 7/16/2007 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/16/2007 at 7:22:42 AM. Contact: ###-####.
|
BLD-Footing | 7/5/2007 | 7/6/2007 | 7/6/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/5/2007 at 11:22:33 AM. Contact: ###-####.
|
BLD-Footing | 6/28/2007 | 6/28/2007 | 6/28/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/28/2007 at 10:27:10 AM. Contact: ###-####.
|
BLD-Footing | 6/27/2007 | 6/28/2007 | 6/28/2007 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/27/2007 at 3:22:39 PM. Contact: ###-####.
|
PubWorks Subgrade Approval | 6/28/2007 | 6/28/2007 | 6/28/2007 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 5/15/2007 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/16/2007 | | DONE |
|
|
|
|
Telephone call | | | 4/16/2007 | | DONE |
|
|
|
left vm for behrman homes - permit ready and fees given
|
Permit Ready to Issue | | | 4/16/2007 | | |
|
|
|
|
Plan assigned to (SRZ) | 4/12/2007 | 4/12/2007 | 4/13/2007 | | PASS |
|
|
|
4/13/2007 16:04:06 SRZ - activity updated through activity BLDA022 from case BLD07-00724.
|
Case Summary (BLD) | | | 4/13/2007 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/27/2007 | | 4/13/2007 | | PASS |
|
|
|
|
Pending Assignment by SRZ | 4/12/2007 | | 4/12/2007 | | DONE |
|
|
|
4/12/2007 14:32:51 SRZ - activity updated through activity BLDA160 from case BLD07-00724.
|
Routing - Erosion and Sediment | 3/26/2007 | | 3/27/2007 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 3/27/2007 | | 3/27/2007 | | PASS |
|
|
|
No fire sprinklers required (Nativa Terrace Block 3, Lot 23)
|
Routing - PLANNING | 3/22/2007 | | 3/26/2007 | | PASS |
|
|
|
Routed to Diane 3/23/07 CHF07-00013
|
Routing - PUBLIC WORKS | 3/22/2007 | | 3/22/2007 | | PASS |
|
|
|
|
Routing - Addressing | 3/21/2007 | | 3/22/2007 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 3/22/2007 | | 3/22/2007 | | PASS |
|
|
|
Approved as Category 1 by CFH07-00013
|
Application received | | | 3/21/2007 | | |
|
|
|
|